project manager
SHL
Total years of experience :4 years, 8 Months
Project :A project to rehabilitate educational buildings in the Medina region G2
SCOPE OF WORK: Rehabilitation and restoration of 12 schools in the Medina region, including all architectural, structural, mechanical, electrical, and firefighting and alarm system finishing works.
RESPONSIBILITIES:Planning and coordination:
Hold meetings with key stakeholders (e.g. Ministry of Education, Madinah Education Department, contractors, local community) to understand project requirements and expectations.
Develop a comprehensive project plan that includes goals, tasks, timelines, budget, and scope of work.
Obtaining all necessary permits and approvals from the relevant government agencies. Preparing tender documents and managing the process of selecting the appropriate contractor.
Communication and management:
Create an effective communication plan to facilitate communication between all stakeholders involved in the project.
Managing the work team and assigning tasks and responsibilities to each member. Monitor work progress periodically and submit reports to stakeholders.
Resolve any problems or challenges that arise during the workflow.
During project implementation:
Site Administration:
Supervising all construction activities and ensuring their compliance with applicable specifications and standards.
Manage site safety and ensure all occupational safety and health procedures are followed. Coordinating with contractors and suppliers to ensure that materials and services are delivered on time and according to the required specifications.
Resolving any disputes or disagreements that arise between the project parties.
Budget control:
Carefully monitor project expenses and ensure adherence to the specified budget. Preparing periodic financial reports and informing stakeholders of any changes in costs. Look for opportunities to save money without compromising the quality of work.
After completing the project:
Delivery and inspection:
Ensure all work is completed according to specified specifications.
Conducting a final inspection of the buildings to ensure their safety and suitability for use. Handing over the buildings to the Ministry of Education or the Education Department in Medina.
Evaluation and documentation:
Evaluate project success and identify lessons learned.
Oct 2023 - Present
Preparing final project documents that include all relevant information. Archive all project records and facilitate future access
PROJECT: THE NATIONAL BANK OF SAUDI ARABIA, AL‐NASIM DISTRICT BRANCH AND AL‐WISAM DISTRICT BRANCH IN TAIF
SCOPE OF WORK CONSTRUCTING AN CONSTRUCTION BUILDING ON THE GROUND FLOOR, FINISHING IT, AND HANDING IT OVER TO THE MANAGEMENT OF THE NATIONAL BANK RESPONSIBILITIES:Coordination and preparation:
Holding meetings with representatives of the National Bank of Saudi Arabia to understand their requirements and expectations from the project.
Review project documents, including plans, designs, and budget.
Develop a comprehensive work plan that defines the tasks and responsibilities of the consulting office and a timetable for the project.
Select a qualified team of engineers and experts with experience in the field of construction. Obtaining all necessary permits and approvals from the relevant government agencies. During project implementation:
project management:
Supervising all phases of the project, from planning and design to implementation and delivery.
Monitor work progress periodically and submit regular reports to the Saudi National Bank. Managing the work team and assigning tasks and responsibilities to each member. Resolve any problems or challenges that arise during the workflow.
Communication and management:
Create an effective communication plan to facilitate communication between all project parties.
Holding periodic meetings with representatives of the National Bank of Saudi Arabia, contractors and suppliers.
Sep 2021 - Oct 2023
Manage strong relationships with all stakeholders involved in the project.
Cost control:
Carefully monitor project expenses and ensure adherence to the specified budget. Preparing periodic financial reports and informing the Saudi National Bank of any changes in costs.
Look for opportunities to save money without compromising the quality of work. After completing the project:
Delivery and inspection:
Ensure all work is completed according to specified specifications.
Conduct a final inspection of the building to ensure its safety and suitability for use. Handing over the building to the National Bank of Saudi Arabia.
Evaluation and documentation:
Evaluate project success and identify lessons learned.
Preparing final project documents that include all relevant information.
Archive all project records and facilitate future access.
PROJECT: EXPANSION OF THE TRIPLE ARAR WATER PURIFICATION PLANTSCOPE OF WORK: IMPLEMENTATION OF THE THIRD EXPANSION OF THE STATION FROM THE CONSTRUCTION OF THE RAW WATER TANK, THE R.O BUILDING, THE AIR BLOWER BUILDING, THE CONTROL BUILDING, THE COOLING TANKS, THE WORKERS’ BUILDING, THE IMPLEMENTATION OF THE ROAD NETWORK AND THE INTERNAL PIPE NETWORK OF THE STATIONRESPONSIBILITIES:A SITE ENGINEER TO CARRY OUT
THE CONSTRUCTION WORKS INSIDE THE STATION, INCLUDING TANKS, ISOLATING THE TANKS AFTER CONSTRUCTION, TESTING THEM, HANDING THEMOVER TO THE CONSULTANT, FOLLOWING UP THE PROJECT WITH THE PROJECT MANAGERON A SCHEDULE, MAKING RECEIPT REPORTS, FOLLOWING UP ON THE SUBCONTRACTOR RESPONSIBLE FOR IMPLEMENTATION, MAKING THE ROAD NETWORK AND THE PIPE NETWORK CONNECTING BETWEEN THE TANKS, AND FINISHING WORKS
PROJECT: SANITARY NETWORK IN YANBU AL‐BAHRSCOPE OF WORK INSTALLING THE SEWERAGE NETWORK OF YANBU EL BAHER CITY RESPONSIBILITIES:EXECUTING SURVEYING OF THE DRAINAGE NETWORK, DETERMINING THE LEVEL OFEXPOSED EXCAVATION, INSTALLING 6‐INCH FIBERGLASS PIPES, INSTALLING MANHOLES AND BACKFILLING, THEN CONDUCTING TESTS FOR THE LINES, REVIEWING THE DIFFICULTIES WITH THE CONSULTANT, MAKING REPORTS, AND ASSISTING THE PROJECT MANAGER IN THE TECHNICAL
OFFICEAND SUPERVISING THE SUBCONTRACTOR, THE SAUDI TUNNELS COMPANY, TO IMPLEMENT THE WORKS OF MICRO TUNNELING, MAKING MANHOLES, INSTALLING PIPES OF DIAMETER 800 MM, HANDING THEM OVER TO THE CONSULTANT, BACKFILLING, THEN THE ASPHALT PROCESS, FINISHING THE MANHOLES AND TESTING THEM.