إمام irtiyantoko, Electrical Engineering

إمام irtiyantoko

Electrical Engineering

Bumi Suksesindo - Gold Mine

البلد
إندونيسيا
التعليم
بكالوريوس, Electrical Engineering
الخبرات
23 years, 4 أشهر

مشاركة سيرتي الذاتية

حظر المستخدم


الخبرة العملية

مجموع سنوات الخبرة :23 years, 4 أشهر

Electrical Engineering في Bumi Suksesindo - Gold Mine
  • إندونيسيا
  • أشغل هذه الوظيفة منذ نوفمبر 2017
Electrical Site Engineer في IMK Gold Mine
  • إندونيسيا
  • نوفمبر 2016 إلى أكتوبر 2017
site engineer في pt. Bramindra Indotama
  • إندونيسيا
  • مارس 2015 إلى أكتوبر 2016

support construction activity engineering design

Site - Electrical & Instrumentation project engineer في Cargill
  • إندونيسيا
  • أغسطس 2013 إلى فبراير 2015

e. Job Description :
• Coordinate construction activity of E&I contractors
• Setting out the works in accordance with the drawings and specification
• Conduct regular briefing with site team to follow-up and report on the work progress in order to anticipate any possible delays with regards to planned tasks.
• Provide Technical Support to other site team members
• Conduct regular meetings with project team, consultants and contractor to solve technical issues and other related matters
• Evaluate and resolve any discrepancies and problems arising during construction which affect the quality of works performed
• Enforce the relevant safety regulation and implementation.
• Conduct regular inspections and assess the work performance done by E/I contractors and subcontractor.
• Coordinate site test and inspection: grounding system, lighting system, cable tray and layout, lightning protection, cable insulation, motor, etc.
• Support the site activities including Pre-commissioning / commissioning;
• Support Electrical Equipment installation, test and commissioning of:
8 Cells 8DJH Gas insulated Switchgear by Siemens
3x1600 kVA and 2x 2000kVA Geafol dry type transformer by Siemens
2 panel main switch board LV distribution by Schneider
3 panels Sivacon LV Switchgear/MCC withdrawable by Siemens
3 panels Sinamic Inverter / variable speed drive by Siemens
7 panels 300kVAR Capacitor bank
• Coordinate and support equipment package installation, E/I test and commissioning of:
Natural Gas Steam Boiler by Vyncke Forbes Marshall
Chilled glycol & water Compressor, AHU, Cooling tower by Johnson Control
Air Compressed System by Kaesar
Deodorizer Plant by Desmet
Waste Water Treatment Plant by Nijhuis
Raw Water Treatment Plant by HatenboerWater
Fire sprinkler system by Gunnebo
Fire alarm system by Siemens and Notifier.

Electrical Engineer في ENERKON - SUCOFINDO Join operation for PMC
  • إندونيسيا
  • نوفمبر 2012 إلى أغسطس 2013

Project Management Consultancy for Indonesian State Gas Company (PGN) project Muara Bekasi Upgrade - Sumatera Jawa Transmission.

Engineering Assessment - Gas Turbine Power Plant (Simple Cycle) with future expansion to Combined Cycle

Review main contractor job progress for engineering procure and construction stage.
• Assessment for Electrical Design Engineering for preparation of commissioing / start-up and preparation of engineering document handover to Client.
• Commissioing Support for Electrical System.
• Electrical support for O & M preparation
• Develop conceptual and basic design.
• Develop preliminary cost - time estimates of project
• Provide Engineering data, Engineering Calculation, Equipment Specifications, Equipment Data Sheet, RFQ, MTO
• Develop drawings including the preparation of: Single Line Diagrams, Schematic Diagrams, Cable Schedules, Interconnection
• Schedules, Equipment / Cable Routing / Tray Lay-out Drawings, Grounding System Lay-out and Details, Installation Standard Drawings

Electrical Engineer في British American Tobacco
  • إندونيسيا
  • نوفمبر 2011 إلى أكتوبر 2012

Handling project upgrading capacity of utility and production.

Electrical Engineer في Indonesian Services Bureau affiliate ZEE Engineering
  • إندونيسيا
  • يناير 2011 إلى نوفمبر 2011

Responsibilities included:
 Develop concept and basic design.
 Initiates major equipment specifications inquiries.
 Liaise approve alternative proposals with the other discipline engineers.
 Provide preliminary cost estimation.
 Provide deliverable: Engineering Calculation, Equipment Specifications, Equipment Data Sheet, Tender Bid Evaluation, Equipment RFQ, MTO and Drawing.
 Develop detailed drawings including the preparation of: Single Line Diagrams, Schematic Diagrams, Cable Schedules, Interconnection Schedules, Equipment / Cable Routing / Tray Lay-out Drawings, Grounding System Lay-out and Details, Installation Standard Drawings

Electrical & Instrument Planner (Turn a round project) في Cegelec for BP Tangguh LNG
  • إندونيسيا
  • سبتمبر 2010 إلى ديسمبر 2010

Responsibilities included:
 Scope the full extent of maintenance work needed to conduct the relevant repair / preventive / predictive / design-out activities on the organization’s plant and equipment.
 Write applicable maintenance procedures that promote defect-free maintenance work quality Plans, administers and coordinates multiple, special projects; organizes and employs resources to achieve project objectives; prepares and monitors project material.
 Develop work pack for electrical and instrument preventive maintenance
 Develop cost and time estimates of planned maintenance work
 Purchase all necessary parts, equipment, services and documentation to perform the maintenance work

Electrical Engineer - Engineering Services في VALEINCO "was INCO Ltd" (Nickel)
  • إندونيسيا
  • أغسطس 2006 إلى أغسطس 2010

Responsibilities included:

Basic Engineering stages:
 Develops the proposed project scope and alternative project .
 Develop concept and basic design.
 Initiates major equipment specifications inquiries.
 Liaise approve alternative proposals with the other discipline engineers.
 Provide preliminary cost estimation.
 Considers the Constructability, Maintainability and Operability for each of the proposed alternatives scopes.
 Participates in the HAZOP sessions.
Detailed Engineering stages:
 Provide material specifications, Materials Requisition, Bill of Materials documents
 Generate new drawings as required for the project & mark-up existing drawings to reflect the new design.
 Develop detailed engineering calculations, cable sizing and drawings including the preparation of: Single Line Diagrams, Schematic Diagrams, Cable Schedules, Interconnection Schedules, Equipment Lay-outs, Cable Routing and Lay-out Drawings, Cable Trench/Tray Lay-out Drawings, Grounding System Lay-out and Details, Installation Standard Drawings
 Produce Engineering Work Package
Construction stages:
 Field inspection periodically to ensure work is technically being performed in accordance with EWP requirements.
 Pre-commissioning of all installed equipment and completion of any deficiencies.
 Resolve any inter discipline related construction problems.
 Ensure the construction is being installed to meet the completion dates.
 Ensure the Q/A (Quality Assurance) requirements are implemented.
 Reviewing of the Contractor/Consultant measurement of progress of work.

Commissioning and Hand-over stages:
 Ensure all tests and documentation is complete.
 Provide commissioning procedures & ensure correct procedures are carried out during energizing equipment.
 Carry out test running of all equipment.
 Carry out full performance checks of the project systems.
 Ensure any changes to the original design are effected on the construction “As-built” drawings.

Technical Service Engineer في Molindo Inti Gas
  • إندونيسيا
  • يوليو 2004 إلى يونيو 2006

Responsibilities included:

 responding to customer call-outs;
 evaluating and resolving problems;
 assisting with the installation of equipment;
 liaising with and working alongside technical sales engineers;
 offering customer training;
 repairing, testing and maintaining equipment;
 monitoring the performance of products;
 maintaining manuals;
 providing customers with regular reports and feedback on their service requests;
 developing and maintaining relationships with customers;
 making recommendations to maintenance technicians;
 offering feedback on future product development, features and functions

Maintenance Engineer في Kinerja Sejahtera
  • إندونيسيا
  • فبراير 2004 إلى يونيو 2004

Responsibilities included:

 designing maintenance strategies, procedures and methods;
 planning and scheduling planned and unplanned work;
 diagnosing breakdown problems;
 directing, instructing and supervising maintenance technicians and fitters;
 liaising with client departments and customers;
 controlling maintenance tools, stores and equipment;
 monitoring and controlling maintenance costs;

Maintenance Technician في Surya Abadi
  • إندونيسيا
  • نوفمبر 2002 إلى ديسمبر 2003

Responsibilities included:

 Perform routine maintenance program;
 planning and scheduling planned and unplanned work;
 diagnosing breakdown problems;
 perform fault analysis and preventive program

QC Engineer في Schneider Electric
  • إندونيسيا
  • أغسطس 2000 إلى يوليو 2002

Responsibilities included:

 To ensure that the product fulfils or exceeds customer expectations.
 Make sure the product functionality meets the needs of the clients.
 Create and test the applications ensuring they accomplish with quality standard product.
 Perform vendor quality audit.
 Manage the measuring equipment calibration program.
 Manage and follow up vendor quality problem.

الخلفية التعليمية

بكالوريوس, Electrical Engineering
  • في Brawijaya University
  • فبراير 2000

GPA: 3.01 out of 4. Activity was as laboratory assistant for electrical machinery. Member of Elect

Specialties & Skills

Electrical Engineering
Electrical Safety
Project Engineering
Project Estimation
Electrical Design
Lighting Calculation
Ms Office
electrical design drawing and calculation
electrical engineering design

اللغات

الانجليزية
متوسط

الهوايات

  • Travelling and backpacker