To lead and manage the instrumentation and electrical project’s groups/teams, ensuring that project
activities are properly planned, engineered and carried out on schedule and within approved budget
* Supervise and control all the activities regarding installation, termination, calibration, testing and
commissioning of field instrument, PLC, MCC and Switch gear
* Construction and progress Control of electrical & instrumentation construction activities.
* Analyzing, understanding and solving execution problems of Engineering
* To provide technical support to execution team about scope of work and field side activities also
make the execution and shutdown/turnaround plans for jobs.
* Managing all project cost effective & optimize the execution within defined time frame & allocated
budget
* Kick-off meetings with client to understand project scope of work and arrange manpower and
equipment accordingly and timely
* Conducting meetings with sub-contractors to review their readiness and progress
PROJECTS
North Jeddah Bulk Plant Vapor Recovery Unit (SAUDI ARAMCO)
This project will install an activated carbon vapor recovery unit at the above mentioned Bulk Plant which
will avoid releasing volatile organic compounds directly into the environment.
* Procurement of Power, control cables, instrument and FOC cable
* Arranging inspections for ARAMCO supplied material
* Arranging and witness 3rd
party testing for Switch Rack, FOC cable and instruments
* Daily and weekly meetings with client and sub-contractors
PROJECTS
JRD Substation Installation (SAUDI ARAMCO)
Project to replace the existing obsolete switchgears and MCC’s at Jeddah Refinery Substations and MCC
rooms with new metal clad switchgears, control gears and outdoor switch racks
* Procurement of Power and control cables
* Procurement of Breakers, over load relays, contactors and their accessories from EATON
* Procurement of Breakers, over load relays, contactors and their accessories from GE
* Daily and weekly meetings with client and sub-contractors
* Witness for third party testing for MCC panels and switch rack
* Arranging and maintaining site facilities
* Planning for daily execution
* Adjusting a projects priorities and milestones based upon client changing needs, resource
availability, and job requirements
* Communicating with client for shutdowns and taking dates for the same
* Ensure material availability before starting shutdown
* Preparing method statement for shutdown activities
* Red markup for any field change
* Ensuring that all Health & Safety processes and procedures are followed
* Assessment of contractor’s project Bi-weekly report and ensuring that the project activities are
being carried out according to the submitted over all schedule programs
Relocation of Beacons & Horns of the GDS @ JR (SAUDI ARAMCO)
Relocation of Beacons and Horns at 12 No’s of different location and installation of new once to cover the
necessary areas of Jeddah Refinery
* Coordinating the procurement of Cables, conduit and conduit fittings
* Mentoring junior members of the project team
* Ensuring the smooth integration of new installation
* Ensure daily and weekly tool box talk
* Method statement for relocation and new installation work
* Communicating with Emergency response department (ERD) of JRD
* Planning for active Beacons and Horns shutdown with ERD of JRD
* Carrying out site surveys and visits
* Witness for PLC programming (Allen Bradly)
* Assistance for commissioning and pre-commissioning activities
Modification of Debutanizer/Amine Treating/LPG Blender (RP3); Petro Rabigh
* Witness the overhauling & testing of control valve, includes below
1. Before overhauling seat leak test
2. After overhauling seat leak test
3. After overhauling body/Shell leak test
4. Ensuring the calibration with all accessories & actuator leak tests
Olifin-1 ESD upgrade of YANPET (SABIC)
Project to replace 12 heater interlock system by new TMR ESD system & implement 2oo3 transmitter for
each safety function and existing final control element are to be provided with 2oo2 SOVs
* Procurement of instrument, control & fiber optic cables
* Procurement of all bulk material (all types & sizes of conduit with fittings)
* OTDR testing prior to FO cable laying
* New JB Ex”e” (28 no.) procurement & installation with hook up
* New field instruments PT, LT, TT, LT, SOVs (350 No.) installation with hook up
* New ESD (PLC panel) installation in SIH with termination
* Pre-commissioning & commissioning assistance
Deep Dive Instrument Upgrade in Turnaround (2014) of YANPET (SABIC)
* Procurement of all type of lead instrument (PT, extension cables) & bulk material
* Conduit installation for homerun and secondary cables
* Installation of proximity JB for new proximity sensors
* ESD panel installation with new safety barrier installation
* Cabling for all JBs, ESD and Marshaling cabinet with termination and loop checking
* Assistance for testing & commissioning
MV cable laying & jointing in YANSAB (SABIC)
* Removal/back pulling of existing MV cable 300mm2 (Led Shielded Armored)
* New MV cable laying/pulling of same specs between two substations
* Splicing/Jointing of new cable at various lengths
* Assistance Hi-pot testing after laying and jointing
Over hauling and calibration of PSV in Turnaround (2013) of SAMREF
* Overhauling of PSVs
* Calibration of these as per provided data sheets
* Testing of calibrated PSV and inspection
PROJECT
Company: Kum Yang Engineering Company; KSA
Position: E&I engineer
Client: WASIT GAS Project ARAMCO (January 2013 to August 2013)
* Working out the manpower requirements for the project
* Planning and scheduling resources to meet project goals
* To lead and manage the instrumentation and electrical project’s groups/teams, ensuring that project
activities are properly planned, engineered and carried out on schedule and within given time frame
* Ensure proper cable tray installation for both electrical and instrument cables
* Ensure correct type and size of E&I cable pulling
* Witness for all instrument testing and calibration inspection
* To provide technical support to execution team about scope of work and field side activities.
* Ensure availability of major and bulk material required for execution team
PROJECT
- Company industry:
- General Engineering Consultancy
- Job role:
-
Engineering