Jomo Peter, Senior Planning Engineer

Jomo Peter

Senior Planning Engineer

KAD Construction LLC

البلد
الإمارات العربية المتحدة - دبي
التعليم
ماجستير, Construction Technology & Management
الخبرات
12 years, 8 أشهر

مشاركة سيرتي الذاتية

حظر المستخدم


الخبرة العملية

مجموع سنوات الخبرة :12 years, 8 أشهر

Senior Planning Engineer في KAD Construction LLC
  • الإمارات العربية المتحدة - دبي
  • أشغل هذه الوظيفة منذ أغسطس 2017

PROJECT : MBR - DUBAI HILLS ESTATE PACKAGE 45: PA-04 GRADING, ROADS, SHALLOW AND DEEP SERVICES DUBAI, UAE
EMPLOYER : EMAAR PROPERTIES
PMC : ELLIS DON
CONSULTANT : JACOBS
PROJECT BUDGET : AED 150 MILLION
Construction of Infrastructure and Road works for the project which includes the following items of works Sewerage Network, Stormwater Drainage Network, Potable water Network, Irrigation Network, Fire Fighting Network, Road Crossing Ducts, Electrical LV Network, Electrical HV Network, Telecommunication Network, Emaar IT Network, Spare Ducts, Street Lighting Network, Road works, Pavement works, Tie-in Connections, Construction of Pumping Station, Pocket Substation.

PROJECT : DESIGN AND CONSTRUCTION OF INFRASTRUCTURE DUBAI MARITIME CITY - PHASE 1 COMMERCIAL DISTRICT, DUBAI, UAE
EMPLOYER : DUBAI MARITIME CITY (DP WORLD)
CONSULTANT : KHATIB & ALAMI
PROJECT BUDGET : AED 250 MILLION
Construction of Infrastructure and Road works for the project which includes the following items of works Sewerage Network, Stormwater Drainage Network, Fire Fighting Network, Potable water Network, Irrigation Network, NDRC Works, Road Crossing Ducts, Electrical LV Network, Electrical HV Network, Telecommunication Network, Spare Ducts, Smart City System, Street Lighting Network, Road works, Pavement works, Tie-in Connections, Construction of Pumping Station, Pocket Substation, Lifting Station, Outfall Structure.

DUTIES AND RESPONSIBILITIES:
1. Preparation of Clause14.1/8.3 Baseline/Contract Programme
2. Performed Cost Loading and Resource loading
3. Prepared Manpower Histogram, Cash Flow, Progress S curve, Procurement Schedule etc.
4. Prepared KPI’s for accurately monitoring the Key items/trades.
5. Prepared Updated Programme weekly
6. Prepared Internal and External Monthly Report
7. Prepared Internal and External Weekly Reports
8. Identifying the Delay Events from Client, Consultant and Subcontractors and drafting delay claim notices
9. Drafting all correspondence of related to delays such as Delay Claim Notices, interims and Final Claim Notice.
10. Prepared Extension of Time Claims using the Time Impact Analysis method and Window Analysis Method.
11. Monitored daily site activities, critical activities, resources (manpower, machinery and materials), shop drawing approval, material approval and procurement activities if any concerns or flag to be raised.
12. Preparation of recovery schedules in case the project is running behind the approved program of works to mitigate any delays.
13. Coordination with Project Team, Client, Consultant and Subcontractors.
14. Coordinate and integrate subcontractors with the programme and ensure compliance with the programme requirements.
15. Report to the Project Manager about the current work progress and make a comparison between the plan and actual progress and study impact of alternative approaches to work.
16. Preparation of look-ahead schedules & supply information to respective departments for timely availability of resources on the site.
17. Attend Progress, Site walk and other relevant Meetings as advised by the Project Manager.
18. Performs other duties and responsibilities as may be assigned from time to time.

Senior Planning Engineer في Al Nasr Contracting Company LLC
  • الإمارات العربية المتحدة - دبي
  • يناير 2016 إلى أغسطس 2017

PROJECT : CONSTRUCTION OF LAGOON, BRIDGES, POOLS AND RO PLANT FOR DUBAI PARKS AND RESORTS
CLIENT : DUBAI PARKS AND RESORTS
PMC : HILL INTERNATIONAL AND SAMSUNG C&T
PROJECT BUDGET : AED 200 MILLION
The project is complete construction and commissioning of the Lagoon, Bridges, pools and process related buildings (R.O plant, Circulation Chamber, Aeration Chamber) with all related pipelines from the R.O plant, Aeration Chamber and Circulation Chamber to the lagoon.
The Lagoon is 1.1km long concrete casting with two areas namely Wetland area and the retaining wall area. The project consists of 6 bridges, Bridge 1 & 2 crossing the lagoon, and 2 pools. The water in the lagoon is processed/aerated and circulated by the system that is installed in the 3 buildings and the pumping stations that are part of the project namely - RO plant, Aeration chamber, Circulation chamber and pumping stations. The project has a conveyance system of pipeline and pipeline between the chambers and running into the plants along the lagoon edge, which takes in the water from the lagoon from the skimmers and draw off pits.

PROJECT : CONSTRUCTION OF IN-PARK INFRASTRUCTURE FOR THE
SIX FLAGS THEME PARK (PACKAGE 05)
CLIENT : DUBAI PARKS AND RESORTS
PMC : DXB ENTERTAINMENTS
CONSULTANT : CH2M (HALCROW)
PROJECT BUDGET : AED 152 MILLION
Construction of in park infrastructure works for the Project which includes the following items of works Sewerage Network, Storm water Network, Chilled water Network, Fire Hydrants Network, Fire Main Network, Potable water Network, Irrigation Network, Electrical LV Network, Electrical HV Network, Telecom and ELV Network, Street Lighting Network, Highway Network, Pavement works, Tie-in to the existing utilities, Substation and Building Pads preparation for all buildings except Common Back of House Buildings.

DUTIES AND RESPONSIBILITIES:
1. Preparation of Clause14.1/8.3 Baseline/Contract Programme
2. Performed Cost Loading and Resource loading
3. Prepared Manpower Histogram, Cash Flow, Progress S curve, Procurement Schedule etc.
4. Prepared KPI’s for accurately monitoring the Key items/trades.
5. Prepared Updated Programme weekly
6. Prepared Internal and External Monthly Report
7. Prepared Internal and External Weekly Reports
8. Identifying the Delay Events from Client, Consultant and Subcontractors and drafting delay claim notices
9. Drafting all correspondence of related to delays such as Delay Claim Notices, interims and Final Claim Notice.
10. Prepared Extension of Time Claims using the Time Impact Analysis method and Window Analysis Method.
11. Monitored daily site activities, critical activities, resources (manpower, machinery and materials), shop drawing approval, material approval and procurement activities if any concerns or flag to be raised.
12. Preparation of recovery schedules in case the project is running behind the approved program of works to mitigate any delays.
13. Coordination with Project Team, Client, Consultant and Subcontractors.
14. Coordinate and integrate subcontractors with the programme and ensure compliance with the programme requirements.
15. Report to the Project Manager about the current work progress and make a comparison between the plan and actual progress and study impact of alternative approaches to work.
16. Preparation of look-ahead schedules & supply information to respective departments for timely availability of resources on the site.
17. Attend Progress, Site walk and other relevant Meetings as advised by the Project Manager.
18. Performs other duties and responsibilities as may be assigned from time to time.

Planning Engineer في AMBB Building Contracting LLC
  • الإمارات العربية المتحدة - دبي
  • مارس 2014 إلى ديسمبر 2015

PROJECTS :
1) AL BADIA PHASE 3 PART II BUILDINGS 21, 22, 23, 24, 25, 26 & 27, DUBAI FESTIVAL CITY
Client : Al Futtaim Group Real Estate (AFGRE)
Consultant : BSBG
Project Budget : AED 250 Million
The project work includes construction of Six Residential Buildings, Four Townhouses and Infrastructure works in Al Badia.

2) 2B+G+15 RESIDENTIAL BUILDING IN GREENS
Client : Dutco Group
Consultant : BSBG
Project Budget : AED 101 Million
The project work consists construction of 2B+G+15 residential building in Greens.

3) UNINEST STUDENT ACCOMMODATION
Client : Global Student Accommodation Group (GSA)
Consultant : Stride Treglown
Project Budget : AED 82 Million
The project involves the construction of 2B+G+14 student accommodation project in Dubailand.

4) 2B+G+14 RESIDENTIAL BUILDING IN TECOM
Client : Al Muherieb Real Estate
Consultant : BSBG
Project Budget : AED 90 Million
The project work consists construction of 2B+G+14 residential building in Tecom.

DUTIES AND RESPONSIBILITIES:
1. Preparation of Clause14.1/8.3 Baseline/Contract Programme
2. Performed Cost Loading and Resource loading
3. Prepared Manpower Histogram, Cash Flow, Progress S curve, Procurement Schedule etc.
4. Prepared KPI’s for accurately monitoring the Key items/trades.
5. Prepared Updated Programme weekly
6. Prepared Internal and External Monthly Report
7. Prepared Internal and External Weekly Reports
8. Identifying the Delay Events from Client, Consultant and Subcontractors and drafting delay claim notices
9. Drafting all correspondence of related to delays such as Delay Claim Notices, interims and Final Claim Notice.
10. Prepared Extension of Time Claims using the Time Impact Analysis method and Window Analysis Method.
11. Monitored daily site activities, critical activities, resources (manpower, machinery and materials), shop drawing approval, material approval and procurement activities if any concerns or flag to be raised.
12. Preparation of recovery schedules in case the project is running behind the approved program of works to mitigate any delays.
13. Coordination with Project Team, Client, Consultant and Subcontractors.
14. Coordinate and integrate subcontractors with the programme and ensure compliance with the programme requirements.
15. Report to the Project Manager about the current work progress and make a comparison between the plan and actual progress and study impact of alternative approaches to work.
16. Preparation of look-ahead schedules & supply information to respective departments for timely availability of resources on the site.
17. Attend Progress, Site walk and other relevant Meetings as advised by the Project Manager.
18. Performs other duties and responsibilities as may be assigned from time to time.

Planning Engineer في National Engineering Bureau
  • الإمارات العربية المتحدة - دبي
  • سبتمبر 2011 إلى مارس 2014

PROJECT : RESIDENTIAL BUILDINGS AT QUEUE POINT, LIWAN (PHASE I AND II), DUBAILAND, DUBAI
CLIENT : AL MAZAYA REAL ESTATE
PROJECT BUDGET : AED 1.25 BILLION
APPROVALS OBTAINED FROM MAZAYA REAL ESTATE, DUBAI

1) 52 RESIDENTIAL BUILDINGS AND COMMERCIAL BUIDING AT LIWAN PHASE I AND II
The project work includes construction of 52 Residential Buildings in 52 plots of different storey height such as B+G+20 to G+9 and one Commercial Buiding. The residential buildings are between nine to twenty storeys with one to three bedroom apartments. Liwan is a self-sufficient community spread out over 13 million sq. ft. Inspired by the San Francisco city urban structure.

DUTIES AND RESPONSIBILITIES:
1. Preparation of Clause14.1/8.3 Baseline/Contract Programme
2. Performed Cost Loading and Resource loading
3. Prepared Manpower Histogram, Cash Flow, Progress S curve, Procurement Schedule etc.
4. Prepared KPI’s for accurately monitoring the Key items/trades.
5. Prepared Updated Programme weekly
6. Prepared Internal and External Monthly Report
7. Prepared Internal and External Weekly Reports
8. Identifying the Delay Events from Client, Consultant and Subcontractors and drafting delay claim notices
9. Drafting all correspondence of related to delays such as Delay Claim Notices, interims and Final Claim Notice.
10. Prepared Extension of Time Claims using the Time Impact Analysis method and Window Analysis Method.
11. Monitored daily site activities, critical activities, resources (manpower, machinery and materials), shop drawing approval, material approval and procurement activities if any concerns or flag to be raised.
12. Preparation of recovery schedules in case the project is running behind the approved program of works to mitigate any delays.
13. Coordination with Project Team, Client, Consultant and Subcontractors.
14. Coordinate and integrate subcontractors with the programme and ensure compliance with the programme requirements.
15. Report to the Project Manager about the current work progress and make a comparison between the plan and actual progress and study impact of alternative approaches to work.
16. Preparation of look-ahead schedules & supply information to respective departments for timely availability of resources on the site.
17. Attend Progress, Site walk and other relevant Meetings as advised by the Project Manager.
18. Performs other duties and responsibilities as may be assigned from time to time.

الخلفية التعليمية

ماجستير, Construction Technology & Management
  • في National Institute of Technology Karnataka
  • يونيو 2011
بكالوريوس, Civil Engineering
  • في University of Kerala, TKM College of Engineering
  • مايو 2009

Specialties & Skills

Cost Analysis
Resource Analysis
Project Control
Planning and scheduling
MS Excel
Autocad
Primavera P6
MS Office
MS Project
Fidic Conditions of Contract
Power BI

اللغات

الانجليزية
متمرّس
الهندية
متمرّس

العضويات

Member of Society of Engineers (SOE) UAE
  • Member
  • February 2018

التدريب و الشهادات

Dubai Municipality Approved Civil Engineer (الشهادة)
تاريخ الدورة:
February 2018