Construction Project Manager
EMC
Total years of experience :13 years, 4 Months
Project Manager for 4 residential building
and 9 private schools rehabitation
1. Site Engineer - (EMC) 2017-2020
Project: Construction of the Beirut East Gate Project in Baabda.
Responsibilities: The execution, Quality control and Quantity Survey for Beirut East Gate consisting of 6 blocks Multi-Purpose and two residential Buildings.
The site work was divided on:
Manpower: 4 Forman
78 Labors
2. Site Engineer - (EMC) 2015-2017
• Project: Construction of the Ashrafieh Sub-Station.
• Responsibilities: The execution, quality control and Quantity Survey for Ashrafieh Electrical Sub-station.
The site work was divided on:
Manpower: 1 Forman
45 Labors
Heavy Equipment
2014-till date Site Engineer - Concrete Division (Bridges - Makka 1st Ring Road)
Saudi Ben Ladin Group
(architecture and construction of buildings and project)\
2013-2014 Zone manager - Finishing Work ( S.A.N.G - Bahraa)
Interior Finishing for national guard soldier and officer villas
2012-2013 Site Manager - External Work(King Saud University - Ar Reyadh)
Saudi Ben Ladin Group
(architecture and construction of buildings and project).
Road Construction and Hardscape.
2010-2012 Site Engineer - Construction and Finishing (Princess Noura Unversity - Ar Reyadh)
Saudi Ben Ladin Group
(architecture and construction of buildings and project)
Construction and Interior Finishing for Recreation Center
2010 Sohel Abou Ghannam Engineering Office
Shop drawing / AutoCAD operator
Study areas such as structural engineering, soil mechanics and foundations, environment and water resources engineering, transportation and construction engineering, and hydraulics.