Provide interface management facilities and support between HLG and other EPC
contractors working on project.
Develop and submit AUP Interface management plan.
Page 3 of 7
Develop and submit High Level interface matrix. (AUP/EPC’s)
Develop and update AUP main Interface register.
Lassie with Interface team of other EPC contractors.
Arrange and participate interface meetings.
Provide AUP design documents requested by other EPC contractors.
Update and submit interface AUP Weekly and Monthly progress reports to the
Client.
Provide interface support to HLG Engineering and Construction Teams
/ Pump Stations - Khalifa Port and
Industrial Zone (KPIZ) project No 208
EPC contract
Provide a leading role in the review Project design documents provided by project
consultant
Package Manger of Utilities Pumping Stations; \[Potable Water Pumping stations 1,
2, 3 & 4 and Irrigation Pumping station\].
* Khalifa Port and Industrial Zone (KPIZ) - Project 1000-208
Client
AECOM
Khalifa Port and Industrial Zone (KPIZ) will be a multi-purpose facility located at
Taweelah, Abu Dhabi. Taweelah is located approximately 60km north-east of Abu
Dhabi, between Abu Dhabi and Dubai.
The project comprises the construction of a container handling facility, an industrial
port and the development of an industrial, logistics, commercial, educational and
residential special economic and free trade zone.
Provide a leading role in the review of the subcontractor’s design documentation
and supervise the subcontractor’s construction and commissioning of each PS to
ensure the design complies with the requirements of the subcontract and to ensure
the construction complies with the subcontractor’s design documentation.
Provide a leading role in the review of material and equipment submittals to assist
in the valuation and assessment of claims and effectively liaise with the Client’s
Page 4 of 7
Engineer on matters associated with the design, construction and commissioning of
the works.
Saadiyat Link Project: Manager STP-1 16, 500 m3
/ day:
Client - Tourism Development & Investment Company (
Reviewing / studying the project document (Utilities / ME services) to prepare
information discrepancies lists and trying to sort it out via raising RFI’s to the
Engineer.
Studying subcontractors offers and prepare vetting sheet for final approval.
Provide support to Construction department (liaise with Abu Dhabi government
authorities to get NOC prior to commence construction works).
Provide support to my line manager(s).
Provide support to Planning, QA/QC, Commercial, Procurements departments.
responsible for the execution and supervision of
plumbing, fire protection and fuel compressed vacuum systems.
The central plant and infrastructure project phase included the development of
central plant, laundry and water tanks during which I was responsible for domestic
water filtration system irrigation water supply, drainage - external mains and
buildings, storm water drainage network, hot and cold water services, plumbing
installation - steam, condensate, compressed air and vacuum lines, central
supply - propane gas installation, central supply - fuel installation (bulk & day tanks
- pumps and lines), external water / fire and irrigation mains, fire protection system
(sprinkler, foam, mist, hose reel, hydrants), industrial laundry - laundry equipment,
boilers, heat exchanger, and calorifier.
Responsible for liaison with various sub-contractors and major equipment suppliers
on a daily basis to finalise shop drawings, monitoring of progress at site.
of Plumbing and Fire Fighting
Multiple Projects
Responsible for the preparation of quotations and prices for plumbing and fire
fighting works in buildings and towers from from Department of Social Services and
Commercial Buildings, Public Works Department and Abu Dhabi Municipality,
negotiation the final prices of plumbing and fire fighting materials with the suppliers,
preparation of shop drawings, technical materials submissions for consultants and
local authorities approval, and execution of all plumbing and fire fighting works for
varies Projects Resident and offices buildings ( 20, 15, 10 and 7 Floors) Schools,
Villas complex.
Page 7 of 7
Project Engineer responsible for surveying, excavation, concrete works, plumbing,
Infrastructure and finishing works for the followings project:
50 Villas
responsible for surveying, excavation, concrete works, plumbing
and finishing works, execution of Elevated water storage tank and more than 4000
m2 fair face concrete floor for airport and airplane housing.
Responsible for coordination of survey, excavation, concrete work, plumbing and
finishing works on multiple residential blocks
MUDON,
SUSTAINABLE CITY, 800 VILLAS AND GEMS SCHOOL
Client: Dubai Municipality Drainage & Irrigation Department
Consultant: MWH Global, Inc.
The project comprises the construction of Sewage gravity network, sewage pumping
station & related work, sewage rising main & valves chambers and irrigation rising main
& valves chambers.
My responsibility is to provide a leading role for Engineering & Construction
management for sewage pumping station and associated buildings (Inlet, screen
chambers, wet well, screening building, MCC odour control building, Generator set
building, Fire Fighting water storage tank & pump room and Site work and
miscellaneous (interlock tiles and boundary wall).
Provide engineering support for valve chambers for Sewage & irrigation rising
mains.
Provide technical support to Commercial and Procurement departments.
responsible for supervision of Sewage and Rain water
drainage and Water supply works for the project. Dubai Festival City is constructed
on 650 hectares of land near the banks of the Dubai creek. Rresponsibilities
include review of technical submittals, coordination with Tenant MEP coordinators,
modification of concept design to suit on-site conditions in compliance with
specified regulations and standards, supervision of on-site construction activity,
material and equipment installations and to coordinate with contractor and sub-
contractors to ensure QA/QS standards are followed.
Dewan
Responsible for the execution and supervision of all Plumbing works, Water
Filtration System, co-ordination with ADWEA for water main supply to the raw water
storage tanks, Sand filtration and storage of filtered water. Solely responsible for the
preparation of tender documents including quotations for plumbing and fire fighting
works in buildings and towers from the Public Works Department and Abu Dhabi
Municipality, negotiation of prices of plumbing and fire fighting materials with
suppliers, preparation of shop drawings, technical material submission for
consultant and local authority approval, execution of all plumbing and fire fighting
works.
G+M+5 Typical floors+ Roof\]
Responsible for the execution and supervision of all plumbing works, liaison with
sub-contractors (Firefighting and compressed air system works) and major
equipment suppliers on a daily basis to finalise shop drawings, Coordination with the
architect for equipment approvals, shop drawings and inspection of services. Lead
an extensive study on a case to case basis to provide alternative solutions to
possible clashes between various critical services.
Page 6 of 7
courses: PMI Scheduling Professional course (PMI-SP) 2015 - Cambridge Institute, UAE Management Professional course (PMP) 2014