Planner (Instrument)
Qatar Gas
مجموع سنوات الخبرة :33 years, 8 أشهر
Machine Condition Monitoring Systems (Bently 3300/
3500, SYSTEM1):
- Understanding of concepts of Machine Condition monitoring system
components.
- Bently Temperature, axial/radial vibration, axial thrust, Card/probe settings
configuration and maintenance.
Antisurge control systems (CCC/SERIES 5 ):
- Understanding concepts of Antisurge control systems.
- Understanding CCC system components.
- Day to day maintenance/PM.
Other Systems ( AMS/Valve-link)
- Understanding concepts of AMS/ VALVE LINK system.
- Understanding AMS/ VALVE LINK system components.
- Utilizations while Day to day maintenance/PM.
While working in Qatar gas
Part of Expansion start-up and Commissioning Team for New Mega
trains producing 7.8 MTPA Largest in the world.
Signing of SAT.
Assisting star-up/pre-commissioning activities.
Loop Checking, Function checking and raising punches.
Worked with Vendor for assisting commissioning activities.
Thorough understanding of LNG process.
Start-up sequence checks for Companders & compressors.
Preventive and corrective maintenance schedule/(SAP)
Field Instrumentation selection, installation, & troubleshooting of all type of transmitters:
Control valves: Control valve calibration, understanding of types of Control
valves, its components, servicing, preventive maintenance, application of
DVC valve link /AMS etc
Utilizations while Day to day maintenance/PM.
While working in Qatar gas
Part of Expansion start-up and Commissioning Team for New Mega
trains producing 7.8 MTPA Largest in the world.
* Signing of SAT.
* Assisting star-up/pre-commissioning activities.
* Loop Checking, Function checking and raising punches.
* Worked with Vendor for assisting commissioning activities.
* Thorough understanding of LNG process.
* Start-up sequence checks for Companders & compressors.
* Preventive and corrective maintenance schedule/(SAP)
Field Instrumentation selection, installation, & troubleshooting of all type of transmitters:
Control valves: Control valve calibration, understanding of types of Control
valves, its components, servicing, preventive maintenance, application of
DVC valve link /AMS etc
Previous experience
While working at PETRORABIGH, KSA
* Around 1¾ years of experience in Analyzer Instrumentation involving
FAT/SAT of analyzers and shelters as well spare part management, while
working with PETRORABIGH (Saudi Aramco+Sumitomo), KSA.
* Attended ‘FAT’ for the analyzers and the related systems (AMDS), at
“YOKOGAWA, SINGAPORE”.