Adaptation of primary Distribution of Disi Amman Conveyor
Execution of 62 Km of DIP, different diameters starting from 1000 mm, construction of new pump station with 3 new variable speed split case horizontal pumps with driving motor (3phase 400volts, 50Hz, 1500rpm)& additional 2 new pumps one for Old YPS & the other for Al Kharabsheh PS- Horizontal split case pumps with driving motor (3phase 400volts, 50Hz, 1500rpm), in addition to the Scada system for 213 PRVs& 27FCVs & 21FMs
• Resident Engineer for Water project in Zarqa.
Rehabilitation and Restructuring of Zarqa and Russaifah Water supply networks the cost of the project is about US $ 275, 000, 000 million
• Senior civil and design engineer for infrastructure of Ayla project AQABA.
02/2010-02/2013
Phase 1A land development of the Ayla site is approximately 430 hectares with a235 meters sea frontage, the developments: the lagoons 75hectares, 1, 540 hotel rooms 3, 000 residential units 20, 000 sq.m. Of commercial 24- hole golf course and golf academy and required infrastructure to service the above developments.
• Senior civil and design engineer for infrastructure of MARSA ZAYED project AQABA.
-------------------------------------------------------------
02/2013 - 11/2013
MARSA ZAYED is a multi-phase development project in AQABA. The total project site area is 3, 200 Donums divided into seven main parcels (NO.s T1-T7).the development: the Earth work & Grading, All Infrastructure works for parcels:T3 and T7, Including roads, surface drainage, potable water, waste water, Irrigation, electrical & telecommunication.
SOUF Water Supply System Project
This consists of:
● Water supply networks of DI pipes and GI pipes
● 2 reservoirs with different capacities
Actual contract value 5.5 millions
Alkoura Ajloun Jerash & Almafraq
Water supply network of DI pipes, PE pipes and GI pipes with actual contract value (JOD) 12, 348580
Responsible for:
The construction supervision of all civil works according to the Contractual drawings and technical specifications
Checking the shop drawings submitted by the Contractor.
Following up the quantity surveying
Following up the lab tests
Following up the electromechanical works
Preparing the daily, weekly and monthly reports checking the Contractor invoice
---------------------------------------------------
Rehabilitation of Aqaba Water Facilities including:
Water supply network of DI pipes, PE pipes and GI pipes and 4 reservoirs with different capacities.
Responsible for:
The construction supervision of works in accordance with the technical specifications and drawings
Preparing the daily, weekly and monthly reports
Checking the submitted shop drawings
Followed up the quantity survey and checking the Contractors invoices.
Following up the lab tests and taking the proper action required for the failed ones.
1. Baqa’a infrastructure project.
2. Amman Water Supply System project, Contract # 11, which consists of:
Reservoirs with different capacities
Water supply network of DI pipes, PE pipes and GI pipes.
Construction box culverts
Asphalt and concrete roads and bath ways
Storm water network on concrete pipes
Enchanting the electricity network
Responsible for:
1. The construction supervision of works in accordance with the technical specifications and drawings.
2. Preparing the daily, weekly and monthly reports.
3. Checking the submitted shop drawings.
4. Followed up the quantity survey and checking the Contractors invoices.
5. Following up the lab tests and taking the proper action required for the failed ones.
The “learning resources center” project
This consists of:
Buildings areas of 3045m2
Ground reservoir of 100m3
Responsible for:
1. Construction of all civil works according to the Contractual drawings and technical specifications
2. Submit the shop drawings for approval
3. Following up the quantity surveying
4. Following up the lab tests
5. Following up the electromechanical works
6. Preparing the daily, weekly and monthly reports
7. Prepare the contract invoices
“Amman city sewerage project”
This consists of:
Concrete & DI sewer pipes of different diameters
Construction different manhole types
Execution of house connections
Responsible for:
Supervising the execution works, pipe laying works, backfilling works and the base course works
Supervising the asphalt works.
Supervising the concrete works for encasements and manholes.
Salt water supply system project
This consists of:
Water supply network of DI pipes, PE pipes and GI pipes.
Construction different manhole types
Execution of house connections
Responsible for:
Supervising the execution works, pipe laying works, backfilling works and the base course works
Supervising the asphalt works
Supervising the concrete works for encasements and manholes
This consists of:
Concrete and DI sewer pipes of different diameters
Construction of different manholes types
Execution of house connections
Responsible for:
Supervising the execution works, pipe laying works,
Supervising the asphalt works.
Supervising the concrete works for encasements and manholes.
infrastructure project (water supply, sewerage networks, buildings and roads, asphalt work, concrete works and Soil Tests).
هندسة مدنية-انشاءات