Project Manager
AAW
Total years of experience :26 years, 5 Months
Al Jouda for Contracting. Project: Lamar Towers -Jeddah -KSA an investment of 3 Billion Saudi Riyals.
Following and controlling the earthworks (cut, filling, leveling and soil replacement).
Following and controlling the infrastructure works, casting piles and trimming head of pile.
Following and controlling the concrete works, block works, finishes…etc
Prepare daily & weekly site progress report.
Control the productivity of site works.
•
Following and controlling the earthworks (cut, filling, leveling and soil replacement).
Following and controlling the infrastructure works, casting piles and trimming head of pile.
Following and controlling the concrete works, block works, finishes…etc
Prepare daily & weekly site progress report.
Control the productivity of site works.
Control and ensure all works are carried in strict compliance with the PQP.
Check the Quality of work.
Prepare daily & weekly site progress report.
Control the productivity of site works.
Coordinate with the consultant & supervise the performance of the Sub-Contractors.
Monitor and ensure the availability of required resources on site.
Control & efficiently execute the snagging & handing over procedure.
Gettco Contracting Company is a subsidiary of Al Faisal Holding, Doha, Qatar www.alfaisalholding.com. Project: World Trade Center, Algeria, an investment of 150 Million $US in Hamma, Algeria.
Following and controlling the infrastructure works, casting piles and trimming head of pile.
Following and controlling the earthworks (cut, filling, leveling and soil replacement) of networks (water and electrical).
Following and controlling the concrete works, block works, finishes…etc
Maintain records for each subcontractor.
Maintain records for each activity on site.
Hold periodic meetings with subcontractors to resolve potential problems and review schedule progress and performance on site.
•March.2008 till June 2010 Section Site Engineer, ACC, (Arabian Construction Company) Doha branch. Project: The Pearl Qatar - Viva Bahriya VB-29, an investment of 750 Million QR in Doha, Qatar.
Control and ensure all works are carried in strict compliance with the PQP.
Check the Quality of work.
Prepare daily & weekly site progress report.
Control the productivity of site works.
Coordinate with the consultant & supervise the performance of the Sub-Contractors.
Monitor and ensure the availability of required resources on site.
Control & efficiently execute the snagging & handing over procedure
EL MARASEM) Jabal Al Kalaa, Project: Makkah, Saudi Arabia, an investment of 7 Billion Saudi Riyals.
Following all construction activities of the project on site.
Monitor the progress of the works on site.
Coordination between the Consultant (Dar El Handassa) and Site Teams in all the activities of the project
Sahara building systems steel structures.
Monitor the progress of the steel works.
Coordination between the Consultants and the sites teams
Gulf of Aqaba for Touristic Investment “GATO
Supervise and inspect the earthworks (cut, filling, leveling and soil replacement) Supervise and inspect networks works (water and electrical)
Supervise and inspect the construction works (civil and finishes
Supervise and inspect the construction works.
Coordinate the work of various trades and Sub-contractors on site.
Civil works Quantity surveyor.
Gulf Of Aqaba For Touristic Investment “GATO “the owner of Sonesta Taba Resorts & Casinos (5 stars resorts), Taba, Egypt.
•Site Engineer, MIB (Misr International Bank), Cairo, Egypt
Sahara building systems agent of Butler group, Cairo, Egypt
•Senior Site Civil Engineer, Gettco International, Algeria, a subsidiary of Al Faisal Holding Company, Doha, Qatar.
•Section Site Engineer, ACC, (Arabian Construction Company) Doha branch.
•Construction Manager, Al Jouda Contracting.
•Project Manager, AAW International Consulting Office, (DR Ahmed Abd el Warith)