Masud Khan, Chief Engineer

Masud Khan

Chief Engineer

China National Electric Engineering Company

البلد
باكستان - إسلام أباد
التعليم
بكالوريوس, Power Systems
الخبرات
49 years, 1 أشهر

مشاركة سيرتي الذاتية

حظر المستخدم


الخبرة العملية

مجموع سنوات الخبرة :49 years, 1 أشهر

Chief Engineer في China National Electric Engineering Company
  • باكستان - إسلام أباد
  • أشغل هذه الوظيفة منذ نوفمبر 2013

Looking After installation and commissioning of 500KV GIS BAY DIA and 600MVA 500/220KV power Transformmer including protection wiring testing and commissioning.

o Worked as Project Manager (Consultant) at Hail في New Hail-Al-Jouf Interconnection Project
  • المملكة العربية السعودية - الجوف
  • ديسمبر 2010 إلى يوليو 2013

21 Dec, 2010 to 2013 30 April o Worked as Project Manager (Consultant) at Hail - New Al-Jouf Interconnection Project.
Consultant Project Manger o Scope comprises Construction of New 380kV Al-Jouf
Dar Engineering Substation, Extension and modification of existing
Saudi Arabia 380kV Hail Substation and interconnecting 380kV
Transmission Line (377km)
o Drawing and material review was part of job.

o Worked as site manager في Al-Fanar Co
  • المملكة العربية السعودية - الرياض
  • ديسمبر 1976 إلى أبريل 2013

19 Dec 2003 to 10 May o Worked as site manager at under construction

PROJECT MANAGER في Al-Fanar Co/ WAPDA PAKISTAN
  • المملكة العربية السعودية - الرياض
  • فبراير 1976 إلى أبريل 2013

2005 132/13.8 Kv GIS S/Stn at Riyadh having capacity
Al-Fanar Co. (K.S.A) 60x3MVA power transformers. The S/S Installation
o Consists of all types of activities such as power
transformers, 13.8kv switchgear, control relay panels,
132Kv GIS switchgear. And all type of cabling
relating to above switchgear.
o Testing activity related to above is also being managed by me.
o Installation activities for other SERVICES are also
being managed by me. Such as Water sprinkler
system, fire alarm systemFM200 system air- conditioning system and building electrification.

PROJECT MANAGER في Al-Fanar Co
  • المملكة العربية السعودية - الجوف
  • فبراير 1975 إلى أبريل 2013

Aug.2001-21 Dec 2002. o Worked at 115/13.8kv, National Guard S/Stn.
Al-Fanar Co. (K.S.A) Which includes all types of electrical activities such
Project Site Engineer as? Installation of all electrical equipment's in
(Construction) . outdoor and indoor area.
o Cabling and protection wiring of all electrical
equipment's outdoor and indoor also managed
testing & commissioning
o Control building and outdoor lighting. HVAC
system wiring and commissioning.

PROJECT MANAGER في Alfanar co
  • المملكة العربية السعودية - الرياض
  • فبراير 1975 إلى أبريل 2013

Jan. 01-july 01 o Installed, Tested and commissioned 100 MVA,
Site Manager. 132/33kv Power Transformers, And 33kv ABB
Alfanar Co. (K.S.A) . Switch gear indoor GIS at S/S 8801, Al-Qassim.
The job comprised of carrying out working in energized substation under LOA which includes


2
wiring modification in exiting MVA power
Transformers. T1 & T2 and its related 33kv- switchgear section A & B. The modification works
were being commissioned in step by step outage.
o All testing and commissioning activities also
carried out for various relays and protection

PROJECT MANAGER في Al-Fanar Co
  • المملكة العربية السعودية - الرياض
  • فبراير 1975 إلى أبريل 2013

May.98-Dec.99 o Worked in above capacity with Al-Fanar Co
Al-Fanar co. (K.S.A) o Laying of 132 kv XLPE power cables to different
Project Site substation around Holy Makkah. (The suppliers of
Engineer (Construction) cable Saudi Cable Company) .The job, which also
included 6Km of cable tray route designing, And
installation in side Haram cable tunnels.
o The jobs also included carrying out power cables
tests at site. Also dealing with technical
correspondence regarding the above project.

PROJECT MANAGER في alfananr
  • المملكة العربية السعودية - الرياض
  • فبراير 1975 إلى أبريل 2013

My job was to manage as well as consultant for construction of 02 numbers 380/132KV substations having capacity 500MVA and transmission line 380KV double circuit with four bundled conductor 400km long in rough terrain from Hail to Jouf.

PROJECT MANAGER في wapda,pakistan
  • باكستان - بيشاور
  • يناير 1975 إلى أبريل 2013

Construction and maintenance of high voltage substations and transmission lines from 110KV upto 500Kv.It includes awarding contracts and executing the works.Also designing installation testing and commissioning of the network substation and transmission lines.

o Worked as director في High Voltage & Short-Circuit laboratory
  • باكستان - إسلام أباد
  • أكتوبر 2008 إلى ديسمبر 2010

1 Oct, 2008 to 20 Dec, 2010 o Worked as director at High Voltage & Short-Circuit
Director HV&SC Lab. Laboratory, Rawat. Supervising various TYPE tests
PEPCO. Pakistan of electrical equipment like power transformers,
power cables, CTs, PTs, metal clad panels and other
electrical equipment of various voltages. Power
frequency voltage of 500kV and impulse testing of 1800kV.

Manager في wapda.
  • باكستان - إسلام أباد
  • ديسمبر 1976 إلى يونيو 2010

Dec 21, 2002 to 18 Dec2003. o Worked as a Site Manager at 132/33 kV Substation
Al-Fanar Co. (K.S.A) 8802 & 8803, in Al-Qassim for Installation of additional 100MVA Power
Transformer and its related modification
works
All work being carried out in Energized
System under LOA.
The work comprises Installation of power
transformer 33kv switchgear with control
relay panels, all cabling work, testing & Commissioning activities.

30 Sept, o Worked as a senior engineer at 220kV/132kV/11kV في wapda,pakistan
  • باكستان - بيشاور
  • ديسمبر 2006 إلى يناير 2008

25 Dec, 2006 to 2008 30 Sept, o Worked as a senior engineer at 220kV/132kV/11kV grid station Mardan, NWFP. Managed the operation
NTDC-WAPDA and maintenance of 220kV/132kV 3X160 MVA
Deputy-director 220kV power transformers, overhauling of 220kV and grid-station 132kV circuit breakers.
Pakistan o Overhauling of 220kV and132kV diverter switches of tape-changers.
o Replacement of 132kV oil-breaker with new SF6
GEC ALTHOM (France) breaker.

20 Dec, o Worked as project manager في Al-Fanar Co
  • المملكة العربية السعودية - الرياض
  • مايو 2005 إلى يناير 2006

Worked as project manager for 132kV cables project (total route 5km) . The project consisted of designing,
Al-Fanar Co. (K.S.A) procurement and lying of 132kV 1200mm2 power
cables, 12 pair X 0.9mm2 pilot cables and 36 fiber
optic cables.


1

Exe- Engineer في WAPDA
  • باكستان
  • يناير 2000 إلى ديسمبر 2000

Jan.00-Dec.00 WAPDA o Worked as Exe- Engineer operation, managed
(Pakistan) . maintenance of 38 No S/S .and 900-km
Executive Engineer. transmission lines.
o The job included managing look after for all
technical and administration matters.
o The job also included maintenance for all
equipment. Also taking care for different
modifications in the network Substations.

o Worked as a project site engineer في Al-fanar Co
  • المملكة العربية السعودية - الشرقية
  • سبتمبر 1997 إلى مايو 1998

Sep.97-May 98 o Worked as a project site engineer with Al-Fanar
Al-fanar Co. (K.S.A) Co, on construction of 115/13.8KV new substation
Project Site Engineer at Alkhafji and modification of two Nos Addl
(Construction) S/Stn.including installation of equipment such as power transformer.
o HV circuit breaker, disconnector relay & control
panel including inter connection lighting. Fire
alarm system in control building.
o The laying of under ground power cable in duct as well as direct burial in ground including cable
sealing cable termination, Control cable laying and its termination in different equipment in control
building and switch yard. It included all substation
commissioning activities.


3
Sep.95-Sep.97 o Two years experience as a senior engineer with
WAPDA (Pakistan) WAPDA on construction of 500 /220 kv S/Stn of
Senior 900MVA capacity. Having two Nos, transformer
construction/protection bays of 450 MVA capacity .It was a turnkey project
Engineer. with Nazir & Co as contractor with NESPAK as consultant and Siemens/ AEG construction as main
manufactures / supplier of electrical equipment for 550kv. Being also responsible for testing /
commissioning.
o The 220kv yard was the constructed by imperial
construction ABB as the main supplier of equipment the works included supervision and
erecting of equipments relay and control panels
power transformers XLPE power cable laying and its termination inside sub station control cable
laying and its wiring testing of the equipments and its final commissioning including interfacing.


o Worked for seven and half years on construction of

Senior Construction في wapda,pakistan
  • باكستان - بيشاور
  • فبراير 1988 إلى أغسطس 1995

Feb.88-Aug.95 220-132/66kv S/s, under ground power cables and
WAPDA. transmission lines With WAPDA, it included.
(Pakistan) . o Supervision of site selection, site preparation,
Senior Construction floating of tender for control building
Engineer. and equipment foundation works, calling
quotation for petty purchases such as bus bar
clamps, wire ferrules etc.Shifting of
electrical equipments from WAPDA
Types stores to site of Work. Also.
dealing with all of technical
Correspondence
Sub Station: o Installation of all types of electrical equipment in new substations and also in existing substations
where extension was required.
Power transformer of voltage of 220, 132
Kv, 66kv 33kv were installed.
o HV circuit breakers of220kv and 66kv installation.
o Laying of XLPE power cable of different
o Capacities in cable ducts as well as direct burial in ground and inside S/s including terminations, also
its testing and commissioning.
o Laying of control cables in cable trenches including
its termination.
o Disconnect switches of 220kv, 132kv and 66kv
installation.


4
o Indoor metal clad switchers of 11kv of different
make as Mitsubishi, siemens,
Toshiba, AEG, ABB etc.
o Installation of control and relay panels in control
house building.
o Battery and battery chargers installation such as filling electrolyte, charging and discharging
process.
o Also carrying out testing and commissioning
activities related to above.
Transmission line: o Supervised construction of over head transmission
lines of 132kv and 66kv in plane and hilly areas.
The construction activity included management of route marking preparation of profile, floating of
tenders for civil works, shifting of all materials from WAPDA stores marking of tower location
Excavation, converting of towers erection, stringing and final energization.

Senior Maintenance Engineer في WAPDA (Pakistan)
  • باكستان - بيشاور
  • فبراير 1986 إلى يناير 1988

Feb.86-Jan.88 o Worked for two and half years as senior engineer
WAPDA (Pakistan) . with WAPDA in operation and maintenance of
Senior Maintenance 220/132/66kv-33kv s/sand transmission lines and
Engineer underground power cables.
o Worked for two years as senior engineer with

Executive Engineer في WAPDA (Pakistan)
  • باكستان - بيشاور
  • فبراير 1984 إلى يناير 1988

Feb.84-Jan.88 wapda in operation and maintenance of 11/0.4 kV
WAPDA (Pakistan) . S/S and distribution lines being also responsible for
Senior Distribution revenue collection.
Engineer o The work also includes laying of underground
power cables, construction of overhead lines of 11kv and related maintenance of both activities.

Substation Engineer في wapda,pakistan
  • باكستان - إسلام أباد
  • يوليو 1983 إلى يناير 1984

July.83-Jan.84 o For seven months worked with ministry of
MEW (Kuwait) . electricity and water, Kuwait on supervision
(Substation Engineer Construction of 132/66/33kv substations of GIS
construction) . type. It included installation of equipments such as
GIS circuit breakers, GIS bus bars, power
transformers, underground power cable and testing/commissioning of equipment including
underground power cable.

Asst construction Engineer في wapda pakistan
  • باكستان - إسلام أباد
  • فبراير 1975 إلى يناير 1983

Feb.75-Jan.83 o Worked for eight and half years on construction of
WAPDA (Pakistan) . 220/132/66kv
Asst construction Engineer s/s and transmission lines underground cables with
WAPDA it included in: Substation: o Installation of all types of electrical equipment in all Substations and also in existing substations
where extension was required
The activity included
o Power transformers of160mva, 220/132kv,


5
20/26mva, and 10/13mva with ratio of
132/11kv installation.
o HV circuit breaker of 220kv, 132kvand 66kv
installation.
o Laying of XLPE power cables of different
capacities in cable ducts as well as direct burial in ground and inside Substations including its
termination.
o Disconnect switches of 220kv, 132kv and 66kv
installation.
o Indoor metal clad switchers of 11kv of different
makes such as Mitsubishi, siemens, Toshiba, AEG,
ABB etc.
o Installation of control and relay panels in control
house building.
o Battery and battery chargers installation such as filling electrolyte charging and discharging process.
o Testing and commissioning of all electrical
equipment including protection wiring.
Transmission line: o Supervised construction of overhead transmission
lines of 132kv and 66kv in plane and hilly areas. the construction activity included management and route making, preparation of profiles, floating of
tenders for civil works, shifting of all materials from WAPDA stores, making of tower location,
Excavation concreting of towers, erection, stringing and final energization.


6

الخلفية التعليمية

بكالوريوس, Power Systems
  • في Engineering University Peshawar
  • نوفمبر 1974

B.Sc. Electrical Engineering First Class (1974) Merit achievements: Awarded meritorious performance awarded by Chairman WAPDA for best over all working in the field of Substation and transmission lines. Training attended: o Attended 14 weeks training on maintenance, Operation of substation and transmission lines being conducted by M/s Harza, Germany. o Training on event and fault recorders installed at computerized 500/200/132kv substation conducted by siemens, Germany. o Training on maintenance management conducted by Ontario hydro, Canada by Canadian Engineer. o Maintenance of 11kv distribution system (refresher course) o Training on Benning battery chargers, France conducted by French Engineer. o Senior management training at Wapda Staff

بكالوريوس, Powersystems
  • في University of Engineering Peshawar
  • نوفمبر 1974

obtained first class

Specialties & Skills

Installation Management
System Testing
Commissioning
Maintenance Services
ENGINEER
EXCAVATION
MITSUBISHI
SIEMENS
SUBSTATIONS
TESTING
TRANSMISSION LINE
TRANSMISSION LINES
construction of electrical substations and transmission lines
training on event and fault recorders
overall performance in the field of electrical substation construction and maintenance
training on Benning battery chargers
training on maintenance management conducted by Ontario Hydro Canada
refresher course on maintenance management of 11kv distribution system
14 weeks training by M/rs Harza Germany on maintenance and construction of substations and T lines
09 weeks senior management course at Wapda staff college Islamabad

اللغات

الفرنسية
مبتدئ
الانجليزية
متمرّس
العربية
متوسط
الأوردو
متمرّس

العضويات

Pakistan Engineering council
  • Attending courses for upgrading engineering knowledge
  • July 1977
Pakistan Engineering council
  • member
  • July 1977

التدريب و الشهادات

certificate (الشهادة)
تاريخ الدورة:
January 1976
صالحة لغاية:
May 1976
MS project and Primevera (الشهادة)
تاريخ الدورة:
October 2010
صالحة لغاية:
December 2020
Available (الشهادة)
تاريخ الدورة:
September 2008
صالحة لغاية:
December 2020