Project Control Manager في ERSA Construction Co. Inc.
  • كرواتيا - Slatina
  • أشغل هذه الوظيفة منذ أغسطس 2022

ERSA Construction Co. Inc. Slatina - Croatia
The Water Supply and Wastewater System of the Slatina Agglomeration & Beli Manastır Wastewater Treatment Plant Project EU Funded Projects - Project Control Manager

The works under the Project represent the largest segment of the Slatina Agglomeration project, which includes the construction, reconstruction and rehabilitation of water and communal infrastructure in Slatina and seven suburbs. The project includes the construction, reconstruction and rehabilitation of 62 kilometers of sewerage network, construction and reconstruction of 12 kilometers of water supply network, construction of preparation for 2071 house connection to the sewerage system, construction of four rain spills and 33 pumping stations. Also, a new water reservoir with a capacity of one thousand cubic meters will be built and preparations will be made for 989 house connections to the water supply network. The Project is FIDIC Red Book and financed by European Union FunFunding.Establish risk management protocol which includes identification, documentation, mitigation and tracking of potential risks on the project. In addition, determine potential cost and schedule/progress impacts of potential risks as they are identified.

- Establish and manage project schedule development, review and update processes and to ensure accuracy and alignment with the overall master schedule.
- Identify and communicate design changes, scope changes and schedule slippages and potential impacts and participate in the identification of mitigations. Ensure trends of cost and schedule are identified, manage change management process and communicate and suggest corrective actions.
- To follow up on proposals, reviews, and negotiations for the timely execution of contracts and purchase orders.
- Track proposal reviews, negotiations and contract execution. Managing & coordinating and tracking the supplier delivery plan to ensure suppliers meet the demand per the plan.
Interact with the Project Management team and corporate management team and participate in regular project meetings.
- To provide reports for the progress and status of SOWs open for long periods. Coordination of closure of POs at project-end and keeping track of work orders status. Periodically review financial reports to ensure compliance with budget targets, re-conciliation of project charges against approved contracts and support gathering data related to unit costs within sites.
- Perform contract administration of contracts based on FIDIC Contracts (Slatina is Red Book 1999, Beli Manastır is Yellow Book including local procurement procedures),
- The Managing Contract Administration Department comprised of local and expatriate claim and contract specialists.
- Examine and review the contract documentation, claims and procedures in accordance with the requirements.
- Mentor and lead a large staff of project controls team members, ensure project is staffed appropriately, conduct regular staff performance reviews and manage any staffing issues that may arise.

Construction Manager في Tekfen Construction Co. Inc.
  • أذربيجان - Baku
  • مارس 2021 إلى أبريل 2022

Tekfen Construction Co. Inc. Baku - Azerbaijan

Azerbaijan Central Bank of Azerbaijan

Construction Manager

The New Central Bank building would be situated on Heydar Aliyev Avenue, one of the top locations in Baku, close to three buildings have already completed by Tekfen Construction all, which received the most highly respected prizes of ‘Best Project’ and ‘Award of Merit’ listings in their respective categories from the ENR Global Best Project Awards organization: the Baku Olympic Stadium, the SOCAR Tower and the Azerbaijan Ministry of Taxes Tower. The project covered the construction of a new 37-storey building for the Central Bank of Azerbaijan. The turnkey project, which was for a tower 168 meters high on a site with a total area of 67, 981 square meters, was due to be completed in 36 months.
- Delivering the project on time, within budget and in compliance with the charter’s terms and conditions with a full understanding of scope, all fit-out, joinery and architectural finishes.
- Team building, HSE, temporary works, Quality and procurement implementation.
- Developed the Project Management Plan and the Project’s Scope Management Plan. Design development and coordination. Planning of design and construction process.
- Developing a detailed baseline schedule.
- Developing client and consultant relationships.
- Developed a procurement plan as well as the budget and cashflow forecasts.
- Reviewing shop drawings.
- Managed integrated change controls.
- Validated and controlled scope and managed scope creeps.
- Developed and managed the implementation of the safety plan and oversaw Health & Safety on-site.
- Managed all logistics and developed solutions.
- Mentor and lead a large staff of project team members, ensure the project is staffed appropriately, conduct regular staff performance reviews and manage any staffing issues that may arise.

Construction Manager في Yapı Merkezi Co. Inc
  • تنزانيا - Dodoma
  • أبريل 2020 إلى يناير 2021

Yapı Merkezi Co. Inc. Dodoma - Tanzania

Design and Build Contract for the Standard Gauge Railway (SGR) Line from Morogoro to Makutopora (MDM Project) Phase 2 / Construction Manager

As Construction Manager, management and coordination have done during the design and construction project in LOT-2, MDM, which had also contracted to the Yapi Merkezi. This section stretches from Morogoro through Dodoma to Makutopora in Singida. The stations after Morogoro will be 8 No’s: Mkata, Kilosa, Kidete, Gulwe, Igunda, Dodoma, Bahi and Makutopora. Phase 2 of the Tanzania standard gauge railway (SGR) had been designed for passenger trains with speeds of 160km/h and freight trains with a top speed of 120km/h. The segment, LOT 2, has eight stations including a dry port at Ruvu. The contract involves the following.
- The Project was a FIDIC Yellow book.
- The Client was Tanzania Railways Corporation (TRC) and Consultant: Korail JV
- Project Cost: $2 billion.
- Track length: 333 Km Main Line and 81 km siding/passing; 414 Km.
- Maintenance: Workshop Facilities at Marshalling Yard.
- 4 Tunnels (approx. 2622 meters).
- 168 No’s of Bridges, Overpass, Underpass, Livestock, 646 No’s Culvert approx. 21, 791 meters., Approx. 55, 7 mil. m3
- Design development, and coordination. Planning of design and construction process.
- Team building, HSE, temporary works, Quality, and procurement implementation.
- Interface with the other disciplines for planning, design, and construction methodology.

Construction Project Manager في Özge Cons. Co. Inc.
  • تركيا - إزمير
  • سبتمبر 2019 إلى أبريل 2020

Özge Cons. Co. Inc. Izmir - Turkey

Construction and Rehabilitation of Sewerage & Stormwater Networks in IAOSB
Project Manager

As Project Manager, management and coordination were done during construction and rehabilitation of sewerage and stormwater networks project in IAOSB - Izmir.
- Design development and coordination. Planning of design and construction process.
- Team building, HSE, temporary works, Quality, and procurement implementation.
- Interface with the other disciplines for planning, design and construction methodology.

Site Manager في PORR Qatar Construction
  • قطر - الدوحة
  • سبتمبر 2018 إلى أغسطس 2019

PORR Qatar Construction Doha - Qatar
Al Wakrah Stadium & Precinct Main Works and Masterplan Project - (€ 587.3 Million) Midmac - PORR - Sixco JV (MPSJV) 17.08.2018-15.08.2019 Site Manager

Al Wakrah Stadium would be incorporated into the 2022 FIFA World Cup Qatar. The client is the Supreme Committee for Delivery & Legacy. Design, engineering, construction, testing, commissioning and completion of a 40, 000-seat two-tiers FIFA compliant Stadium. The stadium had a tournament capacity of 40, 000 spectators during the games and, by using modular best practice design, the number had reduced to 20, 000 spectators for the legacy program in Qatar. Another significant element of the design project was the merging of cooling technology systems with climate-control requirements for renewable energy production.
My responsibilities in this project:
The project site has been divided into a two-parts pitch area and precinct-external works zone. As site manager for both the design & construction of the external works (375, 000 m2) - public space that also contains VVIP/VIP/Hospitality level - of the project was designed & constructed with.
Two training fields cooled to 26 degrees with the above-mentioned integration of cooling-technology system,
Two indoor halls, Four tennis courts, Two basketball pitches,
Various sporting facilities, including a cycling and running track, horse riding areas and other green spaces.
Temporary Rest rooms all around the stadium, which will serve during 2022 FIFA World Cup and then these facilities will be removed by the time reducing 20, 000 seats.
In addition, a community market (4000 m2), and community facilities, such as a mosque and scschool Also, a 10, 000 sqm retail complex is planned & constructed.
Car Parks were designed and constructed in this level, which serve to full capacity of the stadium.
The pitch: The turf used for the playing surface was grown at the turf farm that was placed in external works area.
Including masterplan works, and retails, energy center, infrastructure, landscaping, utilities and asphalt road works, and concrete interlocking pavement lines within the site. Work also includes all MEP works and interface between the disciplines.
For the soon future as an extension of the design, there will be a four-star 150room hotel.

Construction Manager في Al Khor Expressway Project – RedcoPORR JV
  • قطر - الدوحة
  • أغسطس 2017 إلى أغسطس 2018

Al Khor Expressway Project - RedcoPORR JV 18.08.2017-16.08.2018 Construction Manager

Responsible as Construction Manager for civil works and MSE Walls packages of Multiple layers Interchanges A and B in Redco International -PORR Qatar JV
The client is Ashghal - Public Works Authority / Tekfen Construction
Consultant: KEO International Consultants
PORR representative for Redco-PORR JV on Al Khor Expressway Project, Doha, Qatar. The contract involved constructing 3 post-tensioned in-situ bridges, 17 multi-span main bridges, 30 underpass/subway/culvert structures and 150, 000m2 of MSE walls. Responsible for both structure and MSE contracts including P & L.

Site Manager في PORR- SBG -HBK JV
  • قطر - الدوحة
  • أكتوبر 2015 إلى أغسطس 2017

Doha Metro Track Works Project - 18.10.2015 - 17.08.2017 Site Manager

Doha Metro Track Work Project (250 Mn. USD) Responsible as Site Manager for the design and construction of 172 km (344 km rail installation) of the Doha Metro Track Work project. Within the scope of phase 1 of the Metro Doha project, four underground lines have been constructed.
The track system was designed as ballast-less track system STA (Slab Track Austria) including sections of mass-spring systems. The planning & execution of tracks has comprised eight (8) sections, such as tunnels, at-grade and bridges. In addition to the main tracks, turnout areas and the associated transition areas were established. As a basis for slab track design the existing alignment was revised and optimized.
Design interface with each of the Doha Metro Project’s civil contractors. Construction interface with Doha metro Greenline, Redline North, Redline South and Goldline civil contractors.
Design interface with Doha Metro System subcontractors.
Construction interface with Doha Metro System subcontractors.
Planning & development of track slabs and track works design process.
Planning & execution of track slab (500.000m3) and track installation in tunnels, viaducts and at grade sections at 8 different project sites.

Senior Project Engineer في PORR Qatar Construction
  • قطر - الدوحة
  • أكتوبر 2014 إلى أكتوبر 2015

PORR- SBG -HBK JV. Doha - Qatar

Green Line Underground and Green Line Elevated & At Grade

Senior Project Engineer (Greenline Elevated & At Grade)

As a Senior Project Engineer, construction works at Viaduct - Site 2, Office Area of JV and QRail - Site 4, MLPA Plant, Material Laying Area -Site 3, such as formwork fabrication for viaduct, concrete casting pre-cast beams at Site 3, construction of slab deck, pier caps, foundations & columns at piers, erection of scaffold.

Supervise/coordinate onsite construction as per QRail guidelines and project heads instructions, support the engineering activities if required to ensure the activities are integrated with the execution sequences, review ITP and MoS, prepare the required reports for the project progress during the construction phase, monitor construction progress and ensure that site activities and equipment items (and associated components) are installed according to approved milestones, participate in bid evaluations/clarifications to address the best practices and resource requirements, facilitate constructability & operability workshops to address all project concerns and requirements to be address during downstream activities, conduct site visits to verify the best construction practices are followed and advise Project Teams on improvements needed, participate in 3D-Model reviews to ensure best practices are addressed in ensuring smooth construction phase, review invoices of subcontractors and vendors and provide management with approval comments and recommendations of payment, responsible for mentoring, guiding, and measuring performance of any subordinates, monitoring/supervising the documentation to reflect the "as build" condition as required and verified by the concerned discipline engineering, updates the drawings/documents along with CAD Operators.


Project Engineer (Greenline Underground Switch Box M30-31)

Doha Metro Greenline Underground Project (4 Bn USD) Responsible for project management of design and construction of Underground Station for Doha Metro Greenline Underground project.

Design development and coordination. Planning of design and construction process.

Team building, HSE, temporary works, Quality and procurement implementation.

Construction of station up to 32m deep, 200m long and 50m wide by implementing all necessary dewatering, slope protection, excavation, base, wall, roof and TBM oriented structures.

Interface with Tunnel team for planning, design and construction methodology.

Interface with MEP, Architectural team for design of the station.

Project Manager في Yapi Merkezi Saudi Co.
  • المملكة العربية السعودية
  • يوليو 2013 إلى سبتمبر 2014

Yapi Merkezi Saudi Co. Al Nariyah - Saudi Arabia

Al-Nariyah Depot and Workshop Project

Project Manager

Al Nariyah Depot and Workshop Project, which was undertaken by Yapi Merkezi Saudi Co. as the Main Contractor. A Government-funded $165 million, new build heavy goods train maintenance depot in a remote desert location. Within the scope of the project;

Locomotive and wagon maintenance shop, general stores, fueling system, 4 generator rooms, paint shop, wagon washing facility, yard facility, and track & signal maintenance units and Hostel are being constructed by Yapi Merkezi Saudi Co.

23 New steel framed buildings, comprising of Locomotive Works Shops (15, 000 sqm),

Wheel Shops, Bearing Shops, Wagon maintained areas (14000 sq. m), stores.

Installation of supporting statutory services, operational equipment for maintenance of freight, (portal wheel lathes, underfloor wheel lathes, bogey drop table, train carriage lifting system) roads, drainage, water treatment, power generating plant, 1.2 million liters heavy oil refueling system, permanent workforce accommodation for 300 technical staff. 
Essentially a small self-contained village in what was barren desert, had been constructed by Yapi Merkezi Saudi Co.

Full Engineers delegated powers under F.I.D.I.C 1999 Red Book over Contractor with 1000 + persons on-site workforce.

Day to day workload management and parentage of 25 multi-national technical and operational staff, from all corners of the World (India, Pakistan, Philippines, Turkey, and GCC).

Design development and coordination. Planning of design and construction process.

Team building, HSE, temporary works, Quality and procurement implementation.

Deputy Project Manager في Cengiz Libya Cons Co
  • ليبيا - سبها
  • يناير 2010 إلى فبراير 2012

Cengiz Libya Cons Co. Sabha - Libya

Sabha Infrastructure Project - Design & Construction of Infrastructure works

Deputy Project Manager

As a Deputy Project Manager, Design & Infrastructure Works (master plan - for the year 2030, sewage and potable and stormwater lines, telecommunication, electric, substations, landscaping, road and asphalt works of 6303.5ha) of Sabha Infrastructure Project in Sabha City - Libya.
Because of the war the project was stopped.

Project Manager في Özmim Cons. Co. Inc
  • تركيا - Tokat
  • مارس 2009 إلى ديسمبر 2009

Özmim Cons. Co. Inc. Tokat - Turkey

Construction of Hydro Power Plant - 1 (HES-1)

Project Manager

As a Project Manager, construction of Hydro Power Plant - 1 (HES-1; the first one of the three phases) on a turnkey basis which as a subcontractor in Reşadiye-TOKAT - Turkey. The construction was undertaken as an employer by TURKON-MNG.

Tenant & Fit-out Works Coordinator في ENKA Co. Inc
  • روسيا - Moscow
  • أغسطس 2008 إلى فبراير 2009

ENKA Co. Inc. Moscow - Russia

Metropolis Shopping Center Project

Tenant & Fit-out Works Coordinator

Executed, as a Tenant &Fit out works coordinator, finishing works of Metropolis Shopping Center (Shopping Center 170.000 m2 and 3 Office Blocks (2 *9 floors and 1*11 floors) and Car Park (5 floors) of totally 344.000 m2 Area with 256 Tenants) - 400 million $.

Project Manager في G.F.C. Group Co. Inc. Iasi
  • رومانيا - Iasi
  • سبتمبر 2007 إلى يوليو 2008

G.F.C. Group Co. Inc. Iasi - Romania

Construction of Carrefour and Praktiker Mall

Project Manager

As a Project Manager, Construction of ERA Carrefour (33.600m2+Carpark / 2500 slots) and ERA Praktiker Malls on a turnkey basis which were in Iasi-Romania.

Civil Works – Production and Site Managing Engineering في Yapı Merkezi Co. Inc. Rail Systems Group
  • تركيا - اسطنبول
  • يناير 2003 إلى أغسطس 2007

Yapı Merkezi Co. Inc. Rail Systems Group - Istanbul

Civil Works - Production and Site Managing

Engineering

Kayseri Light Rail System Quotation, Izmir Subway II. Stage Quotation, Algeria Railway, Ankara-Istanbul Railway Line II. Stage Quotation and Marmaray Stage CR1 Quotation Preparation as a Tendering Department Engineer.

Istanbul Metropolitan Municipality Zeytinburnu - Bağcılar Tramvay Line Works, monthly interim payments, attachments, NUP and as-built had been prepared in Technical Office.

08.01.2004 - 12.02.2005 Eskişehir Metropolitan Municipality Light Rail System Project (ESTRAM-124 million $) monthly interim payments, attachments, NUP (New Unit Price) and as-built were prepared as a Technical Office Engineer. ESTRAM Project has UITP2004 award.

Fevziye Mektepleri Foundation Işık University Şile Campus 1. Stage Building, as an Infrastructure Work Chief (mechanical installations, wiring works, piping and sewage system installations, vehicle and sidewalks, retaining walls, pools, treatment plant etc.). Designed substructure works, prepared bill of quantities and estimated accounts, NUP (New unit price), substructure work programs, production of works, reported about the productions for project manager, prepared as built and decomplete definitive works.

Project Manager في İşcan Co. Inc
  • تركيا - اسطنبول
  • يوليو 2001 إلى ديسمبر 2002

İşcan Co. Inc. Istanbul - Turkey

School Constructions

Project Manager

Responsible as a Project Manager in Istanbul.

Zeytinburnu- Kazlıçeşme Abay Anatolian Girl’s High School project, which was design & built that has 28 classrooms (960 people capacity), conference hall, laboratory, a cafeteria (300 people capacity), multifunctional sport complex.

Istanbul Kağıthane Primary & Secondary School Construction project that has 30 classrooms (960 people capacity), a cafeteria (300 people capacity), multifunctional sports complex.

Project Control Engineer في 4th Army Corps 551. Fortification Building Battalion Comm.
  • تركيا - أنقرة
  • أغسطس 2000 إلى يونيو 2001

4th Army Corps 551. Fortification Building Battalion Comm. Bahçelievler - Ankara Project Control Engineer

551. Military Construction Engineering Battalion Command, Architectural Drawings of Building Constructions Yenikent and Eğirdir 2x10 A.I.T., bill of quantities, estimated accounts, prepared work schedules, purchased materials of constructions and controlled of productions.

Konya Karapınar Hotamış resort T.S.K. Region Support Application Project, prefabricated, Learning and Community Education Center Construction and covered of it.

Prepared Tender Documentations and Control, Constructions of 850 m² prefabricated Canteen and Classrooms for General Usages in Battalion

Projects and Steel Construction Calculations of Carpentry and accounting Yard offices prepared and controlled at Ankara - Polatlı Army Motor III. Degree.

Project Manager في Dekim Eng. Cons. Co. Inc
  • تركيا - إزمير
  • أغسطس 1999 إلى يوليو 2000

Dekim Eng. Cons. Co. Inc. Mersinli - Izmir

Project Manager

As a Project Manager.

Construction of Tansaş Shopping Center at Balıkesir,

Istanbul Beşiktaş Tansaş Shopping Mall Center Design & Built.

Construction of Istanbul Arnavutköy Tansaş Shopping Mall Center.

Istanbul Levent ve Kartal Tansaş Shopping Mall Centers Restoration.

All these above projects were done as Design & Built.

Bodrum Taşdibi BP Fuel-Oil Station Construction.

Performed work with an unwavering focus on safety, maintaining a safe, secure and healthy work environment.

Primary client point of contact for the above-mentioned projects.

Managed all aspects of the scopes, schedules, budgets, and quality for each of the projects.

Successfully provided for the timely completion of the contracted scope of the works.

Construction Manager في Sezer Eng. Cons. Co. Inc
  • سبتمبر 1998 إلى يوليو 1999

Izotaş Izmir Intercity Bus Terminal
• Pump advance Stations, construction of retaining walls, long distance floors etc.
• Constructed and assembled steel and buried components, huge dimension and
mass concrete applications.
• Site managing, technical safety and monthly interim payments were organized.
• Meetings and letters were organized among the Contractor-Control and Employer.
• As-builts (with AutoCad 14) and decomplete definitive works were prepared for
Contractor firm Obitaş Co. Inc.

الخلفية التعليمية

ماجستير, M.Sc. in Civil Engineering
  • في Mehmet Akif Ersoy University
  • أبريل 2020
ماجستير, MBA in Business and Management
  • في University of Bayford
  • نوفمبر 2018
بكالوريوس, Civil Engineering
  • في Balıkesir University
  • يوليو 1998

Specialties & Skills

Management
AutoCAD
Civil Engineering
Project Management
materials
operation
primavera
primavera p6
project execution
ms project
negotiation
project planning
CONSULTING
CUSTOMER RELATIONS
ENGINEERING
LEADERSHIP
MICROSOFT OFFICE
MICROSOFT WORKS
PROCUREMENT
PROJECT MANAGEMENT
QUALITY
AutoCAD
Construction Management
Management
Civil Engineering
Planning
Construction & Property

حسابات مواقع التواصل الاجتماعي

الموقع الشخصي
الموقع الشخصي

لقد تم حذف الرابط بسبب انتهاكه لسياسة الموقع. يرجى التواصل مع قسم الدعم لمزيد من المعلومات.

اللغات

العربية
مبتدئ
الانجليزية
متمرّس
الروسية
مبتدئ
التركية
اللغة الأم
الاذربيجانية
متمرّس

التدريب و الشهادات

Training of Trainer (تدريب)
معهد التدريب:
G&I Training Academy- Azerbaijan
تاريخ الدورة:
October 2021
المدة:
60 ساعة
Become a Project Coordinator (الشهادة)
تاريخ الدورة:
January 2020
Primavera P6 Project Planning and Scheduling Masterclass – Basharat Bhatti (الشهادة)
تاريخ الدورة:
January 2020
Become a Project Manager (الشهادة)
تاريخ الدورة:
January 2020
PRINCE2® Practitioner Certificate in Project Management (الشهادة)
تاريخ الدورة:
March 2021
صالحة لغاية:
March 2024
Project Management Professional (PMP) (الشهادة)
تاريخ الدورة:
February 2021
صالحة لغاية:
February 2027