Mechanical Draftsman
Suez Qatar Doha West Sewage Treatment Plant – Refurbishment Project
Total des années d'expérience :17 years, 7 Mois
Projects:
- Refurbishment of Doha West Sewage Treatment Plant (STP) Old Plant - Doha West Qatar
Responsibilities:
• Worked as Mechanical, Electrical & Civil Draftsman at Suez - Doha Qatar (supplied) and responsible for preparing General Arrangement layout, Mechanical Layout, Electrical Layout, Civil Layout, ISOMETRIC and Pipe Support.
Project Assigned
- Inlet NTRF Balancing tank
- Inlet Works & Detritors
- Sludge Thickener Tank
- Centrifuge Building
- Vortex Grit Chamber & FOG Fit
- Aeration Tank 1, Aeration Tank 2, Aeration Tank 3
- Sludge Recirculation Pumping Station RAS/SAS
Projects:
- Sewage Treatment Plant (SWTP) 12, 600cum/day - Barwa Affordable Housing
- Deep Injection Well Pumping Station - Al Muntaza Street Extension, Ashgal Project
Responsibilities:
• Worked as Electro-Mechanical Draftsman at Protec Water & Energy Doha Qatar and responsible for designing and detailing of Projects from P&ID, PFD, SLD, Civil Lay-out, Equipment Lay-out, Piping General Arrangement, Isometric, Support, Electrical Layout, As-built etc.
Projects:
- Manateq Qatar Economic Zone 1 - Admin Building
- Renovation of Bones and Joint Hamad Medical Corporation
Responsibilities:
• Worked as Mechanical Electrical & Plumbing (MEP) Design Coordinator at Leighton Contracting Qatar. Responsible in all kinds of drawings and preparation of HVAC, Plumbing, Drainage, Fire Protection, Cable Trays, Cable trunking, Cable ladder, High Voltage HV, Medium Voltage MV, Low Voltage LV and Extra Low Voltage ELV Drawings.
• Preparing Combined Services Drawing, Section details and As-built Drawings.
• Leading the CAD team to complete projects - with coordination of Project Managers Design Manager, Design Engineers and Construction Department.
• Manage different projects of different CAD files, plotting, filing, archiving, receiving and releasing.
• Studying and discussing a design project with the engineers and determining the detailed specifications of the model.
• Determining the scope of the design and choosing the initial parameters accordingly
Projects:
- Muntazah Commercial and Residential Building
- Renovation of Adadio Building
- Golden Gulf Building
Responsibilities:
• Worked as Mechanical draftsman at TEA-Iskan Group of companies Doha Qatar and responsible for drawing and preparation of HVAC, Plumbing, Drainage, Fire Fighting layout and Combined Services Drawing, Site survey, preparation of as Built Drawings, Quantity take off etc.
Water Engineering
• Worked as Electro-mechanical Draughtsman at Metito Overseas Limited, Doha Qatar and responsible for designing and detailing of Projects from P&ID, PFD, SLD, Civil Lay-out, Equipment Lay-out, Piping General Arrangement, Isometric, Support, Electrical Layout, As-built etc.
• Leading the CAD teams to complete projects - with coordination of Project Managers Design Manager, Design Engineers and Construction Department
• Manage different projects of different CAD files, plotting, filing, archiving, receiving and release
• Studying and Discussing a design project with the engineers and determining the detailed specifications of the model
• Determining the scope of the design and choosing the initial parameters accordingly
• Dividing the whole design in sufficient number of sub-parts and designing each sub-part independently
• Consulting with the engineers during the design phase and using their feedback for modification of the design
• Preparing detailed technical content describing the in and out of the draft
• Submitting the finalized design to the concerned senior officials
• Guiding the subordinates regarding efficient and effective drafting techniques
• Preparing Bill of Material, Tender drawings
• Visual Inspection at Project site, fabrication shop and reflecting mark-ups
Engineering / Supervision
• At IWI Engineering, Worked as planning assistant, at Sohar Aromatic Project Sultanate of Oman, Monitoring the daily and weekly progress
• Main tasks are to maintain deadlines, client coordination, engineering documentation, site visit, coordination with field services, supervising the installation etc.
• Assigning and managing daily plan and task for ongoing projects, dealing with main contractor, client etc.
• Responsible for preparing Rigging plan with calculation, permits and documentation
Design and Construct
• Preparing and issuing detailed drawings to fabricator base on the design required of the project's
• Submitting the finalized design to the concerned senior officials
• Guiding and supervision of fabricator
• Preparing Bill of Material, Tender drawings
• Visual Inspection at Project site, fabrication shop and reflecting mark-ups
Telecommunication Engineer
• At Net Pacific, Worked as Project Engineer, in Philippines, Monitoring the daily and weekly progress
• Main tasks are to maintain deadlines, client coordination, engineering documentation, site visit, coordination with field services, supervising the installation etc.
• Assigning and managing daily plan and task for ongoing projects, dealing with main contractor, client etc.
• Responsible for preparing permits and documentation
• Completed "Bachelor of Science in Computer Engineer (BS-CoE) ", 5 - years Degree Course, from AMA Computer University Philippines.