Client: HIB - Housing Infrastructure Board Libya / Tripoli
Water Network & Infrastructure Projects in the Eastern Part of Libya,
Shabiah, Dernah
Project value: approx. 500 Mio €
- Resident Civil Site Manager for the Infrastructure projects in the city of
Dernah, Al Qubbah, Al Abraq,
- Responsible for water distribution network, water reservoirs, sewage
network as well as storm water network (FIDIC Red Book),
- Responsible for design approval and execution work
(Implementation work of water supply network and high elevated
& ground water tanks and reservoirs
Conceptual Engineering and Design for secondary oil containments
Project value: 0, 5 Mio €
- Coordinationof conceptual engineering and system drawings in order
to update the oil pipeline and pump stations according to the WHG
2009,
- Site visits and technical advice to the client for all valve- and pump
stations along the pipeline from Italy via Austria to Germany -
Ingolstadt.
- Responsible for mass calculation, cost estimation and
investigations of variants of different execution methods,
- Developed new material items for secondary oil containments in order
to save time and money during execution,
- Developed and implemented new fixing opportunities in cooperation
with BIO-Tape Germany (welding not permitted),
Business English und
- Site supervision for the complete civil works, especially for the Roll Mill
Train (400m), Cooling Tower and Furnace area,
- Supervised execution referring all water & sewage network pipelines,
trenches, flumes, pits, ducts, etc.,
- Supervised implementation for all machine anchors & embedded parts
in accordance to the detailed machinery drawings from Siemens,
- Supervised execution for the Cooling Tower as well as for smaller water
reservoirs referring the production capacity,
- Site supervision for a water reservoir (approx. 150.00m3),
- Prepared masses & cost calculation for the Furnace, Roughing Mill,
Cooling Bed area,
- Technical support for the client in cooperation with machinery experts
from Siemens,
- Prepared weekly monitoring and progress reports
Prepared minutes of meetings
- Prepared photo documentation and collated key project
documentation
Development & Production Capacity Project
value: 10 Mio US$
-
Client: HL AG Austria
- Prepared design and construction drawings for road and railroad
bridges
- Created detail documents, feasibility studies, bills of quantity and
tendering documents
Geographic Information System for ZT Eisner GmbH Austria
GIS for 37 local Government in Styria
- Incorporated sewage water and water supply systems into digital
layout,
- Connected digital drawings and GIS data
Local Governments in Styria
- Led design and construction drawings for waste water and water
supply systems
- Prepared concepts, calculation, quotation and tendering
- Supervised execution on site
for international construction projects for industrial plants, water
transmission lines & water distribution networks.
Responsible for internal & external coordination as well as implementation of
water-, infrastructure-, and renewable energy projects
- Proposal Management
Preparation of Technical & Commercial Proposals (including complete project
cost calculation) for Water & Infrastructure projects
Internal & external coordination of proposal process
- Pre-Qualification Process
Preparation of pre-qualification documents and follow up of process with
Clients (SEC - Saudi Electricity Company, KAEC - King
and JV representative for SETEC/GAUFF/Engicon,
- Responsible for project budget, planning, implementation of project,
- Internal & external coordination of project tasks (local offices & client),
- Technical advice & support for the client (Miyahuna und Water Authority
Jordan),
- Coordination and reporting to KfW, Miyahuna & Jordan Water
Authority
- Coordination of Detail Design of complete distribution water network,
- Prepared tender documents (FIDIC Red Book) for water network
rehabilitation (Instructions for tenderer, General & Particular
Technical Specifications, Bill of Quantities, etc.), as well as
rehabilitation for water reservoirs in the project area (250.000 m3),
- Approval for all design drawings,
- Prepared all kind of reports (technical reports & advise, monthly-
and quarterly progress reports) for client and KfW,
- Scheduling General Project Time schedule,
- Monitoring and updating detailed time schedule during the tender
phase,
- Document controlling
Project value: 150 Mio US$
Project value: 2 Mio US$
-