Performing pipeline & process facilities services like Pumping, Nitrogen services, pigging, drying, hydrostatic test, leak test, oil flushing, chemical cleaning and flanges management.
Performing Nitrogen service as N2 unit operator.
Select rotary equipment (pumps and compressors), generators, Nitrogen equipment, valves, special pipe pieces and tools suitable to job requirements.
Reviewing tender's documents and P&IDs.
Visiting sites to complete missing data.
Preparing specifications for the required equipment.
Preparing technical proposals and job procedures according to tender's specifications and job requirements.
Preparing all technical data and providing technical support for operation team.
Participation in companies' registration and audits preparation steps.
Main Projects
United Gas Derivatives Co. (UGDC) - Complete NGL Plant Shut Down
Performing Nitrogen purge, mechanical services, pressure test and leak test for processes facilities (plant boundaries, mol. sieve dryers, dried gas filters, mercury removal vessel, expander feed separator, gas/liquid cold box, demethanizer, demethanizer reboiler, depropanizer, depropanizer reboiler, NGL surge drum and cold hydrocarbon drains drum) existing at UGDC natural gas liquids (NGL) plant during shut down.
ESTYRENICS - Polystyrene Production Plant Pre-commissioning
Performing pre-commissioning activities like drying, pneumatic gross leak test (GLT), commissioning leak test (CLT), vacuum leak test (VLT), Nitrogen purge and retro-jetting for the processes facilities and piping systems existing at polystyrene production plant.
PETROBEL - New Land Oil Treatment Train Pre-commissioning
Performing pre-commissioning activities like pneumatic gross leak test (GLT), commissioning leak test (CLT) and Nitrogen purge for the crude oil processing facilities (three phase separator, crude oil heat exchangers, land oil train gas boot, thermal oil expansion vessel, thermal oil sump), tanks, fuel system, piping and suction & discharge piping of crude oil transfer pumps & thermal oil circulation pumps existing in the new land oil treatment train.
PETRODARA - OIL PRODUCTION COMPANY at RAS GHAREB EASTERN DESERT
Injecting water to the wells using injection fluid pump
BAPETCO - BADR 3 Gas Plant Shut Down
Performing Nitrogen pumping to plant facilities during shut down
BAPETCO - EL-OBAYED Gas Plant Shut Down
Performing Nitrogen pumping to plant facilities during shut down.
PETROBEL - DENISE-B Development Project - Offshore Deep Water new
(DENISE 4 / TUNA) Pipeline Commissioning
Performing dewatering, drying and nitrogen purging for (16”/ 6.5km) subsea pipeline.
BAPETCO - NEAG 1
Crude Oil Pumping using Triplex Pumps
KHARAFI NATIONAL - EGYPT - KN West DAMIATTA Project
Pre-Commissioning Activities of Underground piping for Fuel gas System
PETROSILAH - ELFAYOUM Plant
Cleaning using Coiled Tubing for totally plugged pipeline
HASSAN ALAM HOLDING - AIN SUKHNA Plant
Air Blowing Activities and Nitrogen Pressure Test for Process Lines
PETROBEL - New Land Oil Treatment Plant ABO-REDIES
Pre-Commissioning Services for New Land Oil Treatment Train
UNITED GAS DERIVATIVES COMPANY - UGDC Damietta Export Facilities
Pre-Commissioning for the New Extension of Damietta Project
Khalda Petroleum Co. (KPC) - AKIK Gas Plant Commissioning Project - Gas/Glycol Contactor Chemical Cleaning
Performing chemical cleaning to remove 20% hydrocarbons scale and 80% heavy iron oxide scale from gas/glycol contactor tower existing at KPC AKIK gas plant.
GUPCO - Ramadan 6 (Rehabitation Project)
Performing pre-commissioning activities like pneumatic gross leak test (GLT), commissioning leak test (CLT) and Nitrogen purge.
BAPETCO - Assil & Karam Project
Performing Flange management, Air blowing, Air flushing, Performing pre-commissioning activities like pneumatic gross leak test (GLT), commissioning leak test (CLT) and Nitrogen purge.
- مجال الشركة:
- النفط والغاز
- الدور الوظيفي:
-