Work Experience

Total years of experience :34 years, 3 Months

Sr. Projects Manager at Canal Co. For Electricity Distribution
  • Egypt - Ismailia
  • My current job since June 2018

Technical Affair Sector, Technical Review & Protection Department, Testing Department Manager

1. Review Electrical Equipment’ Technical Specification.
2. Committee Member for studying & issuing “Electrical Equipment Technical Specifications”
3. Committee Member for Check, Factory Test and Handing over All Transformer types.
4. Electrical Equipment’ tendering member for checks and analyzing.
5-Testing Department Manager' duties

Senior Projects Manager at Al Mashariq Trading &Contracting Co
  • Saudi Arabia - Eastern Province
  • June 2011 to June 2018

1. Responsible for safe delivery of project to all constrains, such quality, schedule, risk and cost.
2. Manage project teams & activities from project initiation, design, execution, control and closing.
3. Providing leadership to internal project stakeholders.
4. Manage the project costs and create monthly reports, including profit/ loss.
5. Maintaining customer relationship to achieve long term retention and satisfaction.
6. Reporting project progress to a project ‘sponsors.
7. Promptly QHSE compliance at every opportunity.
8. Issuing Purchase Orders after, technical’ approval & financial comparisons and negotiations.
9. Coordinating personnel and managing subcontractors.
10. Identifying project risks and planning with appropriate people to resolve them.
11. Responsible for project definition, process management, documentation and resource allocation.
12. Utilizing my practical construction’ experiences relocating to site -after successfully completing engineering phase-for following up site construction activities, support construction team and solving site issues.
Both Projects were successfully energized at TIME.

Project Manager at : ThyessenKrupp-Xervon (EGY)
  • Egypt - Port Said
  • July 2009 to June 2011

ThyessenKrupp-Xervon (EGY)
PDH-PP (Port Said.-Egypt) Petrochemicals
TCI-Sanmar (Port Said.-Egypt) Petrochemicals

1. Initiates, manage & follow up the electrical erection teams & their activities (Transformers, MV switchgears, LV Panels, MCC, Cables pulling, Cables trays, Workshops & LC.) (PDH-PP)
2. Initiates & follow up Instruments erection, test, commissioning and loop check teams & their activities. (TCI)
3. Issue the erection punch list and follow up. (PDH-PP/TCI)
4. Follow up the Instruments installations activities. (PDH)
5. Arrange, handle and follow up the I CAPS & teams. (PDH)
6. Contribute the Weekly Construction Meeting. (PDH-PP/TCI)
7. Contribute the Daily site Meeting. (PDH-PP/TCI)
8. Check up the project time schedule. (PDH-PP)
9. Issue the monthly progress invoices and reports. (PDH-PP/TCI)
10. Issue the monthly stores reports & requests. .(PDH-PP/TCI)
11. Initiates & Interview the new staff.
12. Check monthly site cost control.
13. Negotiates with subcontractors.

Project Manager at Offshore platforms (Alex) ENNPI-
  • Egypt - Port Said
  • December 2007 to July 2009

1. Check up the erection activities (transformers, MV switchgears, LV &LC panels).
2. Site construction advisor (onsite technical support).
3. Issue the erection punch list and follow up.
4. Issue the pre-commissioning activities.
5. Attended the startup activities.
6. Issue engineering comments and TQR.
7. Issue and did modifications for MV and LV switchgears.
8. Contribute the Weekly Construction Meeting.
9. Contribute the Daily site Meeting.
10. Checkup offshore punch list and start up.

site project manager at ABB
  • Libya - Benghazi
  • October 2006 to December 2007

Greatest Manmade River (Sluq-LIBYA), 319 &318Projects.
1. Check up the erection activities (Transformers, MV Switchgear, LV Panels, MV Pumps, cables & SCADA panels).
2. Commissioning the Low voltage networks, Switchgear, Main Incomers, etc.
3. Preparing to commission Medium Voltage Switchgear.
4. Energizing the whole pump station (MV and LV), Start up and put into service all loads.
5. Maintenance and trouble shouting for the old pump station.
6. Issue the maintenance manual for old pump station (11 and 3.3KV switchgears).
7. Issue and did modifications for MV and LV switchgears.
8. Operation and maintenance of pump station.
9. Contribute the Daily and Weekly Construction Meetings.
10. All project manager’ tasks for Project, 319.
(Mission) Instrumentation & Automation

Project Manager(mission) at Lafarge Surma Cement LSC (Chahtak- Sylht)
  • Bangladesh
  • June 2006 to September 2006

Main areas of responsibilities:-
1. Check up the erection activities.
2. Lead a team for checking and testing.
3. Check and test the Automation systems.
4. Issue the Acceptance protocol from the point of view for Instruments and Automation.
5. Issue and follow up the Punch List items.
6. Issue a few Automation modifications.
7. Contribute the Weekly Construction Meeting with the construction companies.

at Personal Private Contracting Company EG for Contracting&Trading
  • United Arab Emirates
  • September 2005 to June 2006

Main areas of responsibilities:-
1. Responsible for safe delivery of project to all constrains, such quality, schedule, risk and cost.
2. Manage project teams & activities from project initiation, design, execution, control and closing.
3. Providing leadership to internal project stakeholders.
4. Manage the project costs and create monthly reports, including profit/ loss.
5. Maintaining customer relationship to achieve long term retention and satisfaction.
6. Reporting project progress to a project ‘sponsors.
Page 3 of 5/ku19/9
7. Promptly QHSE compliance at every opportunity.
8. Issuing Purchase Orders after, technical’ approval & financial comparisons and negotiations.
9. Coordinating personnel and managing subcontractors.
10. Identifying project risks and planning with appropriate people to resolve them.
11. Responsible for project definition, process management, documentation and resource allocation.
12. Contribute the Weekly Construction Meeting with the project ‘sponsors.
13. Contribute the Weekly T&C Meeting with the project ‘sponsors, including modification.
14. Handing over safely& at time with all constrains.

Project Manager at ABB
  • Libya - Benghazi
  • July 2005 to September 2005

Greatest Manmade River (Sluq-Libya)-LIBYA), 319 &318Projects.
1. Check up the erection activities (Transformers, MV Switchgear, LV Panels, MV Pumps, cables & SCADA panels).
2. Commissioning the Low voltage networks, Switchgear, Main Incomers, etc.
3. Preparing to commission Medium Voltage Switchgear.
4. Energizing the whole pump station (MV and LV), Start up and put into service all loads.
5. Maintenance and trouble shouting for the old pump station.
6. Issue the maintenance manual for old pump station (11 and 3.3KV switchgears).
7. Issue and did modifications for MV and LV switchgears.
8. Operation and maintenance of pump station.
9. Contribute the Daily and Weekly Construction Meetings.
10. All project manager’ tasks for Project, 319.

site project manager at SNAMPROGETTI
  • Libya - Zawiya
  • January 2005 to June 2005

BENTINI Construzioni S.p.a (LIBYA)
Mellitah Gas Plant (Western Libya Gas Plant)-LIBYA

1. Issue, manage & follow up E&I Installation activities (transformers, MV switchgear, LV panels, cables & fire systems).
2. Issue the time activities schedule.
3. Issue the daily, weekly and monthly Reports.
4. Issue and Control the monthly Progress.
5. Issue and Control the working Plan.
6. Contribute the Weekly Progress Meeting (SNAMPROGETTI)
7. Control the Working Activities.
8. Contribute the Weekly Internal Construction Meeting.
9. Issues & check the change orders.
10. Issues the stores requests.

Electrical Testing and Commissioning M at Cegelec
  • Egypt - Cairo
  • June 2004 to December 2004

Power Station
750 MW Combined Cycle Project-Cairo-Egypt
1. Follow up & Checkup the installation activities, GIS, Power Transformers, MV SWGR, Load Centers, MCC, Low
current, ..etc.
2. Commissioning activity concerning GIS, Main and Aux. Power Transformers, M. V .Switchgears, L.V. Load Centers,
Protection and MCC.
3. Attending the daily start-up meeting for reporting the current activities and cooperation between other contractors.
4. Attending the weekly chairman meeting for updating the activity schedule and works programs.
5. Attending the weekly Progress meeting for updating the activity schedule and works programs and solving the
present problems.
6. Schedule and managing the works activity program.
7. Studying and giving a technical solution for mall designed items such as (Transformer protection system
arrangement and DC system configuration).
8. Startup activity for all equipment, motors, panels…. etc.
9. Trouble shouting during reliability runs periods.
10.Calibrations of all instrumentations devices.

Construction manager at Siemens Limited
  • Egypt - Alexandria
  • June 2002 to June 2004

Industrial Solution & Services
E.G.METAL IND. site-Ismailia-free zone
1. Issue, manage & follow up E&I Installation activities (transformers, MV switchgear, LV panels, Cables (MV&LV),
fire systems & LC).
2. Issue the daily, weekly and monthly Reports.
3. Issue and Control the monthly Progress.
4. Issue and Control the working Plan.
Page 4 of 5/ku19/9
5. Contribute the Weekly Progress Meeting.
6. Control the Working Activities.

Senior Engineer at Siemens Limited Industrial Solution & Services IDKU-LNG site-RASHEED (BECHTEL) Q
  • June 1999 to June 2002

mission)
HEBI for pharmaceutical raw materials (Qena free zone- Egypt) Construction manager/ Commis. & Start up manager

Engineer at ANSALDO industria (Italian company) EL-KURIEMAT Thermal power station (2x650 MW)-Upper Egypt- El -Gable El-Asfar waste water treatment plan
  • Egypt
  • September 1997 to June 1999

Main areas of responsibilities:-
1-Testing and putting into service the medium voltage switchgear and all related protective device and relays.
2-Testing and putting into service the motor control center (MCC), (110 V DC. Battery, Battery charger and UPS),
protection relays & alarm for main, aux. and starts up power transformers.
3-Loop check for all pneumatic & motorized boiler valves.
4-Testing and putting into service the medium voltage switchgear (ABB type) and all related protective devices
and relays.
5-Testing and putting into service the low voltage switchgear and all related equipment.
6-I was in mission to test and putting into service the protection relays, CTs...Etc.-for Unit #1.
Also, testing and putting into service all motorized and pneumatic Boilers valves and interface with DCS system.

Maintenance Engineer at EL-SAGRI establishment for trading and contracting
  • United Arab Emirates
  • July 1995 to June 1996

Main areas of responsibilities:-
1-Maintenance engineer for the medium and low voltage networks in King Saud University.
2-Maintenance engineer for the medium and low voltage networks and site equipment in Waste Water treatment
plant, Tower pump station & raw water treatment plant for the National Guard project

Commissioning Engineer at CANAL ELECTRICAL DISTRIBUTION COMPANY
  • Egypt - Ismailia
  • March 1991 to July 1995

-Maintenanace engineers for medium & low voltage networks.
2-Member of committee for check and test the electrical equipments (kiosks, switchgear, cables (low & medium), RMU, .etc.).
3-Member of committee for making the technical specifications of the electrical equipments (Kiosks, Switchgear, cables…).
4-Testing for Cables, Kiosks & switchgears.
5-Determine the faulty cables - faulty cables van operator.

Maintenance and operation engineer at CANAL ELECTRICITY ZONE
  • United Arab Emirates
  • May 1990 to March 1991

Main areas of responsibilities:-
1-Maintenance and operation engineer for Nwebaa Diesel power station-South Sinai (3x3.2 MW).
2-Training in gas power station (1x28MW-Ismailia gas station

Maintenance engineer
  • December 1988 to May 1990

company-in Ismailia

Education

Bachelor's degree, Engineering
  • at Zagazig University
  • June 1983

University Banha-branch. Power & electrical machines - May1988 (General Grade: Good / Project: Very good; named: Control of power system by Using microprocessor)

Specialties & Skills

Turnkey Projects
Electrical Installation
Electrical Engineering
Electrical Testing
Construction & Property
CABLEADO
CLOSING
DELIVERY
DOCUMENTATION
FINANCIAL
LEADERSHIP
MANAGEMENT
NEGOTIATION
NETWORKING
project execution
procurement
ms project
project planning

Social Profiles

Personal Website
Personal Website

URL removed due to policy violation. Please contact support for further information.

Languages

Arabic
Expert
English
Expert
French
Beginner
German
Beginner

Memberships

PMI
  • PMI' membership since 2012, registration no.238 7774
  • February 2012

Training and Certifications

Online Break the chain of COVID-19 infection (Training)
Training Institute:
MBUR
Date Attended:
April 2020
Online Marketing Fundemantals (Training)
Training Institute:
google
Date Attended:
July 2017
Project Management Professional (Training)
Training Institute:
SAC Training-Jeddah KSA.
Date Attended:
August 2012
Duration:
35 hours
Protection relay &circuitbreaker (Training)
Training Institute:
Cairo University-Faculty of Engineering
Date Attended:
July 1997
Duration:
35 hours
Protection relay &circuitbreaker (Training)
Training Institute:
Cairo University-Faculty of Engineering
Date Attended:
July 1997
Duration:
35 hours
Demand side management (Training)
Training Institute:
Cairo University-Faculty of Engineering
Date Attended:
July 1996
Electrical installations in building &factories (Training)
Training Institute:
Cairo University-Faculty of Engineering
Date Attended:
May 1995
Duration:
35 hours
Using capacitors in electrical power system (Training)
Training Institute:
Cairo University-Faculty of Engineering
Date Attended:
June 1993
Duration:
35 hours