My major responsibilities include:
• Bid evaluations, technical questionnaire and technical bid analysis.
• Design calculations.
• Supplier and layout drawings review and comments.
• Progress report etc...
For projects like: Mega train LNG plant, Ammonia and fertilizer plants, Ethane recovery plant…etc.
Head of maintenance service, SOBRIMER subsidiary.
• Responsible for the curative and preventive maintenance of equipments and facilities.
• Responsible for the optimal use of production means and their preservation.
Head of Supervision service, Mers El-Kébir III project (construction of brick factory).
Responsible of supervision of utilities installations such as:
• Electricity: (MV/LV Substation 3 x 630KVA, LV supply and connections, electrical assembly, wiring of switchboards and motor control centers).
• Gas: Installation of L.P.G. facilities.
• Compressed air: Installation of compressors and air facilities.
• Water process station and fire protection network.
• Supervision of the no-load tests and semi-industrial tests of whole plant in collaboration with manufacturer supervisors (CERATEC-Belgium).
Methods office engineer.
My major responsibilities included:
• Preparation of planning’s of operations realization.
• Enumeration of means: human, material and financial necessary to the realization of operations in the best conditions.
Degree of electrotechnical engineer - electric machines- • Thesis: “Study of a law voltage frequency (U/F) to maintain the overload capacity of an asynchronous motor constant”