• Follow up constructions activity and erection activities.
• Follow up and inspection for fabrication (Material, dimension, welding, painting).
• Perform NDT according to standards and project specifications.
• Perform internal auditing for factory sectors according to ISO. 9001:2000
• Follow up and review time schedule of projects.
• Witnessing Hydro testing as per applied specifications and approved procedures.
• Check coating and/or painting as per applied specifications and approved procedures.
• Material Receiving.
• Responsible for all the duties of the welding inspector before, during and after welding
• Welder Qualification with Conformance the applicable codes and standards
• Weldments Pre-weld inspection Verification that dimensions Fit-up and weld preparations are in accordance with the engineering drawings and applicable code
• Follow up and inspection for fabrication (Material, dimension, welding, painting).
• Perform NDT according to standards and project specifications.
• Perform internal auditing for factory sectors according to ISO. 9001:2000
• Follow up and review time schedule of projects.
• Witnessing Hydro testing as per applied specifications and approved procedures.
• Check coating and/or painting as per applied specifications and approved procedures.
• Material Receiving.
• Responsible for all the duties of the welding inspector before, during and after welding
• Welder Qualification with Conformance the applicable codes and standards
• Weldments Pre-weld inspection Verification that dimensions Fit-up and weld preparations are in accordance with the engineering drawings and applicable code
September 2008
To Present
Quality control Inspector
at Hassan Allam Construction - Steel Fabrication Factory
Location :
Egypt - Alexandria
Hassan Allam Construction - Steel Fabrication Factory
Position: Quality control Inspector
From: Jan 2009-Until now
Duties:
• Follow up constructions activity and erection activities.
• Follow up and inspection for fabrication (Material, dimension, welding, painting)
• Perform NDT according to standards and project specifications.
• Perform internal auditing for factory sectors according to ISO. 9001:2000
• Follow up and review time schedule of projects.
• Witnessing Hydro testing as per applied specifications and approved procedures.
• Check coating and/or painting as per applied specifications and approved procedures.
• Material Receiving.
• Responsible for all the duties of the welding inspector before, during and after welding
• Welder Qualification with Conformance the applicable codes and standards
• Weldments Pre-weld inspection Verification that dimensions Fit-up and weld preparations are in accordance with the engineering drawings and applicable code
Position: Quality control Inspector
From: Jan 2009-Until now
Duties:
• Follow up constructions activity and erection activities.
• Follow up and inspection for fabrication (Material, dimension, welding, painting)
• Perform NDT according to standards and project specifications.
• Perform internal auditing for factory sectors according to ISO. 9001:2000
• Follow up and review time schedule of projects.
• Witnessing Hydro testing as per applied specifications and approved procedures.
• Check coating and/or painting as per applied specifications and approved procedures.
• Material Receiving.
• Responsible for all the duties of the welding inspector before, during and after welding
• Welder Qualification with Conformance the applicable codes and standards
• Weldments Pre-weld inspection Verification that dimensions Fit-up and weld preparations are in accordance with the engineering drawings and applicable code
October 2012
To September 2013
اخصائي رقابه جوده
at EHC LDAN Plant
Location :
Egypt - Alexandria
10 EHC LDAN Plant Egypt Hydrocarbon Company UHDE (KBR) 6000 Scheduled 2012-2013
September 2012
To July 2013
اخصائي رقابه جوده
at L'Oreal Cosmetics Plant
Location :
Egypt - Alexandria
9 L'Oreal Cosmetics Plant L'Oréal Egypt Hassan Allam Construction 1000 Scheduled 2012
July 2011
To June 2012
اخصائي رقابه جوده
at Beet Sugar Plant & Refinery
Location :
Egypt - Alexandria
7 Beet Sugar Plant & Refinery Savola Group Hassan Allam Construction 3000 2010-2011
8 El-Ain El-Sokhna 2X 650 MW Supercritical Thermal Power Plant East Delta Electricity Production Company (EDEPC) Hassan Allam Construction - CCC (Pgesco) 3000 2011
8 El-Ain El-Sokhna 2X 650 MW Supercritical Thermal Power Plant East Delta Electricity Production Company (EDEPC) Hassan Allam Construction - CCC (Pgesco) 3000 2011
January 2008
To January 2009
Main Contractor
at Egyptian Propylene & Polypropylene Co
No Project Name Client Main Contractor (Consultant) Total Tonnage (TON) Year of Achievement
1 Egyptian Propylene & Polypropylene Co. Egypt's Oriental Petrochemicals Company And The Egyptian Petrochemicals Holding Uhde Gmbh. 2200 2008-2009
1 Egyptian Propylene & Polypropylene Co. Egypt's Oriental Petrochemicals Company And The Egyptian Petrochemicals Holding Uhde Gmbh. 2200 2008-2009
January 2000
To December 2000
Main Contractor (Consultant)
at Hassan Allam Construction
Location :
India
No Project Name Client Main Contractor (Consultant) Total Tonnage (TON) Year of Achievement
2 Ain El-Sokhna Glass Factory Saint Gobian Hassan Allam Construction 2000 St. St. - 500PW 2009
3 Egyptian Agrium Nitrogen Products Company - Fertilizers Complex Agrium Uhde Gmbh. 500 2009
4 Arabian Cement Company - Line 2 Arabian Cement Company HAC (Reliance Heavy Industries) 750 PW - 500 St.St. 2009
5 National Theater Culture Ministry Hassan Allam Construction 200 2010
6 Mall of Arabia in Cairo The Egyptian Centers for Real Estate Development Company Hassan Allam Construction *JV* Orascom Construction 1000 2010
2 Ain El-Sokhna Glass Factory Saint Gobian Hassan Allam Construction 2000 St. St. - 500PW 2009
3 Egyptian Agrium Nitrogen Products Company - Fertilizers Complex Agrium Uhde Gmbh. 500 2009
4 Arabian Cement Company - Line 2 Arabian Cement Company HAC (Reliance Heavy Industries) 750 PW - 500 St.St. 2009
5 National Theater Culture Ministry Hassan Allam Construction 200 2010
6 Mall of Arabia in Cairo The Egyptian Centers for Real Estate Development Company Hassan Allam Construction *JV* Orascom Construction 1000 2010
Share on Facebook