Provide Technically excellence and innovative solutions, for adding value for substations
Site setup, Execution of works as per L2 Schedule & Electrical Drawings/Standards.
Managing end to end co-ordination between various Engineering Department from planning to monitor on-site activities and final execution of the project without any delay in the project schedule.
Certification of measurements and invoices raised by contractors as per mode of payment defined in contract.
Effective implementation of all the Health, Safety & Environment standards as per the Algihaz Holding and Suaudi Electricity Company guidelines at site.
Informing the site status, site issues and other project related issues to customer and different internal departments for early completion of project.
Responsibilities & Experience:
Provide Technically excellence and innovative solutions, for adding value for substations
Site setup, Execution of works as per L2 Schedule & Electrical Drawings/Standards.
Managing end to end co-ordination between various Engineering Department from planning to monitor on-site activities and final execution of the project without any delay in the project schedule.
Certification of measurements and invoices raised by contractors as per mode of payment defined in contract.
Effective implementation of all the Health, Safety & Environment standards as per the ABB and customer guidelines at site.
Informing the site status, site issues and other project related issues to customer and different internal departments for early completion of project.
Preparation of field quality Plan.
Preparation of Work Method Statement and Risk Assessment each and every activity.
Preparation of Daily, Weekly and monthly progress reports for daily monitoring of the project for the information of top management.
Erection of 765/400KV, 400/220KV Substations. (Towers, Equipment Structure, Stringing, Equipments, Aluminum Tube erection)
Installation of 333MVA, 315MVA, Transformers, 110MVAR, 63MVAR, 50MVAR, 80MVAR Reactors, CT, CVT, ISOLATOR, LA, 630KVA & 800 KVA Auxiliary Transformers, Control & relay panels, PLCC Panels, LT Switchgear, Battery and Battery charger.
Transformer and Reactors Oil filtration and filling in tank.
Cable laying and Termination of Control and Power Cables.
Installation of substation Earthing system.
Erection, Testing and commissioning of outdoor and indoor illumination system.
Erection, Testing and commissioning of Fire protection system, AC & Ventilation system.
Co-Ordination with testing and Commissioning Team.
Installation of overhead equipment like cantilever assembly contact wire, catinary wire.
Installation of BG-2 type foundation for railway mast.
Installation of mast like Portal, BFB for OHE.
Co ordination with design team with respect to actual condition at site.
Railway station Lighting.
Understand the Scope of Work ( PO & BOQ).
Assisting the Project Manager in Planning of Complete Phase of the Project.
Helping in resolving Different Day to Day problems arising at site during execution of project.
Preparation of Monthly Progress Reports for daily monitoring of the project for the information of top management.
Co-ordination & organizing Project Review Meeting.
Erection of Dry Type Transformers & (Transformer 33KV/440V) of indoor Sub-stations.
Erection of 33kv, 11kv HT panel and 415v LT panel.
Erection in Position, Installation of Rising Mains, Bus Ducts, Cable Tray and Raceway.
Arrangement of Earthing.
Conduiting and Internal Wiring complete with Light FittingsAnd Other Accessories.
Laying of HT & LT Cables & Terminations of Cables.
Co ordination with design team with respect to actual condition at site.