Mohammed Arifuddin Hussain, Senior Electrical Engineer (HV)

Mohammed Arifuddin Hussain

Senior Electrical Engineer (HV)

Al Habtoor Leighton Specon LLC

البلد
الإمارات العربية المتحدة - أبو ظبي
التعليم
بكالوريوس, Electrical Engineering
الخبرات
16 years, 8 أشهر

مشاركة سيرتي الذاتية

حظر المستخدم


الخبرة العملية

مجموع سنوات الخبرة :16 years, 8 أشهر

Senior Electrical Engineer (HV) في Al Habtoor Leighton Specon LLC
  • الإمارات العربية المتحدة - أبو ظبي
  • ديسمبر 2009 إلى مايو 2013

Working with Al Habtoor Leighton Specon LLC
Senior Electrical Engineer (HV)
From Dec 2009 to Present
Reporting to the senior project manager.

Responsible for all site activities such as installation of LV & HV cable laying, switchgears,
Transformers & other electrical equipment and substations associated works including testing and commissioning.

Installation of fiber optic and control cable for communication, protection and monitoring purpose of HV feeders and switchgears.

Carefully studying the approved electrical design & schematic drawing and executing the work
accordingly.

Coordinating with client, consultant and various Dept. of ADDC for site inspections & approvals,
getting NOCs & Clearance from ADDC and other relevant Govt.department for substations & Electrical system Energisation,

Execute all the works as per ADDC & other Govt. Dept. specifications & regulations, Supervising,
collecting and clearing ADDC safety Documents during the process of substation energization.

Preparing material submittal document for ADDC submission & approval.

Assisting in preparation of shop drawings as well as As-Built drawing for ADDC submissions & approvals,

Estimation of materials, man power and machineries as per projects requirement,

Co-ordinating with client, consultant, ADDC, & other Govt. Dept. during the process of execution
& completion of project.


Worked with M/S Ranya Contracting Est.

Consultant في SEHA
  • الإمارات العربية المتحدة
  • يناير 2012 إلى مايو 2013

Client: SEHA
Consultant: BURT, HILL
Contractor: Al Habtoor Leighton Specon LLC.
Duration of work: From Jan 2012 to till date.

Project Scope:
Installation of 22kv HV switchgear panels, Transformers and HV cables and energization of 1no. SWS-Station & 12 nos. substations and permenant power supply to Zayed University,
Khalifa city -B

Consultant في MUBADALA
  • الإمارات العربية المتحدة
  • سبتمبر 2010 إلى ديسمبر 2011

Client: MUBADALA
Consultant: AECOM/Parsons International.
Contractor: Al Habtoor Specon/Hastie international.
Duration of work: From to Sep 2010 to Dec 2011

Project Scope:
Installation of 22kv HV switchgear panels, Transformers and HV cables and energization of 5 nos. 22kv substations in PARIS SORBONNE UNIVERSITY. Al Reem Island.

Consultant في MUBADALA
  • الإمارات العربية المتحدة
  • ديسمبر 2009 إلى سبتمبر 2010

Client: MUBADALA
Consultant: Parsons International.
Contractor: Al Habtoor Specon LLC.
Duration of work: From Dec 2009 to Sep 2010

Project Scope:
Cable installation work for the connections of bulk consumers in eastern region Abu Dhabi
Emirate. Installation work of 33kv and 11kv underground XLPE cable installation associated
Equipments and testing and commissioning as per ADDC specification interconnect
With existing circuit

Contract: D - 9649

Site Engineer في Ranya contracting Establishment.
  • الإمارات العربية المتحدة - أبو ظبي
  • أكتوبر 1996 إلى ديسمبر 2009

Site Engineer.
From Dec 2007 to Dec 2009.
Site In-Charge
From Aug 1996 to Nov 2007
Reporting to the project manager.

Responsible for all site activities such as Erection of 33kv and 11kv overhead Line, Street lighting
works.

Installation of HV & LV panels and 11kv 33kv package unit substation, Transformers, Tee Ring
main unit, Feeder pillar, Service Turret and laying of HV & LV cables and associated works.

Execute all the works as per the work order issued by the Client according to their specification.

Assisting in preparation of shop drawings as well as built drawings.


Preparing joint measurement after the completion of work and get certified by the concerned
engineer for preparing the progress payment.

Supervise site survey works
Estimation of materials, man power and machineries.

Testing of 33kv & 11kv cable and Electrical equipment.

PROJECT INVOLVED
Project Scope:
Installation of 22kv HV switchgear panels, Transformers and HV cables and energization of 5 nos. substations and permenant power supply to New Mafraq Hospital - Mafraq,
Abudhabi.

Electrical site incherge, Electrical site Engineer & Electrical project Engineer. في RANYA CONTRACTING ESTABLISHMENT.Y
  • الإمارات العربية المتحدة - أبو ظبي
  • أكتوبر 1997 إلى ديسمبر 2009

Substation installation, OHL Tramission line installation upto 33kV.

Electrical site Engineer في Ranya contracting Establishment.
  • الإمارات العربية المتحدة - أبو ظبي
  • أغسطس 2008 إلى ديسمبر 2009

Client: ADDC
Contractor: Ranya Cont. Est
Duration of work: From Aug 2008 to Dec 2009


Project Scope:
Supply & installation of 33/11kv overhead pole line and associated equipment (Lot-1) and testing and commissioning as per ADDC specification, interconnect with existing circuit.

Contract: A -3877

Contractor في Ranya contracting Edtablishment.
  • الإمارات العربية المتحدة - أبو ظبي
  • أكتوبر 2006 إلى ديسمبر 2008

Client: AADC
Contractor: Ranya cont. Est.
Duration of wor: Feb 2008 t0 Aug 2008
Project Scope:
Al Reem Island Development, 11kv Temporary network: Laying of 75 km 11kv
underground cables, Installation of 42 nos of 11/.415kv package unit substations and 5 nos.
QRM in Reem island including testing and commission of 11kv cables, package units and
QRMs. Bringing temporary 11kv power network from ADDC E 19 Pry.

Consultant في ADDC/BUNYA
  • الإمارات العربية المتحدة - أبو ظبي
  • أبريل 2006 إلى فبراير 2008

Client: ADDC/BUNYA
Consultant: PARSONS International
Contractor: Ranya Cont. Est.
Duration of work: Apr 2006 to Feb 2008
Project Scope:
North East BAB-Phase 1 Development Project. ( Al Dhabiya & Rumaitha oil field)
Installation of 7 kms 33kv steel lattice tower line in Dhabiya. Erection of 63 kms wooden
pole 33kv overhead line including OPGW line and feeding power supply to Rumaitha oil
field wells.

Electrical site Incharge. في Ranya contracting Establishment.
  • الإمارات العربية المتحدة - أبو ظبي
  • ديسمبر 2004 إلى أبريل 2006

Client: ABUDHABI OIL COMPANY. (ADCO)
Main Contract: Technip/NPCC
Sub-contractor: Ranya Cont. Est.
Duration of work: Dec 2004 to Apr 2006
COMPUTERS SKILLS
MS Office 2003/2007.
Adobe Acrobat Reader
Internet.
MS Internet Explorer
MS Out Look

الخلفية التعليمية

بكالوريوس, Electrical Engineering
  • في Vinayaga research & foundation university.
  • مارس 2007

B.Tech ( Electrical Engineering )

Specialties & Skills

Facilities
Consultant Coordination
Estimating
Project Execution
Coordination
ENGINEER
ESTIMATION
FIBER OPTIC
OVERHEAD LINE
PROJECT MANAGER
SHOP DRAWINGS
SUBSTATION
SUBSTATIONS
TESTING

اللغات

الهندية
مبتدئ
الملايام
مبتدئ
الأوردو
مبتدئ
العربية
مبتدئ
الانجليزية
مبتدئ
التاميلية
مبتدئ

التدريب و الشهادات

NEBOSH- HSE (British standard ) (الشهادة)
تاريخ الدورة:
May 2008
صالحة لغاية:
December 2025