Construction Manager
Al-Jazeera Al-Arabia Contracting Co. Ltd
مجموع سنوات الخبرة :15 years, 7 أشهر
Project: 2nd
Ring Road Intersection Al Beban Makkah
Underpass Bridge
with box section
with MSC Wall Box
Culverts & Drainage
System)
CLIENT : Ministry Of
Transport -
Kingdom Of Saudi
Arabia
CONSULTANT : Khatib & Alami
PROJECT
VALUE
450, 000, 000.00 SAR
STATUE Under progress
Foam work, Reinforcement & Casting of Cast-in-Situ Piles of
24 Open Channel.
* Foam work, Reinforcement & Casting of Precast Girder of 25
m length each.
* Foam work, Reinforcement& Casting of Retaining Walls for
Under Pass Tunnel,
* Road Pavement Structure specially in Low Bearing Capacity,
Soil Stabilization using Geo Grid & Geo Textile Procedures.
* Supervising Asphalt activities, spraying prime coat, tack coat,
& laying of bituminous base course as per specified drawings.
* Preparation of weekly programmed targeted and achieved.
Started as a junior site engineer responsible for documents
and assisting senior engineers and promoted to site engineer
after six months.
* Responsible for carrying out structural markings and general
site supervising.
* Preparing BBS, checking out reinforcement details according
to design and specification.
* Allocating work to sub-contractors and preparing their
monthly bills.
* Participated actively in weekly/biweekly site meetings to
discuss:
* Project construction progress, Construction schedule and
safety precautions
* Preparing and Assisting in Periodic Inspection of Consultant
and Authorities respectively
Confidentiality, Sincerity & loyalty, Dedication LANGUAGE KNOWN 90%