Irfan  Parvaz, Electrical Engineer

Irfan Parvaz

Electrical Engineer

Jones Lang Lasalle ((JLL) V3 ME)

البلد
المملكة العربية السعودية - الرياض
التعليم
بكالوريوس, Electrical &Electronics Engineering
الخبرات
13 years, 2 أشهر

مشاركة سيرتي الذاتية

حظر المستخدم


الخبرة العملية

مجموع سنوات الخبرة :13 years, 2 أشهر

Electrical Engineer في Jones Lang Lasalle ((JLL) V3 ME)
  • أشغل هذه الوظيفة منذ ديسمبر 2019

Renovation of Four-Season Hotel
Project Description: The hotel is in Kingdom Tower from level 30 to 50 Each level consists of 27 Guest
rooms which consist of superior king, Deluxe Room, Deluxe Twin, Deluxe Twin-Disabled, Premium King,
Four Seasons Exec Suites, One Bedroom suite, Presidential suite, Royal Suite, Kingdom suite.
Duties and Responsibility of the above-mentioned project:
- Study of Design drawings, specification to ensure that installation and operation conforms to
standards and to Client Requirement.
- Performing Inspection on daily basis for Installation and performing testing of all MV, Low
Voltage and LC system and equipment. Transformer, MV & LV Cables, MDB, MCC, DBs panels
and breakers, FAS, PAS, Telephone and Data System, MATV, IPTV, Master Clock System, Audio
Video System, BMS system, GRMS, BMU and Fire life safety systems.
- Perform overall quality control of the work (budget, schedule, plans, and personnel’s
performance) and report regularly on project status.
- Supervising and making inspections all electrical works within the project site with the highest
quality and standards in accordance with the approved shop drawings and technical
specifications and preparing snag list

MEP Project Manager في JLL
  • المملكة العربية السعودية - الرياض
  • أشغل هذه الوظيفة منذ ديسمبر 2021
MEP Engineer في V3 Middle East Engineering Consultant
  • المملكة العربية السعودية - الرياض
  • أشغل هذه الوظيفة منذ مارس 2021
MEP Engineer في V3 Middle East Engineering Consultant
  • المملكة العربية السعودية - الرياض
  • نوفمبر 2019 إلى سبتمبر 2020
MEP Project Manager في KING ABDULLAH FINANCIAL DISTRICT
  • الإمارات العربية المتحدة
  • أغسطس 2018 إلى نوفمبر 2019

Client: JASARA
Company: Jones Lang Lasalle ((JLL) V3 ME).
Parcel:
- The Financial Plaza - 3B+LG+UG, 827 VIP parking
- Parcel 5.07 - 2B+G+M+11F+R
- Parcel 5.08 - 2B+G+M+14F+R
- Grand Mosque - B+F+1F for Male and Female
- THE 303 - Entertainment and Cafeterias.
- Parcel 1.12 - 4B+G+M+36F+R
- Parcel 1.10-4B+G+2M+42F+R
- The MISK - Irqah Infrastructure Upgrade Phase 1.
Duration:

Engineer في MEP
  • الإمارات العربية المتحدة
  • يناير 2018 إلى أغسطس 2018
Engineering Consultant في V3 Middle Eas
  • يناير 2018 إلى أغسطس 2018

The Cleanroom at the National center for NANO Technology consists of 'Bldg. 33, 33A and 33B" 2 story
each and it is in the center of the campus, in vicinity of other operational buildings. The building will
have an approximate built-up floor area of 5000 square meters. The building will serve as a pioneer
specialized research facility in the campus, which includes a dedicated specialized research area, and
laboratory facilities with high-tech and top of the line equipment, management, and security. The
buildings will also contain offices, workshops, meeting rooms and halls, reception areas, file and archive
rooms, storage rooms, utility and services areas and auxiliary rooms.

Engineer في MEP
  • الإمارات العربية المتحدة
  • سبتمبر 2016 إلى يناير 2018
Engineering Consultant في V3 Middle Eas
  • الإمارات العربية المتحدة
  • سبتمبر 2016 إلى يناير 2018

King Abdul-Aziz City for Science and Technology (KACST) is a general government institution whose
complex is in the northwestern area of Riyadh and located on both sides of the King Abdullah Bin
Abdul-Aziz Road.
The Biotechnology Research Facility is the first of its kind in the Kingdom and in the region providing
state-of-the-art facilities, which are to include laboratory facilities Bio-Safety Level 2 up to Bio-Safety
Level 3 suites including top of the line equipment, management, and security.
The building consists of two wings of four stories each connected via internal pedestrian bridges
spanning a four-story height central atrium space between the wings. Total gross area including plant
rooms will be approximately 27, 300 square meters with Electrical load of 12 MVA.

Electrical Engineer في STUDY OF BOQ OF SAKAKA AL JOUF
  • فبراير 2014 إلى ديسمبر 2015
Electrical Engineer في PRINCE NAWAAF RESIDENTIAL
  • يونيو 2013 إلى يونيو 2015
Engineering Consultant في V3 Middle Eas
  • يونيو 2013 إلى يونيو 2015

Durrat Al Riyadh, the Kingdom first gated residential neighborhood in Riyadh, the unique Durrat Al
Riyadh Resort & Spa resides on 154, 000 sqm. The hotel consists of twin wings with tower A & B with 3
Basements, mezzanine and 5 floors. The hotels with 162 abodes, including 121 extensive guestrooms,
31 suites and 10 private villas each with an outdoor swimming pool. All guest rooms at the resort are
equipped with a seating area, a flat-screen TV with satellite channels, a kitchen, a dining area and a
private bathroom with free toiletries and a bath. The resort offers a two-floor spa for women and
gents, several indoor and outdoor swimming pools, including an infinity-edge-pool in addition to a
range of leisure facilities.
Main Duties and Responsibility of the above-mentioned project:
- Study of Design drawings, specification to ensure that installation and operation conforms to
standards and to Client Requirement.
- Study of BOQ by ensuring that material mention in project does not affect any major variation
for completion of the project on time, without any major changes in the budget allocated to
the project.
- Provide technical direction and implements the project construction work processes,
procedures, manuals, and systems ensuring that the contractors are building to the latest
revision of the drawings, specifications, and procedures.
- Highly involved in development in making electrical design, estimation of work content,
material take-off and calculation of power distribution system.
- Performing the factory visit and approving the equipment as per standards and specification of
project requirement.
- Monitoring the EHS guidelines’ proper implementation at sites and issuing NCR’s if required.
- Witness or attending any field or shop electrical equipment testing FAT like MV switchgear,
MV/LV power substation, motor control center, power generators & ATS system, testing of
cables, fire detection and alarm system, and other low current systems.
- Performing testing of Transformer, Cables, Circuit Breaker, Low Voltage system, Low Current
system, Audio Video System, BMS system and lab equipment’s.
- Review of completed installations and observe operations, to ensure conformance to design
and equipment specifications and compliance with operational and safety standards.
- Supervising and making inspections all electrical works within the project site with the highest
quality and standards in accordance with the approved shop drawings and technical
specifications
- Corrective and preventive actions to keep production quality on site.
- Using of ACONEX online documentation software to reduce the usage of paper and time.

Electrical Engineer في LULU BATH
  • فبراير 2014 إلى أبريل 2014
Electrical Engineer في AL FAISALIAH HOTEL AND SPA
  • ديسمبر 2013 إلى مارس 2014
Electrical Engineer في SATCO-KKIA- ACCOMMODATION
  • أغسطس 2013 إلى ديسمبر 2013
Electrical Engineer في K.P ELECTRICAL WORK LIMITED
  • الهند
  • يونيو 2013 إلى نوفمبر 2013
Electrical Engineer في SATCO-KKIA-OFFICES
  • أغسطس 2013 إلى أكتوبر 2013
Electrical Engineer في SONY GROUP AND R.K PLAZA INDIA
  • يونيو 2012 إلى فبراير 2013
Electrical Engineer
  • مايو 2010 إلى يونيو 2012

standards and to Client Requirement.
- Performing testing of all Low Voltage and LC system panels and equipment. Transformer, MV
& LV Cables, MDB, MCC, DBs panels and breakers, FAS, PAS, Telephone and Data System, IPTV,
Master Clock System, Audio Video System, BMS system, BMU and Fire life safety systems.
- Interfacing life safety systems with BMS system and checking with FAS matrix.
- Coordinating and monitoring all MEP activities (Electrical & Mechanical) with their program
schedule for proper flow of work ion site.
- Prepare Product reports by collecting analyzing and summarizing information trends.
- Work execution as per planned construction program and progress monitoring for billing.
- Preparing and follow up of programs for materials and site Delivery.
- Work execution as per standards and as per local regulation for quality compliance.
- Conducting weekly report with consultant and Construction’s mangers.
- Checking all the HVAC system with sequence of operation with life safety systems.
- Conduct site inspections to endure adherence to engineering standards and specifications.
Monitor compliance to applicable Codes, practices, QA/QC policies, performance standards
and specifications.
- Perform overall quality control of the work (budget, schedule, plans, and personnel’s
performance) and report regularly on project status.
- Supervising and making inspections all electrical works within the project site with the highest
quality and standards in accordance with the approved shop drawings and technical
specifications and preparing snag list.

الخلفية التعليمية

بكالوريوس, Electrical &Electronics Engineering
  • في Jawaharlal Nehru Technological University
  • أغسطس 2010

بكالوريوس, Electrical &Electronics Engineering
  • في Jawaharlal Nehru Technological University
  • يونيو 2010

in Indian Railway's (k. p electrical works) {Electrical

Specialties & Skills

Stimulation
AutoCAD
BUDGETING
CABLING
CUSTOMER RELATIONS
MICROSOFT WORKS
PERSONNEL
QUALITY
QUALITY CONTROL
REQUIREMENTS

اللغات

الانجليزية
متمرّس
الهندية
متمرّس
الأوردو
متمرّس

العضويات

PMI
  • APM
  • December 2023

التدريب و الشهادات

Primavera (تدريب)
معهد التدريب:
ETC
تاريخ الدورة:
August 2021
المدة:
62 ساعة

الهوايات

  • Cricket Basket ball