Responsibilities:
•Managed power infra projects from conception to completion, ensuring that all work was completed within budget, on time, and in compliance with relevant regulations and standards.
•Leading and managing sub-contractors and site agents, ensuring progress on site, and maintaining a strong focus on project delivery and client satisfaction
•Implementing and maintaining company procedures, including planning, cost control, and weekly progress meetings, resulting in streamlined project execution
•Liaising with consultants and sub-contractors on technical, contractual, and commercial matters, fostering strong relationships and efective communication
•Supporting the Operation Manager in resource scheduling and contract close-out, ensuring eficient allocation of resources and timely completion of projects
•Advising the Commercial Department on subcontract requirements and ensuring timely appointments, contributing to the overall project success
•Reviewing and endorsing material requisitions, establishing proper controls at site stores, and managing equipment allocation and utilization within contracts
•Monitoring delivery schedule of overseas materials and expediting snagging and handover processes, ensuring timely completion and adherence to project specifications.
•Supervising small works contracts and providing necessary support for subordinates, fostering a collaborative and supportive work environment
•Ensuring compliance with the Company Health, Safety, and Environmental Management System, promoting a safe and secure working environment for all team members.
Highlights:
Played a key role in design and built the electrical distribution network feeding Emirati Housing 3000 Villas, a large-scale project targeting a population of 24, 000 people, showcasing strong leadership and project management abilities.
• Managed the construction of 22KV, 11KV distribution networks along with DMS integration.
• Supply, installation, testing & commissioning of MV, LV & FOC cable networks and Street lighting networks.
Achievements:
• Baniyas North Development - Infrastructure, Streetscape & Villas (Phase I & II).
Client: Al Dar Properties PJSC. Consultant: Mott MacDonald.
• Construction of Internal Roads and Infrastructure for 446 Plots at Al Sader Area.
Client: Musanada Consultant: Ital Consult.
• Najmat Phase 3 - Infrastructure Works.
Client: Reem Developers. Consultant: Rafik El Khoury & Partners.
• Al Samha - Emirati Housing 250 Villas, Infrastructure works, Abu Dhabi.
Client: Musanada Consultant: Al Torath International.
• Nareel Island Infrastructure and Public Realm - 148 Residential Plots.
Client: Al Dar Properties PJSC. Consultant: KEO International Consultants
• Infrastructure works for 518 Commercial villas and associated community facilities, Al Ain.
Client: Al Qudra Holding Consultant: Al Salam
• Al Dana Phase II - Infrastructure Works at Al Raha Beach, Abu Dhabi.
Client: Al Dar Properties PJSC. Consultant: Hyder
• Emirati Housing Development 3000 Villas- Infrastructure works at Jebel Hafeet, Al Ain, U.A.E.
(Housing area with facilitating structures with 3000 villas targeting a population of 24, 000 people)
Client: Musanada Developer: TAMOUH Investments. Consultant ACE International
- Company industry:
- Construction & Building
- Job role:
-
Management