مجموع سنوات الخبرة :16 years, 1 أشهر
Brief
• 2, 500, 000, 000 SR Cost.
• 36 Months Duration.
• Composed of 8 separates sites.
Responsibility:
Responsible about full separate site composed of:
• 250, 000 square meter area.
• 9 main buildings with subsidiary buildings.
• 40, 000 square meters Total built up area.
• 412, 000, 000 SR Cost.
• 30 months duration
• Reviewing tender documents, specifications, BOQs, drawings and design calculations.
• Acting as a leader for site activities, drawings and reviewing soil & concrete tests.
• Following up subcontractors such as post-tension, curtain wall, stone, and insulation contractors
• Coordinating with discipline departments to ensure accuracy and quality of work
Project : SABIC Plastics Applications Development Center
Client : SABIC
Consultant : Zuhair Fayez Consulting.
Position : Planning Engineer
Brief
• 307, 103, 707 SR Cost.
• 20 Months Duration.
• Project contains: concrete work, precast HC, steel structure, curtain walls, skylights, stone cladding and multi finishing items.
Responsibility
•Construct Baseline, Recovery and Revised Programs
• Following up the activities and analyze the delay
• Weekly and Monthly Reports shows S-Curve and Cash Flow
Diagrams
• One Week and One month look ahead
• Implement the claims on baseline program and schedule the
time effects.
Project : Immigrants Residence Project in Jizan.
Client : King Abdulla Bin Abdul Aziz Foundation for his Parents housing Inst
Management: AECOM
Consultant : Zuhair Fayez Consulting.
Position : Site Engineer & Site Coordinator.
Brief
• 1, 067, 554, 135 SR Cost.
• 18 Months Duration.
• 1063 residential units.
• 4 schools.
• 6 mosques (4 mosques with 750 prayer capacity and 2 with 1500 prayer capacity).
• Medical center.
• External works (Infrastructure & Roads)
Responsibility
• Fabricate the steel reinforcement for structure element and distribute it for whole the site.
• Construct a ROYAL MEETING HALL.
• Precast coordinator:
I. Identify precast drawings with the architectural drawings.
II. Check the precast elements (hollow core slab & precast panels) which delivered on site and supervise the erection.
Project : Qatrana Cement Project
Client : Qatrana Cement Company
Management: MSDR
Consultant : HOLTEC consulting Private Limited.
Position : Quality Control Site Inspector.
Brief
• 114, 000, 000 JDs Cost
• 24 Months Duration
Responsibility
• • Following up and Reviewing shop drawings.
• Supervise and manage site works to deliver the completion of work with schedule.
• Following up work procedures on site
• Understanding of the Project Standard Specification
• Coordinating technical documents (requisitions, drawings, specifications) between interfacing engineering disciplines.
• Monitoring concrete issues (tests, handling and results)
Projects : Jumeira Village Circle for Villas and Townhouses.
Client : Nahkeel
Management : Ellisdon
Consultant : Dynamic Engineering Consultant
Position : Planning Engineer
Brief
• 246 Villas
• 369 Townhouses
• 675, 000, 000 Dhs Cost
• 19 months Duration
Responsibility:
• Following up site works, and monitoring project performances.
• Updating site activities with Primavera Program.
• Weekly and monthly reports for client, consultant and upper management.