Mostafa Abd Allah Mohamed, Dupty Projects Manager

Mostafa Abd Allah Mohamed

Dupty Projects Manager

Enviroment Systems Est., for Contracting

Lieu
Egypte - Le Caire
Éducation
Baccalauréat, Civil Engineering
Expérience
29 years, 7 Mois

Partager Mon CV

Empêcher usager


Expériences professionnelles

Total des années d'expérience :29 years, 7 Mois

Dupty Projects Manager à Enviroment Systems Est., for Contracting
  • Arabie Saoudite - Riyad
  • Je travaille ici depuis février 2015
Freelance Infrastructure Professional Engineer , Prepared for PMP Certificate à Freelance
  • Egypte - Le Caire
  • juin 2013 à février 2015

Tendering, Estimation, Procurement activities for Private contractors
Infrastructure, Roads & Mining main Projects in Egypt.

Assistant Resident Engineer, Highway à ACE Arab Consulting Engineers "Moharram.Bakhoum"
  • Maurice
  • mai 2011 à mars 2013

Supervision all Construction works of Ring Road for Port Louis
• Monitoring & approve mining works to construct 8km of roads in rock mountains includes 10’000’000.0Cum in cut using safe Chemical explosives, 2’000’000.0 Cum in back filling for roads includes all utilities & draining system.
• Review & Approve Contractor’s monthly Inter-statements.
• Monitoring Contractor’s fieldwork to ensure compliance with project specifications, implementation schedule, quality of work and troubleshooting mechanisms.
• Ensure effective and efficient implementation and monitoring of project component activities.
• Review the design drawings, implementation schedule.
• Review, Approve & Control Permanent Materials Supplies.
• Review, Approve Contractor Claims & V. Orders.
• Monitoring Contractor’s fieldwork to ensure compliance with implementation schedule, quality of work and troubleshooting mechanisms, and approving contractor’s invoices.
• Coordinate with the relevant governmental authorities.
• Ensure a smooth coordination and communication of component related matters between different stakeholders.

Real-Estate Project Manager à Al Amar Consulting Group
  • Egypte - Le Caire
  • juillet 2010 à avril 2011

Real -Estate Project Manager in New Cairo

Senior Infrastructure Engineer à ECG Consulting Group
  • Egypte - Le Caire
  • août 2009 à juillet 2010

Infrastructure R.E in Madinty City Project

Procurement Manager à Consortium of: Misr Sons Development (Hassan Allam Sons Co.) & Consolidated Contractors Int'l Co.
  • Egypte
  • novembre 2007 à juillet 2009

Description of responsibilities:-

• Manage Negotiations & Contractual agreements with Contractors.
• Manage Negotiations & Contractual agreements with Suppliers ( Imported & Local ).
• Review, Approve & Control Permanent ( Imported & Local ) Materials Supplies.
• Review & Approve Contractor Claims & V. Orders.
• Submitting all permanent & temporary materials for approval.
• Monitoring Contractor’s fieldwork to ensure compliance with implementation schedule, quality of work and troubleshooting mechanisms.

Project Technical Advisor & Sanitation Project Resident Engineer à Egyptian Swiss Development Fund (ESDF)
  • Egypte - Alexandrie
  • juin 2005 à octobre 2007

Description of responsibilities:-
• Ensure effective and efficient implementation and monitoring of project sanitation component activities.
• Tender Project Cost Estimation.
• Review the design drawings, bid tender documents, implementation schedule.
• Supervise the Consulting Engineer firm(s).
• Supervise the component staff in the implementation organization as well as the design.
• Manage Negotiations & Contractual agreements with Contractors & Suppliers.
• Review, Approve & Control Permanent Materials Supplies.
• Review & Approve Contractor Claims & V. Orders.
• Monitoring Contractor’s fieldwork to ensure compliance with implementation schedule, quality of work and troubleshooting mechanisms, and approving contractor’s invoices.
• Coordinate with the relevant governmental authorities.
• Ensure a smooth coordination and communication of component related matters between different stakeholders.

MSD à Misr Sons Development Co." Hassan Allam Sons "
  • Egypte - Le Caire
  • janvier 2004 à mai 2005

Tender Projects Estimator Engineer :
•Off-Shore Projects Estimating ( Projects in Gulf Area ).
•Water & Wastewater Projects Estimating.

OCI / MSD J.V. à ORASCOM / MISR SONS DEVELOPMENT J.V.
  • Egypte
  • juillet 2001 à décembre 2003

Submittal, Material & Contractual Engineer :
•Responsible for Claims & V. Orders with the Engineer & Main Contractor.
•Responsible for submitting all permanent & temporary materials for approval.
• Responsible for contractual agreements for all permanent materials ( Suppliers & Installers) .
LUXOR WASTWATER FACILITIES PROJECT
USAID PROJECT No. 263-0236
( The Engineer : CDM )
The Project contains construction of 180 Fadden Wastewater Treatment Plant with capacity
of 20, 000.0 cubic meters per day, Four Pump Stations, 6.0 km Force Main & 90.0 km Sewer and House Connection Lines. ( 43 million Dollar ).

M.K. Int. à Morrison Knudsen Inter., / Contrack Inter., J.V.
  • Egypte
  • avril 2000 à juillet 2001

Site Superintendent for Kom_Ombo City :
• Responsible for Constructing 8 km Sewer lines & 12 km House Connection lines in Kom_Ombo City using different systems of Side Support : ICON System & Traditional system( R.C Pipes 800mm & UPVC Pipes 160 mm to 630 mm ).
ASWAN CITIES WATER & WASTWATER FACILITIES PROJECT
USAID PROJECT No. 263-0236
( The Engineer : CDM )
(101 million Dollar ).

MSD à MISR SONS DEVELOPMENT CO." HASSAN ALLAM SONS "
  • Egypte - Le Caire
  • janvier 1997 à avril 2000

Q. Surveyor / Estimator Engineer :
•Responsible for Quantities surveying & estimating the tender Projects.


Technical Offer Presenting Engineer :
•Responsible for preparing and presenting tender’s Technical Offers.


Contract Administrator / Project Coordinator :
•Responsible for Cairo Airport Project :
Runway 05 R - 23 L Improvements
( 15 million Egyptian Pounds ).
•Responsible for Canal Cities Water & Wastewater Projects Phase II Sewerage Improvement for Cities :
Portsaid Contract No. 3415
Ismailia Contract No. 3387
The Engineer : CMC ( 65 million Egyptian Pounds ).

MSD à MISR SONS DEVELOPMENT CO." HASSAN ALLAM SONS "
  • Egypte - Le Caire
  • août 1994 à janvier 1997

Aug., 1996 - Jan., 1997 Akhbar El-Yom Maintenance Center Project
Site Engineer
• Responsible for Akhbar El-Yom Maintenance Center Project mobilization
The Engineer : Sabour ( 36 million Egyptian Pounds ).

Jan., 1996 - Aug., 1996 West Bank Projects - El - Waraaq Area ( 24Q )
Site Engineer
• Responsible for Constructing 8 km Sewer lines & 10 km House Connection lines in
El-Waraaq Area- Giza - West Bank Projects.
The Engineer : Ambric ( 10 million Egyptian Pounds ).

Aug., 1994 - Jan., 1996 West Bank Projects - El - Haram Area ( 27I )
Site Engineer
• Responsible for Constructing 9 km Sewer lines & 12 km House Connection lines in El - Haram Area - Giza - West Bank Projects.
Tech. Office Engineer
• Responsible for Quantities surveying, Inter statements & Sub-Contractors
The Engineer : Ambric ( 12 million Egyptian Pounds ).

Éducation

Baccalauréat, Civil Engineering
  • à Assiut
  • novembre 1992

Specialties & Skills

Infrastructure Projects
Procurement
Microsoft Office software & the Internet
Quantitative Analysis
Creative Skills

Langues

Anglais
Moyen
Arabe
Expert

Adhésions

Egyptian Engineers Syndicate
  • 2191/18
  • November 1992
Rehab Sporting Club
  • 4913
  • April 2003

Formation et Diplômes

ISO 9001 STANDERD ( March 1999 ). (Certificat)
Date de la formation:
March 1999
Valide jusqu'à:
March 1999