Sr. Planning Engineer at Advanced Construction Company (ACC)
  • Saudi Arabia - Jeddah
  • My current job since June 2013

Senior Planning Engineer Responsible for • Analysis the contract documents regarding defining complete project scope of work. • Preparation of Project Plan (Defining time schedule and milestones, Perform Resource Planning, Assign Cost accounts) • Calculation of manpower projections, preparation of Budget flow Histograms. • Lead a team to prepare Comprehensive Status reports on monthly Basis on Project Progress for management and end client. • Supporting project reporting and trending to include schedule variances, earned value and critical path analyses and advising Corrective action to avoid slippage.

Senior Planner at KAMCO ...Construction company in Dammam
  • Saudi Arabia - Dammam
  • January 2012 to May 2013

Responsible for
• Analysis the contract documents regarding defining complete project scope of work.
• Preparation of Project Plan (Defining time schedule and milestones, Perform Resource Planning, Assign Cost accounts, ….)
• Calculation of manpower projections, preparation of Budget flow
Histograms.
• Lead a team to prepare Comprehensive Status reports on monthly
Basis on Project Progress for management and end client.
• Supporting project reporting and trending to include schedule
variances, earned value and critical path analyses and advising
Corrective action to avoid slippage.

Project Manager at SRACO - SRG
  • Saudi Arabia - Dammam
  • January 2011 to December 2011

Project Manager

Responsible for
• Analysis the contract documents regarding defining complete project scope of work.
• Preparation of Project Plan (Defining time schedule and milestones, Perform Resource Planning, Assign Cost accounts, ….)
• Lead a team and manage day to day activities.
________________________________________

Senior Planning Engineer at AL GIHAZ CO. LTD.
  • Saudi Arabia - Riyadh
  • January 2009 to December 2010

Senior Planning Engineer

Responsible for
• Analysis the contractual documents regarding defining complete project scope of work.
• Preparation of Project Plan (Defining time schedule and milestones, Perform Resource Planning, Assign Cost Accounts, ….)
• Calculation of manpower projections, preparation of Budget flow
Histograms.
• Lead a team to prepare Comprehensive Status reports on monthly
Basis on Project Progress for management and end client.
• Supporting project reporting and trending to include schedule
variances, earned value and critical path analyses and advising
Corrective action to avoid slippage.

Project Manager at Promastar SAE
  • Saudi Arabia - Riyadh
  • June 2006 to December 2008

From Sep. 2007 up to Dec. 2008
Promastar SAE - Project Management Division
Project Manager in CENTER OF DEVELOPMENT OF PROJECTS
(CDP-MOI) Project Management Office (PMO) (Riyadh- K.S.A.)

Responsible for assisting (CDP) in using Primavera Enterprise in planning, scheduling, monitoring and controlling of the projects as part of Promastar team who assisted (CDP) in the setup and operation of a project management office including processes, competency development and tools customization and implementation using Primavera Enterprise Suite.

Participated in the implementation through its 6 steps:
• Assess Needs of the Client regarding Primavera Software.
• Systems design document & functional specifications
• Working model installed and customized on the systems
• Documentation of the results and Pilot test
• Rollout and migration of data
• Final Assessment (reassessment)
________________________________________

From April 2007 to August 2007
Promastar SAE - Project Management Division
Implementation of Primavera Enterprise Suite in EL-Fouzan Trading & Construction Co. (Riyadh- K.S.A.)

Responsible for assisting the projects department using Primavera Enterprise in planning, scheduling, monitoring and controlling of the projects as part of team who assisted the company in the setup and operation of a project management office including processes, competency development and tools customization and implementation using Primavera Enterprise Suite.

From June 2006 to March 2007 (K.S.A)
Promastar SAE - Project Management Division
Project Manager in Jeddah Municipality's Project Management Office (PMO)

Responsible for assisting the projects department is using Primavera

________________________________________

Project Engineer,Project Manager at National Organization for Potable and Wastewater
  • Egypt
  • April 2002 to June 2006

From April 2002 to June 2006
Program Manager / Projects Director
National Organization for Potable and Wastewater - Aswan City, Egypt.

Duties & Main Responsibilities:
 Managing a portfolio of projects consisting of three programs and total of 9 projects mainly in developing the infrastructure in Aswan City, one of the tourist centers in south Egypt, and hence, in the focal point of local and national interests.
 Managing over 6 technical consultant offices, 20 contractors and suppliers (Egyptian and International).
 Liaising with Governmental Agencies in Cairo to secure approvals and funding for the infrastructure projects in Egypt.
 Monitoring and controlling the projects portfolio and presenting the summarized information to HE the Governor of Aswan, the local politicians, the executives of our organization and high-rank politicians and ministerial visitors from Cairo.
 Attending the bi-weekly monitoring meetings with the leaders of other local authority to coordinate for the street works.
 Actively managing the initiation and closing the projects and its transformation to the operating services authorities.
 Reviewing the master plans and schedules of the projects. Generally, supervising planning, executing monitoring and controlling activities of the projects.
Projects in portfolio:
 First program (EGP 100 millions) : 2 infrastructure projects covering 10 compact potable water stations and 9 deep wells (up to 100 m) around the governorate.
 Second program (EGP 200 millions): 5 projects to establish the infrastructure of the New Aswan City: Nile Water Intake project, Potable Water project (on 67 000 m2), New Aswan Pump Station project, 5-Mega-Water Reservoirs project, The City Potable Water Network project.
 Third program (EGP 60 millions): 2 projects to upgrade the existing infrastructure of the old Aswan City: Potable Water Capacity Increase project, Extension of the Water Supply Network project.

Project Manager at National Organization for Potable and Wastewater –
  • Egypt
  • January 1997 to March 2002

From January 1997 to March 2002
Project Manager
Aswan, Egypt.
Duties & Main Responsibilities
 Project Manager for a group wastewater projects in Aswan managing day-to-day activities of the related projects.
 Managing 3 technical consultant offices, 7 contractors and suppliers (Egyptian and International).
 Monitoring and controlling the projects and presenting the summarized information to company management and HE the Governor of Aswan.
 Attending the bi-weekly monitoring meetings with the leaders of other local authority to coordinate for the street works.
 Actively managing the initiation and closing the projects and its transformation to the operating services authorities.
 Preparing the master plans and schedules of the projects and coordinating the detailed schedules and plans from the contractors.
 Preparation of the project time schedules during the design phase and the construction phase using Primavera Enterprise (P3e)
 Follow up and control works, issuing progress reports for the project.
 Delay analysis for the construction projects.
 Coordinating Civil, E&M, sewerage systems.
 Preparing cash flow.
Projects managed:
 Project: Second of the Replacement of Aswan Sewerage System, Budget: EGP 120 millions
 Project: Third of the Replacement of Aswan Sewerage System, Budget: EGP 150 millions
 Project: Water Supply System Upgrade, Aswan, Budget: EGP 130 millions
 Project: Floating Marine Sewage System: a water structure to dispose the tourist ships sewerage. Water Supply System Upgrade, Aswan, Budget: EGP 15 millions
 Project: Building the Abu-Sunble Sewerage System, Budget: EGP 100 millions

Project Engineer at National Organization for Potable and Wastewater
  • Egypt
  • June 1994 to December 1996

From June 1994 to December 1996
Project Engineer
National Organization for Potable and Wastewater - Kom-Ombo, Egypt.
Duties & Main Responsibilities
 Project Engineer for 3 water supply projects in Kom-Ombo participating in technical and managerial day-to-day activities.
 Managing 3 technical consultant offices, 3 contractors and suppliers
 Monitoring and controlling the projects.
 Preparation of the project time schedules during the design phase and the construction phase using Primavera Enterprise (P3e)
 Follow up and control works, issuing progress reports for the project.
 Coordinating Civil, E&M, and sewerage systems.
 Supervising the technical office for the project (Project Support Office PSO).
________________________________________

Site Engineer at (Arab Contractors (AC
  • Egypt
  • January 1993 to June 1994

From Jan 1993 to June 1994
Site Engineer
Arab Contractors (AC) - South Egypt Branch, Egypt.
(The biggest Construction Contractor in Egypt and North Africa)
Duties & Main Responsibilities
 As Contractor’s Site Engineer, reporting to the Client Project Manager, supervising 2 projects in Kom-Ombo area participating in technical and managerial day-to-day activities.
 Supervising all types of construction and civil works.
 Monitoring and control for construction schedule and resources.
 Quantity surveying for preparing our main invoices and reviewing and approving subcontractor's invoices.
 Supervising and controlling quality of all activities according to consultant and client specifications.
 Issuing progress reports for the project.
 Coordinating Civil, E&M, sewerage systems.

Education

Bachelor's degree, Civil Engineer
  • at Asyut University
  • May 1992

معدل جيد يعنى نسبة من 65% الي 75%

Specialties & Skills

Civil Engineering
Civil Site Manager
Project Management
Senior Planner
Primavera P6
Project Manager
Civil Engineer
Senior Planner

Languages

Amharic
Intermediate
Arabic
Native Speaker

Memberships

Egyptian Engineers Syndicate
  • Civil Engineer
  • October 1992

Training and Certifications

PMP Preparation Course (Training)
Training Institute:
Promastar SAE.- Egypt
Date Attended:
May 2005