• The project consist of 2.2km long headrace tunnel, sand trap, weir, intake, cofferdams, powerhouse, 132kv GIS and associated transmission lines. M & E Department concerns to installation, commissioning and testing of following: Generators and exciters and generator monitoring system, Segregated phase bus (SPB) between generator and generator step up transformer, Generator Step-up Transformers, Unit auxiliary transformer, 132kv switchyard (GIS) arrangement based on double bus scheme, 132kv Interconnecting Transmission line between step-up transformer and 132kv GIS switchyard, 11kv distribution line from powerhouse to intake, Generator circuit breaker, Station power distribution system, Medium Voltage (MV) Switchgear, Protection and Relay Equipment, Internal and External lighting, Lightning and Earthing System, Fire detection and alarm system, Diesel Generators for powerhouse and intake and cable and cable tray system.
• Direct managing and supervision for the electrical work to maintain the performance on jobsite.
• Conducting the initial tests and inspections for the electrical items.
• Patrind Hydro Project I am fully involved in erection of large capacity transformers in the range of 62.5MVA, testing and commissioning of complete system package.
• 11KV Switchgear and Transformer protection panels. Meggering and Hi-pot testing termination.
• 132KV GIS Electrical Substations erection, commissioning work and 132KV distribution system AIS.
• Involved in gantry tower erection, testing and commissioning of outdoor switch yard all equipment’s erection 132KV equipment like Surge Arrestor, post insulator, CVT, CTs and overall grounding of AIS floor.
• Low voltage AC & DC panels, 220 volts DC UPS system, DC battery chargers and battery racks, UPS and related DC power and control installations.
• 11KV switchgear panel erection, 400V distribution panel, auxiliary transformers and all related auxiliary and ancillary equipment and devices installation. Pre-commissioning and commissioning of existing Medium Voltage Switchboard.
• Cable tray/ladder and support fabrication and installations.
• Lighting system supervision for the installation of conduit, lighting fixtures.
• Supervision of installation of 11KV overhead distribution line around 6 kilometers.
• Installed up to 630KVA 415V 3 phase diesel generators complete with fuel system and distribution system.
• Supervision of installation of 11KV VCB panels, its testing and commissioning.
• Attending the meetings with client, consultant and writing memos.
• Electrification of two camps, load balancing and monitoring the power supply for reliability.
• Installation and commissioning of ATS panels, distribution transformers, generators, CTs and energy meters.