Lead Proposal & Estimation Engineer à AlBilal Group
  • Émirats Arabes Unis - Dubaï
  • Je travaille ici depuis janvier 2021

Proposal & Estimation Responsibilities:
• Study and review of ITT (invitation to tender) documents to analyse and accurately assess all ITT requirements.
• Prepare a bid preparation schedule for submission of bids; identify people responsible for various activities within predetermined timelines, and a common understanding of the scope.
• Meeting with client representative to clarify scope and propose recommendations.
• Conducting site visit for detailed understanding of scope of required work.
• Preparation of RFQs for subcontractors and vendors.
• Development of detailed resource loaded Level - IV plan for overall project, encompassing all scope requirements.
• Follow-up with the procurement department for vendor offers and obtain vendor responses for the technical clarifications raised. Ensure generation of all deliverables by Engineering Disciplines as per Bid requirement (BOQs, Technical Documents to be attached to Bid, costing for various equipment and bulks etc).Shortlist and identify target vendors for various key equipment/ packages
• Prepare and compile a Risk Register wherein various risk elements of the project are listed and update the risk mitigation strategy for each risk element in consultation with Proposals Manager and discipline engineers.
• Prepare the cost estimate during Tendering / Execution for management review and approval and liaise with discipline engineers for further assistance.
• Preparation of Cash flow of the Project as per Payments milestones / T.C’s.
• Review of project Schedule and cost estimates to be submitted along with Bid
• Prepare technical and commercial proposals as per client requirement with respect to project execution plans, organization charts job specific technical write ups, bank guarantees, commercial and technical qualifications and prepare responses to the client post bid queries.
• Development of BAC (bid acceptance committee) packs for GATE approval process and management signoff.
• Preparing bid package for site execution team for awarded proposals.
• Detailed lesson learned review after proposal submission and implementation in upcoming proposals.

Senior Planning & Estimation Engineer à DOOSAN BABCOCK GMS LLC
  • Émirats Arabes Unis - Abu Dhabi
  • janvier 2018 à décembre 2020

• Ensuring that Corporate Systems are set up and maintained in line with project schedules and project planning package.
• Review and approve Sub-Contractor’s Planning Package, which includes Level-IV schedule, Progress S- Curves, Manpower Deployment etc.
• Prepare progress measurement system for projects and ensuring that progress measurement systems are in line with COMPANY’s project control procedures and rules of credit defined in the procedures.
• Monitor the reported progress and schedule status and identify areas of concern impacting the progress and schedule of the project and advise project management on the proposed corrective actions.
• Identify critical and sub-critical activities of the project and analyze their impact on the overall completion schedule considering the actual status and trends.
• Preparation of variation request/claims for extension of project
• Prepare look ahead schedule and ensure that it covers all the activities as per baseline schedule and actual progress.
• Review and approval of Sub-Contractor monthly invoice.
• Preparing Weekly/Monthly and dashboard reports for Client and Senior Management.

Lead Planning Engineer à Descon Engineering Limited
  • Émirats Arabes Unis - Abu Dhabi
  • août 2015 à décembre 2017

09/2015-Present Descon Engineering Company Limited Abu Dhabi, UAE.
Currently Working Offshore at UPPER ZAKUM (ZADCO) Island Development Project on UZ-750 Project.
Responsibilities:
• Development of Base Line Schedule using Planning Software PRIMAVERA (P6).
• Develop and maintain plans and schedules deliverables at all levels of management with inputs from engineering, construction and commissioning
• Preparation of Weekly; Monthly & Three Months look-ahead Schedule.
• Updating actual Progress and all related information & comparison analysis.
• Project Scope Management
• Review and forecast Contractor Work front availability and conduct continuity of work analysis.
• Tracking and maintain scope changes of Mechanical items for Piping; Structural Steel; Piping & Mechanical Equipment’s and its effect on the overall project schedule.
• Resources Estimation and Loading in P6 plan.
• Estimation of Manpower Requirement for the Project based on standard productivity norms.
• Monitoring of actual resources availability & analysis using Histogram.
• Budget Monitoring & estimation.
• Preparing progress % calculation systems, earned man-hours, productivity & Trend analysis.
• Progress Measurement using S Curves.
• Preparation Executive Progress Summary Report to the Top Management on Project Status for periodical review.
• Evaluated and communicated the results of Work Front Analysis.
• Prepare and monitor Risk and Issues Register.
Descon Engineering Company Limited Abu Dhabi, UAE Worked on a Planning Package of ADCO-SAHIL Development Project Phase-2.
Responsibilities:
• Study of contract documents and develop scope of work.
• Development of Base Line Schedule using Planning Software PRIMAVERA (P6).
• Develop and maintain plans and schedules deliverables at all levels of management with inputs from engineering, construction and commissioning Preparing schedule, Planning & Progress Reports/Statements.
• Creation of project budget and monitoring of the cost incurred.
• Preparation & Distribution of daily and weekly work schedules and S-Curves based on 4‐week and 3-months look ahead plans to Discipline Engineers.
• Generation of Weekly Work front based on Material Control Sheet for assigned area.

Planning Engineer à Descon Engineering Qatar L.L.C
  • Qatar - Doha
  • juillet 2013 à juillet 2015

09/2014-08/2015

Descon Engineering & Construction Company Qatar L.L.C
Doha, Qatar

Project: EPC-Barzan Onshore Project, Qatar
Client: Ras Gas Ras-Laffan, Qatar.
Project Duration: 07/ 2014-08/2015

Project: Continuous Emission Monitoring System (Cems) Project
Client: Ras Gas Ras-Laffan, Qatar.
Project Duration: 04/2014-08/2014

Project: Train-01 & 02 Start-up Flare Reduction Piping Project Phase-II
Client: Ras Gas Ras-Laffan, Qatar.
Project Duration: 04/2014-08/2014

Cost Control And Planning Engineer à Olayan Descon
  • Arabie Saoudite - AlJubail
  • novembre 2011 à avril 2013

• Development of Base Line Schedule using Planning Software PRIMAVERA (P6).
• Development of detailed planning package including baseline schedule, S-curves, manpower and equipment deployments for the work scope
• Preparation of Progress Measurement System (PMS) for Project Execution.
• Development & Incorporation of Vendors Schedule in the Master Schedule.
• Develop and maintain plans and schedules deliverables at all levels of management with inputs from engineering, construction and commissioning
• Perform Contractor Schedule Diagnostics with Expertise in Delay Analysis & Extension of Time (EoT).
• Preparation of Weekly, Monthly & Three Months look-ahead Schedule.
• Preparing of Weekly and Monthly Progress Reports.
• Maintain Project Deliverables register and raising flag on delay..
• Scheduling Monthly Plan and Preparing the Planning Package.
• Updating actual Progress and all related information & comparison analysis.
• Project Scope Management and Preparing Day Work Sheet (Extra Work).
• Review and forecast Contractor Work front availability and conduct continuity of work analysis.
• Tracking and maintain scope changes of Mechanical items for Piping; Structural Steel; Piping & Mechanical Equipment’s and its effect on the overall project schedule.
• Monitoring of actual resources availability & analysis using Histogram.
• Preparing progress % calculation systems, earned man-hours, productivity & Trend analysis.
• Progress Measurement using S Curves.
• Preparation Executive Progress Summary Report to the Top Management on Project Status for periodical review.
• Evaluated and communicated the results of Work Front Analysis..
• Supervising the material management and generating Need List for Priority material.
• Monitoring the Activities of Piping, Structural and Equipment in each step of Construction.
• Monthly updation of Project Financial Status Report and generation of cost & budget forecasts
• Preparation and tracking of client invoices, subcontractor.

Internee à Haier and Ruba
  • Pakistan - Lahore
  • août 2010 à septembre 2010

08/2010-09/2010 Haier &Ruba Lahore, Pakistan
One Month Internship in A.C & Refrigerator Hall
• My duty to study the whole Production, Fabrication, Assembling and Testing system of both plants
• Worked in A.C (Split-Unit) Testing Lab with the Quality Control and Cooling Testing Team and assist them in Identifying the problem of 1.5 Tonnage A.C (Split-Unit) and made a thorough report of problem and give the recommendations.

Internee à Century Paper & Board Mills
  • Pakistan
  • juillet 2010 à août 2010

07/2010-08/2010 Century Paper & Board Mills (Lakson Group of Companies) Pattoki, Pakistan
One Month Internship in Maintenance Department under G.M (Engineering Department) Supervision.
• To study the diagrams of M.W Pulper and discuss its Gear box and Bearing Failure and give recommendation
• To study the Shoe Press and its Lubrication System
• To study the Steam and Condensate System of the P.M-7 and also identify its Problems.
• To Study the Gear Pump and T.S.P Pump and also identify its problems.
.

Internee à Crescent Bahuman Limited
  • Pakistan
  • juillet 2009 à août 2009

07/2009-08/2009 Crescent Bahuman Limited (Power Plant) Pindi-Bhattian, Pakistan One Month Internship in Power Plant, Compressor Plant & Chiller Plant
• My duty to study the whole system and identify the problem and give recommendations

SKILLS AND ACTIVITIES
• Professional Engineer Member of "Saudi Engineering Council"
• Professional Engineer Member of "Pakistan Engineering Council"
• Student Member of ASME &ASHRAE.

Éducation

Baccalauréat, Mechanical
  • à University of Engineering & Technology
  • juillet 2011

2007-2011 University of Engineering & Technology Lahore, Pakistan Mechanical Engineer

Specialties & Skills

Project Plans
PowerPlant
Oil Paint
Plant Maintenance
• H.T.R.I| Cam Duct | C++ | AutoCAD | C.N.C-Simulator| Microsoft Offices | Mat Lab| Aspin-One | Wind
AUTOCAD
CAM DUCT
SOLID EDGE
Prima Vera P3 / P6
MS Project

Langues

Urdu
Expert
Anglais
Expert
Arabe
Débutant

Adhésions

Professional Engineer Member of "Saudi Engineering Council"
  • Professional Member
Professional Engineer Member of "Pakistan Engineering Council"
  • Professional Member
Student Member of ASME &ASHRAE
  • Member

Formation et Diplômes

ISO 9001:2008 (Certificat)
Date de la formation:
May 2012
Valide jusqu'à:
August 2012
AUSPAK (Certificat)
Date de la formation:
July 2008
Valide jusqu'à:
September 2008

Loisirs

  • BOOOK READING AND RESEARCHING