Electrical Engineer
Comesvil Spa
مجموع سنوات الخبرة :12 years, 10 أشهر
Elv, Signalling & security systems Engineer
Riyadh Metro Project Line‐3, Package‐B; Scope is Power Supply Traction Power
systems (PSTP) Cables, Third Rail, PSD Systems, Signaling Installation & testing, and
Telecom installation & testing works.
Responsibilities :
* Worked as Facilities Management Engineer.
* Insulation Resistance test, Contact Resistance test & HI pot test for MV & LV cables.
Page 2 of 4
* Monitoring the installation of Third Rail system (Expansion joints, Midpoint anchor, High Speed
Ramp (HSR), Low Speed Ramp (LSR)) Track circuit etc. Insulation Resistance test, Contact Resistance
test, Hi‐pot, Flash test & Short circuit test for Third Rail systems.
* Testing of DC Dis‐connectors, DC contractors, AC/DC disconnecting panels, MV and LV Switch gear
panels, Voltage Limiting Device (VLD), Breaking Resistance units (BRU) & grounding system,
* Testing of Relays, Transformer Protection Relays, Circuit Breakers, Metering system, UPS system,
Battery system and Traction transformers etc.
* Installation, testing & commissioning of Platform Screen Door (PSD) systems.
* Testing of FO Cables (OTDR & OLTS) and telecommunication systems.
* Assisting for CBTC system pre‐commissioning activities.
* Controlling the MEP installation activities inside the stations.
3). Project Name : Power Plant‐13 (PP13, 1800MW CCPP) (Saudi Electric Company, KSA)
A Servicing company which works and focuses continuously on the energy saving
techniques in Small/Medium Scale industries such as maintaining Unity Power
Factor (UPF) always, by observing the previous/current loads in those industries.
Responsibilities :
* Improving the Power factor (0.96 to 1.00) of Industries and Companies to avoid Penalty and to get
Deduction from the State Electricity Board.
* Erection, Testing and Commissioning of ACDB’S and DCDB’S.
Page 4 of 4
* Supervising the Erection and commissioning activities of Electrical equipment such as Power
transformers, Lightning arrestor, Surge arrestor, Isolators and Earthing Switches.
* Planning, Preparation and Execution of Plant Shutdown/ Maintenance activities
(Xll)
(X)