Section Head Civil Engineer
Consolidated Contractors International Company (CCC)
Total des années d'expérience :29 years, 6 Mois
PROJECT : RABIGH OLEFIN PLANTS PROJECT, (ROPP) - SAUDI ARABIA
• Construction, controlling and management all civil work to be compliance with the approved drawings, specification and planned schedule.
• Prepare the three weeks schedule.
• Order all the steel rebars, shuttering forms and scaffolding required on site.
• Responsible for overall project activities.
PROJECT : Port Said East Container Terminal Project
• Invite the selected subcontractors, compare the issued offers and negotiate the items to reach the best price and Prepare the contracts to be signed with the successful subcontractors in coordination with the Quantity Surveying budged and the conditions of FIDIC.
• Calculating the rates and the cost breakdown for the new items.
• Preparing taking off, variations, closing the final account and cost estimates.
• Overall responsible for our Payment Certificate with the Clint and Review subcontractor invoices.
• Analyze job specification to ensure all required information for calculating cost is included.
• Secure quotations from vendors/ subcontractors on jobs.
• Perform quantity calculations and material take - off for all scope of works.
• Negotiate settlement values and Study projects costs.
• Following up the projects in technical base.
• Assessing capability and cost effectiveness of suppliers.
• Evaluate all contractual correspondence, contractor compliance, maintain records,
Evaluate and recommend claims, review subcontractor invoices.
• Construction projects pricing and contract negotiation.
• Managing quotations & tenders documents & closing business deals.
• Preparing cost estimates of projects quantities, taking off and bill of quantities.
• Analyze job specification to ensure all required information for calculating cost is included.
• Secure quotations from vendors/ subcontractors on jobs.
• Perform quantity calculations and material take - off for all scope of works.
• Negotiate settlement values and Study projects costs.
• Following up the projects in technical base.
• Assessing capability and cost effectiveness of suppliers.
• Evaluate all contractual correspondence, contractor compliance, maintain records,
Evaluate and recommend claims, review subcontractor invoices.
• Construction projects pricing and contract negotiation.
• Managing quotations & tenders documents & closing business deals.
• Preparing cost estimates of projects quantities, taking off and bill of quantities.
· Supervision the preparation of Preambles and Bills of quantities.
· Coordinating the documents & drawings for all projects of the civil, architect, mechanical, electrical and sewage departments to be compatible.
· Collecting the whole documents of the projects from all the departments referring sorting and coordinating by the computer " Excel program" and output them in a complete design including Specification, Preambles, Bills of quantities to get the total value for the tenders.
· Participated & Preparation, Bills of quantities, Preambles, Technical specifications &
Tender document of the civil works by using (CESMM3)\{Civil engineering standard
method of measurement\} plus making programs on Excel for calculation Elevated
Tank, Ground Reservoir, Fuel Tank, Valve Chamber, Clarislocculator, Thickner
Tank and Sedimentation Tank
TRAVEL TO QATAR For 3 months From 1/1/2003 to 31/3/2003
- Inspection and controlling the civil and arrangement work to be compliance
with the approved drawings, specification and planned schedules including:
drilling, grouting by cement bentonite, soft gel, hard gel, jet grout for break
in and out of the shield machines, diaphragm walls, slurry wall, shuttering forms, steel reinforcement, concrete pouring, struts, curing, repair works by non shrinkage grout, pumping tests to ensure that the grout is correct, underground excavations such as annex gallery connections, driving sheet piles.
- Carry out all works inspections as necessary and witness all the site tests
required under the contract.
- Reporting the daily activities & The N.C.Ns, F.OS(Non compliance notice,
Filed orders) and follow up the execution of the corrective actions.
- Verification that the safety plan has been approved, making sure that all
security demands are available in site.
- Check, Comment and follow up the programs prepared by the contractor.
- Check, Comment, Monitor implementation and follow up the quality
assurance and quality control procedures of the contractors for the
construction and manufacturing.
- Managing and attend the final inspection of the completed works and give comments.