ناصر تيم, Senior Contract Administrator

ناصر تيم

Senior Contract Administrator

KTCB

البلد
الكويت
التعليم
بكالوريوس, Civil Engineering
الخبرات
33 years, 3 أشهر

مشاركة سيرتي الذاتية

حظر المستخدم


الخبرة العملية

مجموع سنوات الخبرة :33 years, 3 أشهر

Senior Contract Administrator في KTCB
  • الكويت - الكويت
  • فبراير 2022 إلى مارس 2023

• assisting the client in defense against claims and legal cases raised by the contractor.
* preparing defense documents to be submitted to the expert and the Court

Contract Manager في Total Management Consutancy
  • الكويت - الأحمدى
  • أبريل 2016 إلى فبراير 2022

the Contract Manager in a project management company following up with all contractual issues and communications between the Contractor, consultants and the Client. also all activities required for Contract Administration

Project Manager في PMDC
  • المملكة العربية السعودية - جدة
  • ديسمبر 2010 إلى فبراير 2015

Project Management and Client Representatives for JDURC in urgent solutions for flood control of Jeddah.
The project is consisting of dams, channels, studies, surveying, areal surveying, construction of buildings

Supervision Director في Symbiosis Designs Ltd
  • الأردن
  • أكتوبر 2007 إلى أغسطس 2010

Following up and representing the Engineer in all contractual issues and claims raised up by the Contractors as per FIDIC conditions of Contract. and representing the clients in front of the DAB and Adjudication boards.
General technical and administration management for the supervision teams, procurement, appraisal.
Quality Assurance system audit, preparing and training.
acting as the Engineer during construction stage for all the projects supervised by the company, and supervising the project managers and their staff, coordinating with the Clients and the Construction Managements, resolving all engineering issues or coordinating with designers to resolve it.

Subcontracts Manager في Consolidated Contractors Company CCC
  • المملكة العربية السعودية
  • يناير 2006 إلى أكتوبر 2007

working in two major oil-gas projects as the contracting manager for all pre-award stage and the Subcontracts Manager during the construction stage. 38 subcontrcators were reporting to the department.

Project Manager في Symbiosis Designs Ltd
  • الأردن
  • يوليو 2005 إلى يناير 2006

Supervising the construction of 20, 000 m2 commercial complex and acting as the Engineer's Representative at site.

CQC- Engineer في CH2M Hill/Dragados/Soluziona JV- ENGICON sub-contractor
  • الأردن
  • أغسطس 2004 إلى أبريل 2005

Fast track airport project to be completed within very short period under high pressure. QC team is responsible for complete compliance with Contract requirements in addition to the coordination with the Corps of Engineers. .
Project Components: Taxiway, Parking Ramp, Road and Electrical services.
Project budget:11 million US$

Senior Engineer في Pacific Consultants International in Association with Consolidated Consultants
  • الأردن
  • سبتمبر 2001 إلى يوليو 2004

Project is consisting of 7 different sub-projects with a total contract value of around 50 million JD. Each project includes renovation of existing utilities, or constructing new project’s elements such as museums, restaurants, lookouts, buildings, underground infrastructure, roads, sidewalks, bridges, landscapes, and parking zones.

Duties: -
• Senior Engineer participating in project management.
• Senior Material Engineer:

Responsibilites:-
• Contracts, correspondences and claims management.
• Reviewing Monthly and final Payments.
• Cost estimation for sub projects
• Preparations of Variation Orders.
• Preparation of Contracts Documents.
• Closing Contracts.
• Letters to the Employer and Contractors.
• Auditing Meetings and conducting site inspections.
• Preparation of Monthly and Quarterly Progress Reports.
• Coordination with the related Agencies and Authorities.
• Selecting the site representatives and the supervision team.
• Evaluating Subcontractors abilities to conduct their parts of work.
• Work programs.
• Shop drawings and design changes.
• Monitoring and assisting site supervision stuff.

Site and Material Engineer في SBA Dar Al-Omran
  • الأردن
  • مارس 2001 إلى سبتمبر 2001

Project Name: “Supervising the construction of Wadi Musa Pump Station Bridge, and the construction of the road from Al-Baida to Wadi Musa treatment Plant”
This project is consisting of two sub-projects, the first project is constructing a bridge from the main street to the pump station in Wadi Musa, The second project is constructing a road from Al-Baida area to the treatment plant in Wadi Musa also, with all related works such as slope protection, gabion, box culverts, pipe culverts, …etc.
Duties: Site and Material Engineer.

Project Manager في “Arabian Gulf company”
  • المملكة العربية السعودية
  • سبتمبر 1998 إلى ديسمبر 2000

Project executed was reconstruction of a highway expanding over 56 km from Abha to Jezan, drinking water network to the adjacent villages, rainwater drainage sub-system, 38 box culverts, 5 multi span prestressed concrete bridges, gabion, slope protection, earth works, guard rails, newjersy, irish crossings, ...etc. Value of the project is around 100 million SR.

Responsibilites:-
• Technical and financial administration
• Letters and site memos to the Employer and the Engineer
• Auditing Meetings and conducting site inspections
• Coordination with the related Agencies and Authorities
• Evaluating, monitoring and supervising subcontractors’ abilities to conduct their parts of work
• Preparing and/ or reviewing work programs, shop drawings, progress payments, and as built drawings
• Organizing the work teams to follow up with the quality control procedures

Technical Manager, Site Engineer, Material Engineer في Al-Yarmouk Center For Engineering Researches And Studies
  • الأردن
  • يناير 1992 إلى سبتمبر 1998

My duties during this period were enormous, but the main position was Technical Manager in which the following duties were assigned to me:
• Contracts, correspondences and claims management.
• Reviewing Monthly Payments.
• Preparations of Variation Orders.
• Preparation of Contracts Documents.
• Closing Contracts.
• Letters to the Employer and Contractors.
• Auditing Meetings and conducting site inspections.
• Preparation of Monthly and Quarterly Progress Reports.
• Coordination with the related Agencies and Authorities.
• Selecting the site representatives and the supervision team.
• Evaluating Subcontractors abilities to conduct their parts of work.
• Work programs.
• Shop drawings and design changes.
• Monitoring and assisting site supervision stuff.

Material testing and Site Investigation Engineer في Jordanian Technical Engineering labs
  • الأردن
  • أغسطس 1991 إلى فبراير 1992

Engineer in "Site Investigation" Section, and "Material Testing & Asphalt" Section in central independent testing laboratory.

Material Engineer في Al-Sharq Establishment for Soil and Material testing
  • الأردن
  • نوفمبر 1990 إلى يوليو 1991

Engineer in soil and material testing section

Lab Engineer في Slovania Cista Technica (SCT)
  • الأردن
  • مايو 1990 إلى سبتمبر 1990

lab engineer in mulit million international project. the project was constructing of 60 km highway with all related services. The project ended before completion due to war.

Engineer under supervision في Jordan Army
  • الأردن - عمان
  • مارس 1988 إلى مارس 1990

Work was construction of buildings, roads and infrastructure.

الخلفية التعليمية

بكالوريوس, Civil Engineering
  • في University of Jordan
  • يناير 1988

Specialties & Skills

Construction Management
Project Management
Contract Management
Construction Management
Contracts Management

اللغات

العربية
متمرّس
الانجليزية
متمرّس

العضويات

Jordanian Engineering Association
  • Active member
  • January 1988