Project Manager
Larsen and Toubro limited
مجموع سنوات الخبرة :15 years, 4 أشهر
Client: Kahramaa & EDF
Ÿ Managing Construction: Responsible for overseeing the construction of a 400kV substation, ensuring timely completion and adherence to project specifications.
Ÿ Installation and Commissioning: Supervise the installation, testing, and commissioning of a 400kV, 60MVAr Shunt Reactor and associated cabling work.
Responsible for defect works in Manateq Project.
Involved in replacement of faulty Auxiliary Transformer at RAF3 Substation.
Responsible For Erection of 132/11kV Substation
Inspection of Work completion for ECF and Monthly progress review.
Responsible For Erection of 66/11kV Substation
Inspection of Work completion for ECF and Monthly progress review.
Responsible For Erection of 66/11kV Substation
Inspection of Work completion for ECF and Monthly progress review.
Responsible For Erection of 66/11kV Substation
Inspection of Work completion for ECF and Monthly progress review.
Responsible For Erection of 66/11kV Substation
Inspection of Work completion for ECF and Monthly progress review.
Responsible For Erection of the 132/22kV Substation
Preparation of Red Markup drawings
Inspection of Work completion for ECF and Monthly progress review.
Responsible For Final ECF Clearance and documentation for NOSP.
Preparation of Red Markup drawings
Responsible For Erection, Testing and Commissioning of the 132kV Substations at Kindaruma, Mwingi and Garissa
Responsible For Erection, Testing and Commissioning of the Substations at Olkaria 1AU, Olkaria 2 and Olkaria 4
Responsible For Erection of 220kV Switchyard at MIHAN - SEZ
Responsible For Erection of 132kV Switchyard at Jharsuguda. Odisha