Estimating Engineer / Structural Steel Division
G.P.Zachariades
مجموع سنوات الخبرة :16 years, 6 أشهر
July 2010 - Present G.P.Zachariades ( Bahrain)
Estimating Engineer / Structural Steel Division
* Responsible for costing and estimation of assigned projects from proposal to bid completion.
* Responsible for ensuring that the package for submittal to the client meets all client requirements.
* Checks that all client comments have been incorporated. The PM assures that the package has been through all relevant checks in line with the QA/QC manual.
* Prepares and coordinates the project schedule and maintains this throughout the project.
* Optimizes the use of personnel to achieve the schedule. Forecasts and addresses deviations to schedule.
* Responsible for the total administration of the project in line with procedures. Attends and minutes all project meetings. Maintains project master files. Handles all project communication with the clients.
* Assures efficient dissemination of data to the project team and assists the lead discipline engineers with co-ordination. Co-ordinates staffing of the project with the Design Manager.
* Prepares all project reports required, internally and externally, with the assistance of Project Support Services where required.
* Responsible for assuring that all of the Project Team are familiar with the scope of the project.
* Responsible for assuring that all scope changes are maintained on a trend log and are promptly transmitted to the client for resolution.
Sept 2009 - June 2010 Haji Hassan Engineering, Bahrain
Mechanical / Project Engineer
* Prepare market study and proposal for Haji Hassan Engineering products for Oil and Gas, particularly Heat Exchangers and Pressure Vessels, Structural steel fabrication, , Tanks, Silos, Hoppers, Chute, Platforms, Miscellaneous items.
* Knowledgeable with ASTM Codes and other codes/specifications
* Set meeting with clients for possible sales
* Maintain good Client relationship and good work ethics
* Estimate material and labour cost for each project.
* Prepare correspondence very well
* Understand market movement and react with positive activities to achieve win win situation for the company.
July 2008 - August 2009 Haji Hassan Engineering, Bahrain
Estimation Engineer
* Prepare all estimation, material take off and project cost analysis
* Evaluates project requirement with respect to manpower, equipments, materials and services to provide extensive and feasible approach to project completion.
* Monitoring of work in progress and daily update of inquiries, quotations from clients.
* Prepare all correspondence / submittals as required by client and maintain documents for future references.
* Prepare job cards and input all information to provide detailed and comprehensive data, for issuance to shop floor.
* Communicates with the project team to be able to share information that is relevant to the project and provide updates crucial to project execution.
* Company products includes pressure vessels, silos, heat exchangers, structural, storage tanks, machining works
Projects Handled: • Maintenance works for ALBA including machining works and repair for conveyors, material handling equipments and general machining for spare parts like gears, bushes and others.
• Fabrication works for ALBA and GPIC for storage tanks, silos, chutes, hoppers and bins
• Structural works for GIIC for bucket elevator and 120 ton structural steel structure with staircase.
• Fabrication of Pipe Supports for Degremont France ( Al Dur Project)
• Sub Contractor for Shaw Nass for all pipe spool fabrication and preparation.
• Regular sub contractor for Heat Exchanger repair for Anabeeb Qatar for QChem, and Qapco.
July 2005-Jan 2008 Arabian Asdaf Al Khobar, KSA
Project Engineer/ Contracting Engineer
* Engineer-in-charge for all company's projects and directly reporting to the Project Manager / General Manager.
* Responsible in preparing all projects' planning & schedule in coordination with the Project Manager.
* Monitors work progress, update schedule and give feedback to the Project Manager and clients' representatives.
* Directly in-charge for all projects' material take-off and has full access to the procurement process to facilitate material sourcing and follow-up.
* Supervise company's workshop (Steel Fabrication) fabrication operations to maximize manpower and minimize material wastage.
* Quantifies number of hours to fabricate structural steel and miscellaneous metals.
* Determines installation schemes to establish crew sizes and duration.
* Evaluates all contract documents including all bid drawings, specifications, general conditions and if necessary the project site.
* Determines scope of work for our trade and determines vague areas to qualify bids.
* Assists Project Management staff with pricing issues on major project revisions.
Projects Handled:
* Supply, Fabrication and Erection of Galvanized Steel Frame for Transformer Shade - Substation 30 & 31 @ 3rd Sharq Expansion Project in Jubail
* Maintenance & fabrication works for ALUPCO.
* Supply, Fabrication and Installation of Transformer Oil Tanks (8 nos.) with 100, 000 liter capacity for WESCOSA - Dammam 1st Industrial
* Supply, fabrication of 2 nos. 150, 000 liters capacity Oil Storage tank for Saudi transformer, Dammam, K.S.A.
* Supply, Fabrication and Erection of Galvanized Steel Frame for Transformer Shade - Substation 37 and 35 for N. S. Al Hajri, Jubail.
* Fabrication for Zamil Steel (Structural Steel Division) - Subcontractor for Handrails, Stringers, Structural Steel members (500 tons)
* Supply, Fabrication and Erection for 8 Silos for Afico, !st industrial, Dammam, K.S.A. Complete with Structural Support and Piping. ( 120 tons)
* Painting works for Ministry of Health (sewerage and waste water system, Dammam - Main Contractor - CWC Al Khobar - 132, 000 sq. m.
* Erection works at Hawiyah Gas plant for 3, 000 tons Pipe Racks For Aramco Main Contractor - Gama Industry Arabia Limited
* Erection Works for fire fighting for REDA Fire Fighting Division. - @ Yanbu, 3750 Linear meter, various pipe sizes including fire pump, jockey pump installation
* Installation of Pipe Racks and Pipe Supports for Jubail project - Main Contractor - S.A. . Kent Arabia.
2002 - 2004 Al Oloub Contracting Est. Jeddah, KSA
Project Engineer (Mechanical)
* Maintains good relations with the client and coordinates the activities of the different departments/ disciplines participating in the projects
* Providing input into tendering and business development processes
* Engaging people and managing teams and their performances
* Act as a focal point for information exchange and communication between the client and the Lead Engineers;
* Managing variations in the scope of work and settling issues related to additional or less work;
* Taking actions that are necessary to achieve the objectives as laid down in the approved project plan.
* Meet all quality and HSE standards and requirements
Projects Handled:
* Erection of 50 meters high lightning mast at Hufuf Football Stadium.
* Supervision of fabrication of steel structure for warehouse/hangar ( Zamil standard)
* Erection of SILO (20 tons) at Binzagr Lever (Jeddah)
* Fabrication and erection of offloading catwalk (30 tons) at Binzagr Lever (Jeddah)
* Engineer-in-charge for projects awarded by Binzagr Arabia to our company (Painting, Renovation, Construction, Tileworks, Shifting of Machineries, maintenance for all conveyor systems and material handling equipments etc.)
1999 - 2001 Keylargo Industrial Sales Quezon City, Phils.
Sales and Application Engineer / Cost Estimator
* Well verse in the field of pumps and its applications such as submersible, end suction, horizontal split case and fire pumps.
* Provide strategic and feasible solution to problems with regards to water treatment, sewage and sewerage applications.
* Do maintainance for pumps and piping for power plants, manufacturing plants and others. particularly with feedwater requirements and treatment of discharge and effluents.
* Design water distribution and water application for clients.
* Sales and Applications Engineer for water pumps and other water related accessories.
* Material take-off for projects awarded to our company.
* Design Engineer for LWUA-JAICA funded water district projects (Region I, II and Central Luzon)
* Supervise pipe laying projects for water districts (3" dia. To 18" dia. Black iron steel pipes, u PVC pipes)
1998 - 1999 Toyota Auto Parts Phils. Manila, Phils.
Maintenance Engineer
* Checking of machineries.
* Strategic scheduling of maintenance works and Preventive maintenance for various machineries.
* Recording and timekeeping of periodic maintenance schedule.
* ISO 14000 officer for machineries and equipment.
* Machines maintained - Boring, milling, lathe, cutting, shearing and other machines used in fabrication of gears and other transmission components for Toyota
1996 - 1998 System Builders & Industrial. Contractors Manila, Phils.
Project Engineer ( Cadet)
* Project Engineer for projects awarded by client (Motorola Phils.)
* Estimates and prepares bill of quantities
* Materials take-off for awarded projects.
* Supervise workers, Prepare Timesheet.
* Ensure target completion of projects.
* Maintain good client to office relationship.
* Projects include minor civil works i.e. partitions, painting, tileworks, repair and maintenance for HVAC applications