Work history in KSA
» Tabuk substations
· Tabuk 380 KV/132/33K)V Testing Protection panel for (3)Auto transformers 380/132 KV.
· Tabuk 380 KV/132/33KV Testing transformer protection relays (SEL 487E, Siemns 7SA, Micom P543 and SEL 451E).
· Tabuk 380 KV/132/33KV Automatic Voltage Control AVC panels scheme check and relays.
· Tabuk 380 KV/132/33KV transformers 132/33Kv stability test.
· Tabuk 380 KV/132/33KV auto transformers 380/132 Kv stability test.
· Tabuk 380 KV/132/33KV 132 Kv line feeders trip test.
· Duba green 380/132/13.8Kv 132KV Hyundai GIS LCC scheme check.
· Duba green 380/132KV 380kv Breaker failure PP scheme check.
· Duba Green BsP 380/132Kv Tr.1 380/132/13.8Kv Stability.
» Mekkah substations
· HVM ss 380/110/13.8KV Tr1, Tr2 &Tr.3 110/13.8 kv Protn panel replacement
(Micom P643, P142)
· Al-Shisha ss 110/13.8Kv Line feeder Protection-panel replacement (Alstom Micom P543-SIEMENS 7SD52)
· Univ. ss 110/13.8 kv Line feeder Protection-panel replacement (Alstom Micom P543-SIEMENS 7SD52).
· JQB ss 110/13.8kv Tr1, Tr2 &Tr.3 110/13.8Kv Protn panel replacement (Micom P643, P142).
· S.Azizia 380/110/13.8Kv Tr.4 110/13.8 kv Protn panel replacement (Micom P643, P142).
· MNA2 ss 110/13.8kv Tr.2 110/13.8 kv Protn panel replacement (Micom P643, P142).
· SBK ss Tr.2 110/13.8 kv Protn panel replacement (Micom P643, P142).
· Aljamom2 Capacitors 1, 2 PP testing (GE C70, SEL 478V).
· Aljamom2 UF/OF 13.8kv testing (Siemens 7RW).
· Aziza 3 testing 13.8Kv Switchgear scheme testing.
· Azizia 3 DCDP panel interfacing and scheme.
» Jedah substations
· KFH ss 110/13.8Kv 110 Kv Hyundai GIS LCC function scheme check.
· KFH ss 110/13.8Kv 110KV Hyundai GIS SF6 gauge calibration.
» Al-Taif substations
· Al-Muya ss 110/33/13.8 Kv Telecom-panel installation and interfacing.
· Massara ss 110/13.8 Kv Al-hada 2 OHL 110 kv protection panel installation and interfacing.
Perform function scheme check for protection panels, make interfacing and modification if required.
•Testing (power transformers, line-feeder) protection panels, perform stability test, closed loop test and trip test.
•Testing, commissioning digital and numerical relays
•Testing and reporting all the components of the High Voltage Transmission lines as (current transformer, voltage transformer, circuit breakers).
•Performing Commissioning and reporting for current transformers C.T (insulation test, saturation test (magnetic curve), polarity test and ratio test)
•Performing Commissioning and reporting for voltage transformers (insulation test, and ratio test, ).