Doha Central and Corniche Beatification Package 1, 2, 2A & 3
Organization Name: Parsons international
• Role: Senior Resident Engineer
• Project Scope: Doha Central Development and Beautification Projects aims to make Doha City Centre ‘A Destination of Choice’. A city, meet the needs of its people and visitors, and create memorable experiences by linking people to places and destinations through a convenient, safe, and accessible public realm where Central Doha’s landmarks become points of destination that help users create their own mental map of their surrounding environment. This is through providing pedestrian-friendly transportation including footpaths and crossings to encourage visitors using various modes of transportation, and to promote walking by connecting all lively centers in the area. Implementing the complete vision of development of the area will contribute in enhancing the identity of Qatar's historical and cultural legacy, and recognizing the natural environment of Qatar.
Package 1, 2, 2A And 3 Projects aims to develop the areas surrounding National Museum of Qatar and areas opposite to Museum of the Islamic Art, through developing and beautifying main streets and internal neighborhoods in these areas, in addition to the infrastructure development works.
• Location: Doha, Qatar • Time: April, 2019- to date





Responsibilities:
 assist the Engineer in administering the operational functions of the day-to-day activities on the project
 Direct the site supervision related to site construction and associated works for all infrastructure Works.
 Coordinate his direct activities with the other discipline to maintain consistency and integrity in the overall construction.
 Coordinate with design team for resolution of related issues.
 Act positively and participate in all health and safety issues at site, as required by the Senior Resident Engineer, and the Project Safety Representative.




Enabling Works for Construction of 3 Corniche Pedestrian Underpasses
Organization Name: Parsons international
• Role: Senior Resident Engineer
• Project Scope: The project includes Construction of the Temporary Traffic Management (TTM) Phase-1, Design (as it relates to traffic management, shoring system and provision of dewatering system) and Construction of the Enabling Works for the following three pedestrian underpasses, 1.Al Bidda Pedestrian Underpass 2. Corniche Metro Pedestrian Underpass 3. Al Dafna Pedestrian Underpass Scope
• Location: Doha, Qatar • Time: July, 2019- December, 2020

Al-Bustan South Street
Organization Name: Parsons international• Role: Resident Engineer • Project Scope: Al Bustan project upgraded to a dual carriageway with minimum of 4 lanes in each direction from South of Rayyan Road Junction R6 to South of Al Waab Street Within the project limit the mainline Al Bustan Street at Junction B1, where Al Waab Street intersects with Al Bustan Street: a three-level interchange shall be constructed with a signalized at-grade
junction. At Junction B2 where Al Khufoos Street (Al Rasheeda) intersects with Al Bustan
Street: a two-level interchange shall be constructed with a signalized at grade.
• Location: Doha, Qatar • Time: April, 2018 to July, 2019

Construction Project Manager في Al-Jaber Engineering
  • قطر - أم سعيد
  • أغسطس 2016 إلى أبريل 2018

New Orbital Highway Truck Route P023
Organisation Name: AL Jaber Engineering • Role: Project Manager• Project Scope: 57 Km of roadworks with 5 Main Interchanges, 24 no. bridge structures, 18 no’s Braiding and Emergency exists, Pedestrian and Bicycle paths with appropriate underpass structures • Location: Doha, Qatar • Time: 2016 to 2018
 Secure 12Km Qatar Petroleum gas lines by excavation, casting concrete Foundations, installing Arches, and filling works around.
 Organize method of statements and provide to Qatar petroleum for approval, ensuring all work delivered in accordance with the specifications.

Construction Project Manager في Daewoo Engineering & Constructio
  • قطر - الخور
  • أكتوبر 2015 إلى أغسطس 2016

New Orbital Highway & Truck Route P023
Organisation Name: Daewoo Engineering & Construction • Role: Project Manager • Project Scope: 44 km new dual carriageway that includes five grade-separated interchanges • Location: Doha, Qatar • Time: 2015 to 2016
 Oversaw all onsite and offsite constructions two interchanges including bridges Box Girder type, four underpasses, as well as acquired material and monitored stocks to timely handle inadequacies.
 Collaborating with engineers and architects to determine the specifications of the project.
 Reviewed the project in-depth to schedule deliverables and estimate costs.

Construction Project Manager في Shibh Aljazeera Contracting
  • المملكة العربية السعودية - الرياض
  • يوليو 2005 إلى أكتوبر 2015

Wasit Bridge and Access Road in Jubail
Organisation Name: Shibh Aljazeera Contracting Company • Role: Project Manager • Project Scope: new road construction of 20 KM and a bridge of 4 spans precast post-tensioning girders and street lighting • Location: Eastern Province, KSA • Time: 2013 to 2015
 Constructed four-span Bridge, and two 20km roads in accordance with specifications and agreements.
 Reviewed and prepared contracts, permits, drafts, cost estimates and insurance.
Concrete Works in Jeddah Branch
Organisation Name: Shibh Aljazeera Contracting Company • Role: Project Manager • Location: Jeddah, KSA • Time: 2010 to 2013
 Spearheaded all construction activities of seven bridges, precast post tension girders length from 30m to 41.5 m, and 15 culverts, as well as monitored all operations of four concrete patch plants.
Riyadh Ring Road North West Leg
Organisation Name: Shibh Aljazeera Contracting Company • Role: Construction Manager • Project Scope: Consists of four paths for traffic in addition to shoulders of pot-holed, project includes 3 VAI DUCT BRIDGES • Location: Riyadh, KSA • Time: 2005 to 2010
 Conduct various functions such as Drilling and casting of piles in viaduct bridges with total depth of the pile between 14 meter and 34 meters.
 Completed steel and formwork of the columns in the viaduct bridges with climbing forms to 100 m height.
 Finalised steel and formwork of crosshead with hydraulic lifting System at height 34 meters in agreed time.
 Casted 300 precast post tension girders length 40m and height 2.44m.

Site Engineer في , Emirates Road Contracting Company
  • الإمارات العربية المتحدة - الفجيرة
  • نوفمبر 2001 إلى مايو 2005

Projects; AL HAYL - Ohala Road in Fujairah Emirates, Section | Umm Al Quwain - Falaj Almualla - Dhaid Road| Maintenance of Airport Road in Ras Al-Khaimah

الخلفية التعليمية

بكالوريوس, Civil Engineering
  • في JOEDANAIN UNIVERSITY OF SCIENCE AND TECHNOLOGY
  • نوفمبر 2001
بكالوريوس, Civil Engineering
  • في Jordan University of Science & Technology

in

Specialties & Skills

BRIDGES
BUDGETING
CONTRACT MANAGEMENT
FILE MANAGEMENT
FORECASTING
INSURANCE
LEADERSHIP TRAINING
MICROSOFT WORKS
CUSTOMER RELATIONS

اللغات

العربية
اللغة الأم
الانجليزية
متمرّس