WORKED AS A QA QC INSPECTION ENGINEER (INSPECTOR) IN HPCL MUMBAI.
Job Title: QA QC ENGINEER (PIPING, WELDING, NDT, TANK AND STATIC EQUIPMENT)
Duration: From MAY-8 2014 TO JUNE 10 2014.
Owner: HPCL-MUMBAI.
Company: IRS (INDIAN REGISTER OF SHIPPING/INDUSTRIAL)
Project: LUBE REFINERY SHUT DOWN (PDU PLANT)
WORKED AS A QA QC INSPECTION ENGINEER (INSPECTOR) IN HPCL VISAKHAPATTANAM
Job Title: QA QC INSPECTOR (PIPING, TANK AND STATIC EQUIPMENT)
Duration: From APRIL-8 2014 TO MAY-6 2014.
Owner: HPCL VISAKHAPATTANAM.
Company: RADIANT ENGINEERS.
Project: NHT-CCR SHUTDOWN.
ROLES AND RESPONSIBILITIES: ➢ Pre-visual inspection of all equipments like pressure vessels, Drums, Reactors, Furnace (Heater), Heat Exchangers, Surge drums, Columns, Towers and tanks etc.
➢ Inspection after Cleaning / Chemical Cleaning, &list out the repair activities in accordance with procedures and standards.
➢ Inspection after repair in Heat Exchangers like Tube, Tube sheet change, Ferrule Inspection, Plugging, Seal welding of tubes, Hydro test shell &Tube sides etc.
➢ Visual Inspection of Reactors/Reformers removal & loading of Catalyst, Hydro test of Coils & final Box-Up Inspection.
➢ Inspection of Drums & Vessels for its Mechanical Integrity, review of all NDT Related activities & final Box - Up.
➢ Visual Inspection of Crude Column, Identifying damaged trays, Chimney trays, Removal & install of new trays, Hydro test & final Inspection.
➢ Removal of Old valves & repair, D.P Test, Thickness measurement records review, & re - installation of Valves.
➢ Doing the Inspection of piping loops, heat exchanger, pressure vessels, drums, furnace, columns, tanks and reactor.
➢ Review of NDT documents and PWHT charts and interpretation of film.
➢ Doing internal inspection of drums, vessel, heat exchanger, tanks, column (Trays, steam coil, distributor headers, etc),
➢ Witnessing and review of thickness spot on piping lops, and other equipment parts (shell, steam coil, distributors, impingement plates)
➢ Inspection of equipment nozzles and other support joints.
➢ Witnessing DPT of all seam joints and T joints.
➢ DPT of all nozzles joints from inside of the static equipments.
➢ Witnessing of DPT of all RF pad and air test of RF pad.
➢ Witnessing of hydro test and leak test of all static equipments and piping loops.
➢ Witnessing and reviewing all NDT Techniques (PT, MPT, WFMPT, LRUT, RT AND UT)
➢ Witness Hydrostatic pressure/leak/pneumatic test OF PIPE LINES, RF PADS, VESSELS AND COLUMNS AND FURNACE, HEAT EXCHANGER, AND TANKS.
➢ Witnessing shot blasting, painting and re-insulation.
➢ Witnessing the cold component application on heat exchangers components.
➢ Familiar with ASME Section II, ASME Section V, ASME Section IX, ASME B 31.3, API - 570, API-510, API-620 and API-650.
WORKED IN YANBU ARAMCO SINOPEC REFINING COMPANY (YASREF) LTD IN SAUDI ARABIA AS A QA QC ENGINEER IN NSH (NASSER S. AL-HAJRI) - IN DELAYED COKER UNIT.
Job Title: QA QC INSPECTOR (PIPING/STATIC EQUIPMENTS)
Duration: From 20/07/2013 TO 17/10/2013.
Owner: SAUDI ARAMCO
Client: TECHNICAS REUINADS
Company: N-S-H (NASSER S. AL-HAJRI)
KEY RESPONSIBILITIES
➢ Preliminary and detailed analysis of pipeline, pipe routing.
➢ Stage wise inspection before, during and after fabrication in accordance with the specification and standards.
➢ Verification of hydro-test packages, mechanical completion packages.
➢ Ensure that all inspections are performed in accordance with the project requirement, specification, acceptance criteria and international standards.
➢ Witnessing hydro testing & air leakage test of piping spools.
➢ Inspect lines in accordance with P&ID & isometric drawings for mechanical clearance.
➢ Checking fit up &welding inspection (before, during, &after) as per approved WPS, test plan, relevant engineering drawing, international standard & project specification.
➢ Familiar with basic welding techniques like SMAW, TIG, SAW, GMAW, FCAW etc.
➢ Arranging NDT preventive maintenance progress upon schedule and responsible for proper inspection request. Verify that the NDT and tests have been carried out as per request review of QA/QC part of final documentations.
➢ Review of Inspection & Test Plan, material verification, all stage of inspection, Dimensional inspection, Welding inspection.
➢ Identify the material (pipes, flanges, fittings, etc) as per the material take off list and isometric drawings during the fabrication.
➢ Welding inspection activities (fit-up, preheat, root pass, inter-pass temperature, hot pass, post heating, PWHT & visual inspections.
➢ Familiar with reinstatement of piping systems after completion of all hydro testing activities. Responsible for counter checking by Isometric/Piping plan for the spools erected in the correct location, orientation, alignment and plumpness.
➢ Carrying out final P&ID check of installed piping systems in the module.
➢ Preparation of "AS BUILT" drawings.
➢ Responsible for carrying out Mechanical Clearance, Conducting Hydro and Pneumatic tests, fulfilling commissioning and Pre-Commissioning requirements for the project.
➢ Ensure that all punch list items are resolved; client handover is satisfactorily concluded and that there is no prolongation of project.
➢ Familiar with ASME Section II, ASME Section V, ASME Section IX, ASME B 31.3, ASME B 31.4, ASME B 31.8, API - 570.
➢ Familiar with ARAMCO codes and standards like SAES-L-150 & SAES- L-350.
➢ Familiar WITH SAUDI ARAMCO STANDARD DRAWINGS (SASD) AND SAUDI ARAMCO MATERIAL SYSTEM SPECIFICATIONS (SAMSS)
WORKED AS A QA QC ENGINEER IN LARSEN AND TOUBRO LTD.
Job Title: QA QC PIPING ENGINEER
Duration: From SEPT 2011 to JUNE 2013
Owner: KERALA WATER AUTHOR.
Company: LARSEN AND TOUBRO PVT LTD.
PROJECT: KOZHIKODE WATER SUPPLY PROJECT
KEY RESPONSIBILITIES
➢ Familiar with the inspection of pipe lines, visual, verification of correctness and identification.
➢ Check isometric drawing for correct revision and spool fabrication.
➢ Material inspection for incoming materials and review of material certificates to check compliance to project specification.
➢ Control of welding process as per applicable WPS & PQR requirements.
➢ Ensure that all inspections are performed in accordance with the project requirement, specification, acceptance criteria and international standards. Responsible for submission of all final reports to clients.
➢ Witnessing NDT tests and air test for pipe joints.
➢ Checking consumable type, condition, size etc in process inspection.
➢ Witness welder qualification test in association with approved WPS.
➢ Doing the underground pipe line inspection of HDPE, DI, MS pipe lines.
➢ Doing hydro test inspection after the completion of each one kilometers.
➢ Familiar with hydro testing procedures and reinstatement procedures.
➢ Witnessing field joint coating and inner lining.
➢ Familiar with material inspection, dimensional check and documentation as per construction material standards.
➢ Confident to handle the construction and quality control activities as specified in the drawings and applied standards and specifications.
➢ communicating with my team members regarding the activities to be carried out for work growth.
➢ Review of Inspection & Test Plan, Material verification, stage wise inspection, dimensional inspection, and welding inspection.
➢ Attending daily/weekly, monthly meeting with client to clarify all technical issues.
➢ Handling all piping technical queries and investigating all field pipe work related problems, including the drawing of field sketches when necessary.
➢ Coordinating with Engineering and Construction and liaise with the Client on detail engineering requirements.
➢ Responsible for Piping erection operations and pipe support installation in accordance with schedule, Procedures, Specifications, Priorities and Availability of Construction Drawings
➢ Ensure the Productivity and Quality is maintained by subordinates. Coordinate with other Disciplines in site.
➢ Assist Design Department in solving Piping Modification and Technical Problems in the Field.
➢ Provide technical answers to Engineering Queries raised up by the sub-contractor confirming design drawings and standard requirements.
➢ Responsible for counter checking by Isometric/Piping plan for the spools erected in the correct location, orientation, alignment and plumpness.
➢ Carrying out final P&ID check of installed piping systems in the module.
➢ Preparation of "AS BUILT" drawings.
➢ Responsible for carrying out Mechanical Clearance, Conducting Hydro and Pneumatic tests, fulfilling commissioning and Pre-Commissioning requirements for the project.
➢ Ensure that hydro test reinstatement is to be done as per procedure.
➢ Ensure that all punch list items are resolved; client handover is satisfactorily concluded and that there is no prolongation of project.
WORKED AS QA QC PIPING INSPECTOR IN NEQ STRUCTO CONSTRUCTION LIMITED FOR THE CONSTRUCTION OF LNG GAS TERMINAL KOCHI SITE.
Job Title: QA QC PIPING INSPECTOR.
Duration: FROM 05/01/2010 TO 29/08/2011.
Owner: PETRONET
Client: CINDA
Company: NEO STRUCTO CONSTRUCTION LIMITED
Project: LNG GAS TERMINAL KOCHI
KEY RESPONSIBILITIES
➢ Review of Project specification and P&ID s.
➢ Control of welding process as per applicable WPS & PQR requirements. Have been experienced and well versed with codes like ASME-B31.3/31.1, AWS- D1.1, API-570, API-620, API-650 etc.
➢ Handling all piping technical queries and investigating all field pipe work related problems, including the drawing of field sketches when necessary.
➢ Coordinating with Engineering and Construction and liaise with the Client on detail engineering requirements.
➢ Develop Construction Engineering Technology in line with Company Policy and Procedures.
➢ Elaborates construction feasibility analysis evaluating the available materials & drawings.
➢ Responsible for Piping erection operations and pipe support installation in accordance with schedule, Procedures, Specifications, Priorities and Availability of Construction Drawings
➢ Ensure the Productivity and Quality is maintained by subordinates. Coordinate with other Disciplines in site.
➢ Monitoring the daily work activities of Sub Contractor and updating Sub Contractor Progress Reports.
➢ Assist Design Department in solving Piping Modification and Technical Problems in the Field.
➢ Responsible for counter checking by Isometric/Piping plan for the spools erected in the correct location, orientation, alignment and plumpness.
➢ Carrying out final P&ID check of installed piping systems in the module.
➢ Preparation of "AS BUILT" drawings.
➢ Preparation of field piping system test packages, including system limit on P&ID and piping Isometrics.
➢ Responsible for carrying out Mechanical Clearance, Conducting Hydro and Pneumatic tests, fulfilling commissioning and Pre-Commissioning requirements for the project.
➢ Responsible for line checking after hydro test to complete the post punch list prior to sign-off the test packages before signing the completion of piping / mechanical.
➢ Ensure that hydro test reinstatement is to be done as per procedure.
➢ Ensure that all punch list items are resolved; client handover is satisfactorily concluded and that there is no prolongation of project.
- Job role:
-
Quality Control