Total years of experience :28 years, 1 Months

Sr. Process Engineer at Haji Abdullah Alireza & Co. Ltd.
  • Saudi Arabia - Jeddah
  • My current job since May 2013

Haji Abdullah Alireza & Company (HAACO) acquired part of the water business of SETE Energy Saudia along with 130 personnel of SETE in January 2013. Presently I am working as Sr. Process Engineer providing engineering support for O&M of water treatment plants and new BOOT tenders. I am also involved in the tenders preparation of GE medium speed diesel generators and auxiliaries.

Sr. Process / Proposal / Project Engineer at SETE ENERGY SAUDIA
  • Saudi Arabia - Jeddah
  • April 2004 to April 2013

Project: 48, 000 M3/D INDUSTRIAL WASTEWATER TREATMENT PLANT - MARAFIQ YANBU (IWTP-II)
Reviewed process design, issued RFQs to equipment vendors and evaluation of vendors’ proposals during the tender stage. Worked as Sr. Process and Project Engineer during the detailed engineering and project execution stage. Attended design review meetings with JACOBS/MARAFIQ in Saudi Arabia and visited Foster Wheeler (Engineering partner) offices in Milan (Italy) from February 2010 to November 2010 to perform engineering coordination and finalization of P&IDs & other design documents. I was also involved in developing the plant operation philosophy and control logics in collaboration with Foster Wheeler. Participated in the HAZOP study and was in charge of closing out the HAZOP recommendations. Participated in the DCS design review, Pre-FAT and FAT in Emerson offices Dubai to elaborate the operation philosophy of overall plant as well as individual packages. I was also responsible for the engineering coordination of the following packages ensuring that these packages are delivered compliant with the contractual requirements, RC Standards and within the budget and time schedule:
- Dissolved Air Floatation Units (De-oiling)
- Dissolved Air Floatation Units (Biological)
- Chlorine Gas Injection System
- Polyelectrolyte Preparation and Dosing Packages
- Tertiary and Granular Activated Carbon (GAC) Filtration Systems
- Exhausted GAC removal and fresh GAC filling systems
- Chemical Dosing Packages

Project: 55, 000 M3/D INDUSTRIAL WASTEWATER TREATMENT PLANT - MARAFIQ JUBAIL (IWTP-8)
Reviewed process design, issued RFQs to equipment vendors and evaluation of vendors’ proposals during the tender stage. Worked as Sr. Process Engineer during the detailed engineering stage with the following responsibilities:
- Process design review and finalization of P&IDs
- Prepared specifications and control philosophy of tertiary & Granular Activated Carbon (GAC) Filtration Systems
- Prepared specifications of Chlorine gas injection system
- Engineering coordination of Secondary Dissolved Air Floatation Units

Project: 3 X 8, 400 M3/D BRACKISH WATER REVERSE OSMOSIS DESALINATION PROJECT - MARAFIQ YANBU
Worked as Sr. Process and Proposal Engineer during the tender preparation of this project which was awarded to SETE. My job responsibilities included the following:
- Process Design, engineering and cost estimation
- Preparation of P&IDs and PFD
- Equipment sizing, specifications and selection
- Preparation of Technical Submittal

Project: 35, 000 M3/D BOOT SEAWATER REVERSE OSMOSIS DESALINATION PROJECT - KING ABDUL AZIZ INT’L AIRPORT, JEDDAH
Participated in this project from the tender submission stage up to the completion of EPC work. Job responsibilities included the following:
- Engineering coordination of Reverse Osmosis system, Electrochlorination system, chlorine gas injection system, CO2 Production Plant and chemical dosing packages
- Prepared an evaluation report on the condition of the existing Lime and CO2 storage facilities
- Designing of Limewater Injection System for water Potabilization, e.g., lime powder storage and pneumatic transfer system, lime water preparation and dosing equipment etc.
- Technical evaluation of Environmental Impact Assessment Study Report
- Developed method statement on the Tie-in points between the existing and new facilities
- Technical and commercial evaluation of vendors’ proposals
- Preparation of PFDs, P&IDs and Process Calculations
- Preparation of equipment specifications, data sheets and technical submittals
- Coordination of engineering review meetings between various disciplines

Process/Project Engineer at REZA ENVIRONMENTAL INDUSTRIES
  • Saudi Arabia - Jeddah
  • October 2001 to March 2004

780 M3/DAY EXTENDED AERATION STP PROJECT, ARAMCO HARADH BACHELOR CAMP - SAUDI ARAMCO

Worked as Process / project Engineer with the following Job responsibilities:

- Preparation of P&IDs and Process Flow Diagrams
- Preparation of Equipment Specifications and Technical Submittals
- Line sizing and head loss calculations
- Oxygen requirement and aeration calculations
- Chemical dosing calculations
- Engineering coordination with vendors and discipline engineers

The other Major Projects completed with REZA include:

- 28, 000 m3/d Municipal Wastewater Treatment Plant at Riyadh Industrial City
- 2, 000 m3/d Brackish Water RO plant for Hada Truck filling plant near Jeddah
- 1, 500 m3/d Brackish Water RO plant for Prince Sultan Humanitarian City Riyadh
- 550 m3/d Sewage Treatment Plant for Jeddah Hilton Hotel
- 280 m3/d Extended Aeration STP for Sunshine Beach Complex, Jeddah

Process / Proposal / Project Engineer at DESCON ENGINEERING LIMITED
  • Pakistan - Lahore
  • December 1994 to June 2000

Worked in WETS (Water & Effluents Treatment Services) Dept. as Process/Proposals/Project Engineer for 5 & 1/2 years. Job responsibilities included the designing, cost estimation and project engineering of Water Treatment Plants including Softening, Demineralization, Filtration & Reverse Osmosis Plants. Participated in ISO9001 certification process. The major projects completed with DESCON include:

- 960 m3/d Water Demineralization Plant to KESC/Bin Qasim Unit # 6, Karachi in liaison with Marubeni Corp., BHKK (Japan) & Unidro (Italy)
- 3 x 1, 800 m3/d Mixed Bed Polishers for National Refinery Limited, Karachi
- 1920 m3/d Water Softening Plant & 360 m3/d Water Demineralization Plant for ICI Polyester Ltd., Sheikhupura
- 1, 200 m3/d Water Softening Plant for Sapphire Fibers Ltd., Lahore. The plant was designed on Amberpack System, first ever of its kind in Pakistan
- 840 m3/d Reverse Osmosis Plant for Crescent Textile Mills Ltd., Faisalabad
- 4, 800 m3/d Canal Water Clarifier Filtration system for Crescent Textile Mills Ltd., Faisalabad
- 2 x 900 m3/d Water Softening Plants for Liberty Mills Ltd., Karachi

Education

Bachelor's degree, Chemical Engineering
  • at University of Engineering and Technology Lahore
  • July 1993

Specialties & Skills

Project Management
Waste Water Treatment
Water Treatment
Project Engineering
Process Engineering

Languages

English
Expert
Urdu
Expert
Punjabi
Expert

Training and Certifications

Management of Industrial Waste Waters in Pakistan (Training)
Training Institute:
National University of Sciences and Technology
Date Attended:
September 1997
Self-monitoring Assessment & Pollution Charge (Training)
Training Institute:
WWF
Date Attended:
January 2000
Selection of Pumps & Aerators (Training)
Training Institute:
ABS Pumps
Date Attended:
August 2002
Water Treatment Technology (Training)
Training Institute:
NFC Institute of Engineering & Technological Training in Lahore
Date Attended:
December 1995
RO, NF and Membrane Filtration Technology for Potable Applications (Training)
Training Institute:
by Dr. Mark Wilf, organized by European Desalination Society & Bushnak Academy
Date Attended:
November 2008