Satish Gaikwad, Marine and Bridge Engineer

Satish Gaikwad

Marine and Bridge Engineer

Egis

البلد
الهند - مومباي
التعليم
بكالوريوس, Engg & Technology
الخبرات
11 years, 7 أشهر

مشاركة سيرتي الذاتية

حظر المستخدم


الخبرة العملية

مجموع سنوات الخبرة :11 years, 7 أشهر

Marine and Bridge Engineer في Egis
  • الهند - مومباي
  • أشغل هذه الوظيفة منذ ديسمبر 2018

Currently, I am working for a prestigious- Mumbai Coastal Road Project (Project cost 2100 INR Crores) -wherein I am involved in day-to day site supervision/ inspection of construction works that includes bridges, flyover, Viaduct, Precast PSC work, Vehicular Underpass, Pedestrian underpass, Box structure,

Marine Mono-pile (First time in India) both onshore and offshore Utility services - Carriage way ducts, storm water drain etc.

land reclamation of App 29 Hectare (Filling from -1.5 to + 8.0 MSL) around 6.5m height using suitable fill material. The functionality of this works is to provide a stable base /foundation of infrastructures works.

Construction of rubble mound seawall which is being built along the coastline for a span of 2.9 km using boulder of size varying from 1 kgs to 2-4 t armor stones with concrete

crown wall of 2.1 km to prevent over wave topping and Temporary jetty

Quantity Surveyer في Jkumar Infraprojects Ltd.
  • الهند - مومباي
  • نوفمبر 2016 إلى ديسمبر 2018

Project details:
JNPT Project
Project Cost: - 1670 Cr (Indian Rupees)
Package No. 3
Package No. 1 (Karal Interchange)

Including structure as Pre-tensioning Girder, Post Tension Girder, Major Bridge, VUP, PUP, Elevated Corridor etc.

Nature & Scope of Responsibility

1. Developed healthy relationship with clients, colleagues and seniors.
2. Completed Construction activities with proper safety and Quality
3. Control the wastage of steel by preparing BBS in such a way that cut pieces of reinforcement can be used.
4. Prepare the requirement of Manpower, Machineries and material.
5. Prepare the BBS for FLY/MNB/BOX structure.
6. Prepare the sub-contractor bill.
7. Co-ordination with Superiors for smooth construction.
8. Co-ordination with Client and Lab team for inspection.
9. Timely preparation of all supporting documents.

Senior Engineer في larsen and Toubro Ltd
  • الهند - لكنو
  • يوليو 2015 إلى نوفمبر 2016

Project details:
1) Agra - Lucknow Expressway

Project Cost: - 1650 Cr (Indian Rupees)
As see work 10 km in-between including structure as Major Bridge, Minor Bridge, Pedestrian Underpass (PUP), VUP, PSC Girder, Box Culverts, and Hume Pipe Culverts.
Flyover Construction Above name of Sai River using Friction Pilling method.

Nature & Scope of Responsibility

1. To execute the construction activities of MJB (Flyover), MNB, VUP, PUP, BC, HPC (Ch 256+600 to Ch-266+750).
2. Preparation of sub-contractor bills, reconciliation of material.
3. Co-ordination with Client and Lab team for inspection.
4. Timely preparation of all supporting documents such as RFI, Testing Documents, Bill Copy.
5. Optimum utilization of resources for construction.

Achievements

1. Completed 125 Working pile, @ 261+550 Major Bridge.
2. Completed 05 no’s PUP including Wing Wall at Ch.256+811 to 260+770 in between. This are PUP completed within 6 months.
3. 1 VUP @ Ch. 257+946.
4. 1 MNB @ Ch. 259+496.
5. Completed 06 no’s of HPC within specified time.
6. Completed retaining wall, median/U wall of BC From Ch.258+034 & 261+117.
7. Above all completed structure completed within 12 months only.
8. One of the best Achievements as above all structure there have no any major Accident occurs on Site.

Junior Engineer في J.KUMAR INFRAPROJECTS LTD
  • الهند - مومباي
  • أكتوبر 2012 إلى يونيو 2015

Project details:

1) Kharghar Metro (Navi Mumbai Metro)

2) Sion-Panvel Toll ways Private Limited (STPTL) - Project Cost 600 Cr .(Indian Rupees)

Flyover construction Mankhurd known as CMLR Flyover. - 1 km
General Civil Work PUP, VUP, FOB, Culverts, Drain and Road Works.

Roles and Responsibilities -
 Execution works.
 Calculating the estimate of working day work such as, steel work, concreting work, form work, excavation, filling Murom.
 BBS for structural detailing work.
 Preparing structural work.
 Pilling Work, Pile Cap, Pier, Pier Cap, Girder, Pedestal, Bearing Plate, Slab work, ACB.
 Responsible for verifying laboratory test Slump Test for construction materials.
 Minor Bride Work, Retaining Wall, Road widening Work, DLC, PQC.
 Client Handling, DPR (Daily Progress Report), Utility work.
 Co ordinate with Contractor schedule work & Contractor Billing work.

الخلفية التعليمية

بكالوريوس, Engg & Technology
  • في Visvesvaraya Technological University
  • يونيو 2012
دبلوم, Diploma in Civil Engineering
  • في M.H.Saboo siddik Polytechnic & Engineering
  • مايو 2009
الثانوية العامة أو ما يعادلها, SSC
  • في Board of Technical Education
  • يونيو 2005

Specialties & Skills

MS Project
Staad Pro 2007
AUTO CAD 2022

اللغات

الهندية
اللغة الأم
الانجليزية
متمرّس

التدريب و الشهادات

Marine Training (تدريب)
معهد التدريب:
G-Corporation
تاريخ الدورة:
December 2022
Staad Pro (تدريب)
معهد التدريب:
Cadd Centre
تاريخ الدورة:
April 2014
Auto Cadd (الشهادة)
تاريخ الدورة:
March 2014

الهوايات

  • Travelling