Project Manager
Alfanar Group
Total years of experience :18 years, 2 Months
Group Overview:
Alfanar Construction Company is a pioneer EPC contractor for
Transmission & Distribution and one of the leading company in
Power Transmission & Distribution for executing S/S 110 KV, 132
KV, 380 KV, Transmission Lines & SCADA Projects, With a long
record of successfully executed projects.
Project : Construction of New Aranah Water Treatment Plant
110/13.8kv S/S Makkah
Client : Saudi Electricity Co. (SEC - WOA
Engr. Shafqat Zia
Project : Construction of New Petro Rabigh 380/110KV BSP
Client : Saudi Electricity Co. (SEC - WOA)
Project : Construction of New 132/13.8 KV S/S at Alfanar
Descriptions
• Coordinate between the project design engineers and client
engineers.
• Coordinate between the main project offices & inform the site
for any client request approved by Project Manager.
• Prepare the bill of quantities according to the contract
conditions.
• Prepare the project requirements (materials, manpower, and
equipment) and submit technical advice regarding that after
consulting with the Project Manager and Site Manager.
• Attend the meeting with all parties related to his
responsibility.
• Review of Tender, Technical documents and evaluation of
quotations from vendors as per scope of work and
specifications.
• Preparation for the design submittals to client and to follow
up to get the final approval.
• Review and finalization of BOQ’s for material as per client’s
standards and project technical specifications.
• Coordinate with purchase dept, QA/QC, Planning and Tender
dept for a smooth execution of project.
Experience of indoor and outdoor substation (500KV,
200KV, 132KV & 66KV)
• Installation, Erection and commissioning.
• Testing of supervision of protective schemes.
• Construction /supervision of 11KV lines from grid station to
onward.
• Planned and maintained distribution network properly to
improve availability and reliability of the system through hard
work and dedication
• Reducing losses both technical and non technical
• Leading role for energy loss reduction program in my circle
• Maintenance of overall networks and related equipments
• Monitor the working schedule of whole staff and their
performance on daily basis.
• Analyze and calculate the losses weekly and monthly.
• Assist all team members / staff to improve their working
• Take precautions and apply safety rules during their work.
• Monitored construction Erection and execution of new 11kV
feeders.
• Monitoring new connection and new village electrification
works of LESCO region
• Attending preventive / breakdown / overhauling maintenance
and condition monitoring of distribution substation equipments
• Protection of 500/220/132/11kV grid station and T/line.
Membership : Pakistan Engg Council,Saudi Engg Council