Senior Cost Control Engineer
TYPSA Engineering Services Company
Total years of experience :18 years, 7 Months
Responsible for the weekly & monthly progress monitoring report of the site works. Evaluating contractor’s progress interim payment application . Providing detailed review on the contractor’s variation and claims applications. Assisting in the contractor’s contract review claims. Reviewing of the project work programmes. Reviewing of project forecast cash flow.
Provided budget comparison and analysis for the daily material, equipment, manpower, and other resources requisition by the construction team. Prepared monthly cost reports and provides earned value analysis to the project management. Monitored & updated actual cost of materials, equipment, manpower, sub-contracts, and indirect costs on a regular basis. Updated & revised budget quarterly.Calculated cost estimates and breakdowns for the new variation orders.
Performs computation and detailing of project budget
Makes updates & revisions of budget with regard to project progression
Provides cost information and recommendations to project management
Monitors & updates actual cost of materials, equipment, manpower, sub-contracts, and indirect costs regularly
Provides cost analysis & project progress status
Monitors and provides summary of monthly cost reports
Collects, compiles and monitors progress report from site
Prepared claim applications for the progress works on site
Submitted billing progress to project consultant
Prepared computations for variation orders and site instructions
Checked & reviewed work statement completed by subcontractors
Performed quantity estimates for the approved shop drawings, variation order claims, etc.
Performed computation & detailing of project budget
Made revision on budget regards to project progression
Monitored & updated actual cost of materials, equipment, manpower, sub-contracts, and indirect costs regularly
Provided cost analysis & project progress status
Monitored and provided detailed summary of monthly cost reports
Provided cost information and recommendations
Collected, compiled and monitored progress report from site
Computed and prepared budget for new site instructions and variation orders from consultants and clients
Prepared documents for subcontractor projects
In charged of planning, designing, preparation and construction of several water facilities, buildings, and pipelines along the City of Tagaytay
Supervised and ensured timely completion of project construction and are within allocated cost/ budget
Ensured safety standards were met through performance monitoring and Site Safety Measurement
Requested and monitored project materials on site & resolved all unexpected technical issues and problems encountered
Prepared daily and monthly accomplishment reports
Led team in project designs (Office Building, Concrete & Steel Water Tanks, Pipe Lines and Several Water Facilities)
Ensured accurate estimation on quantity of materials, labors and project cost
Designed and planned projects with the aid of various computer programs
Allocated roles, responsibilities and production activities within the group
In charged of preparing, directing, and supervising construction of several residential buildings
Ensured tasks were completed according to plan & specifications,
Directed & delegated tasks in accordance to target schedule
Re-checked plans/ drawings for quantity accuracy and ensured
materials were according to specifications
Provided cost-effective solutions and proposals for projects
Monitored material quantity and labor cost were within estimated budget & ensured timely completion of projects
Facilitated regular inspection on safety compliance of workers
Prepared accomplishment reports and post project documentations