shoebullah khan, Senior Instrumentation Engineer

shoebullah khan

Senior Instrumentation Engineer

AECOM

البلد
الإمارات العربية المتحدة - دبي
التعليم
بكالوريوس, Electrical
الخبرات
18 years, 7 أشهر

مشاركة سيرتي الذاتية

حظر المستخدم


الخبرة العملية

مجموع سنوات الخبرة :18 years, 7 أشهر

Senior Instrumentation Engineer في AECOM
  • الإمارات العربية المتحدة - دبي
  • أغسطس 2017 إلى أكتوبر 2019

Review Prequalification, Material and Technical Submittal, drawings, clarifying request for information for Plant DCS System and Integrated SCADA System, Electrical and Vendor Packages;

The brief scope Plant DCS comprising of Supply, assemble, install, connect, program, configure, test and commission of complete Distributed Control System (DCS) including wiring and cabling, project managment, configuration, FAT, SAT and documentation complete with, but not necessarily be limited to the following.

Engineer في Archirodon Construction (overseas) Co. Ltd
  • الإمارات العربية المتحدة
  • يونيو 2013 إلى أغسطس 2017

The brief detail of Electrical and Vendor Packages as written below;

•MV & LV Switchgear, 4Nos 11kV Substation including 4Nos 11kV and 2Nos 6.6kV Switchgears, 4Nos, 3MVA, 11kV Generators, 4Nos, 11kV, 20 ohm Neutral Grounding Resistors (NGR), 10Nos 11kV Ring Mains Units, Low Voltage Switchgears and MCC, Capacitor Banks, Harmonic Filters, ONAN Transformers (25Nos)
•MV & LV Power Cables, Control Cables, Earthing system for Substation and whole plant and Lightning Protection System
•Water Boilers (2 Nos, 1000kW each including Ring Mains, Circulating and Make up Pumps, Expansion tank (1m3), Treated Water Tank (1m3) and Diesel Day Tank (1m3)
•Central DCS System for plant automation, Plant Instruments
•Vendor packages Sodium Hypochlorite Dosing System, Equipment: Rotary Drum Thickener, Gravity belt Thickener, Dryer Unit, Centrifuge, Bagging Plant, Blowers, Compressors, Mixer, Aerators, Gas Boosters, Odour Control Units.

Electrical Engineer في Dubai Municipality
  • الإمارات العربية المتحدة
  • يونيو 2008 إلى أغسطس 2011

Preparation Detail Engineering and Shop Drawings and Execution for Power Distribution System (e.g. Single Line Diagram, Load Schedule, Cable Route Plan etc.), Lighting, Small Power, Earthing and Lightning Protection System
•Installation supervision, Testing & Commissioning for MV & LV Switchgear, 4Nos 11kV Substation including 4Nos 11kV and 2Nos 6.6kV Switchgears, 4Nos, 3MVA, 11kV Generators, 4Nos, 11kV, 20ohm Neutral Grounding Resistors (NGR), 10Nos 11kV Ring Mains Units, Low Voltage Switchgears and MCC, Capacitor Banks, Harmonic Filters, ONAN Transformers (25Nos)
•Design, Installation and Testing and Commissioning for MV & LV Power Cables, Control Cables, Earthing system for Substation and whole plant and Lightning Protection System
•Installation, Testing & Commissioning and As built Drawings for Building Management System (BMS) including three Chillers (132 ton cooling capacity each), FAHU (4), AHU (5), FCU units communicating and Non Communicating type, Primary (4) and Secondary Pumps (3)
•Preparation Shop Drawings, Installation, Testing & Commissioning for Chlorination System including chlorinators (6) capacity 40kg/hr each, Dosing Control Units, Chlorine Drums (14) capacity 930kg Cl2 each
•Preparation Shop Drawings, Installation Testing & Commissioning for Water Boilers (2 Nos, 1000kW each including Ring Mains, Circulating and Make up Pumps, Expansion tank (1m3), Treated Water Tank (1m3) and Diesel Day Tank (1m3)
•Preparation and Updating Control and Instruments cable list and updating P&ID
•Identification of location of instruments in the plant
•Hard wiring for Control Signals for Motor, compressors, and Package Equipment.
Rectifying defects of Electrical Equipment during operation of Plant

Estimation Engineer في Archirodon Construction (overseas) Co. Ltd
  • فبراير 2005 إلى يونيو 2008

Design and estimation for following systems; MV and LV power distribution system, Indoor & outdoor Lighting Systems, Earthing and Lightning protection system, Impressed and sacrificial cathodic protection system, Fire alarm system, telephone system, paging and public address systems, CCTV System
Project: Flue Gas Desulphurization (FGD), Jeddah-4 Plant
Owner: SWCC, KSA

Electrical Design Engineer
  • يوليو 2004 إلى يناير 2005

Preparation of Single Line Diagrams
•Short circuit current analysis, Load Flow Analysis and Relays Coordination by CYME software
•Installation, Testing & Commissioning for MV & LV Switchgears, Installations 132kV/11kV Transformers, MV Cable installation and its terminations to Transformers & MV Switchgear
Project: Multi Product Berth, Mesaieed, Qatar
Owner: QP, Qatar

Electrical Design Engineer في ARCHIRODON
  • الإمارات العربية المتحدة - دبي
  • سبتمبر 2002 إلى يونيو 2004

Design;
•Short Circuit Calculations, Load Flow Analysis, Motor Starting Analysis, Relays Setting and Coordination by CYME Software
•External Area Lighting Design Calculations
•Power Cables Sizing for different loads
•Installation of Single Mode Fiber optic cables 13km length from Tankfarm area to Jetty Control Room
•Installation of Emergency Shutdown System for process Pipe lines, Metering and Proving System and its instruments and cables, Motor operated valves, and jetty instrumentation.
•Upgrading instrumentation for tankfarm area
•Installation and Pre commissioning for;
•6kV Switchgear (

  • ديسمبر 2001 إلى أغسطس 2002

Design;
LV Switchgear and Distribution Boards according to the given specifications and loads
•Sizing of LV cables for different loads of the Plant, Preparation of Load List, Cable List, Tagging of Equipment and Cables

Project في Abu Dhabi Fund for Developmen
  • مصر
  • يونيو 2001 إلى نوفمبر 2001

Design;
•MV Power Cables for 11kV Substation Switchgear Incomers, 2.5MW, 11kV MV Pumps & 500kVA, 11/0.380 kV Transformers
•Cable Routing and Sizing of Trays for MV Cables
•MV Switchgear, LV Switchgear and LV distribution Boards according to the given specifications and loads
•LV Power cables, trenches and conduits for Pump Station LV loads
•Lightning and Grounding Protection of Pump House building and External Area
•Fire Alarm System for Pump House
•Internal lighting and External lighting fixtures for specified illumination level of the Pump house
•Telephone System and Telephone Cables
•Material Submittals;
•Material submission of Electrical and Mechanical Systems for Approval to Client
•Procurement;
Preparation of Material Take off sheets and Technical Comparisons of following Systems
Lighting Poles, Fixtures, MV Cables, LV cables, Control cables, Telephone cables, LV Panel boards, disconnect switches, receptacles
Project: Shoaiba Steam Power Plant, Stage I, Phase 1

Electrical Engineer في Saudi Electricity
  • المملكة العربية السعودية
  • يوليو 1999 إلى مايو 2001

Design review, Installation, and Testing and Commissioning for;
Lighting poles and fixtures (internal and external), LV Power Cables, Low voltage transformers (oil filled and dry type), Fire alarm system complete with Fire Alarm Cables, LV Panel boards, Lightning and grounding systems
Implementation of the designed drawings on the site
KKS Code numbering to the switchgear, LV Distribution Systems (e.g. Transformers, Panel Boards, Circuit Breakers and Power Cables)
•QA/QC;
Coordination with Consultant Engineer for inspection of received electrical material on site and for erection completion of electrical works, to fulfill all internal QC inspection requirement before final QC check with Engineer, to prepare & maintain QC records
•Preparation of the As Built Drawings
•Documentation (for systems given below);
Receiving and maintaining records (hard copies) of ALSTOM Electromechanical documents (documents contain electromechanical works reports and drawings of 5×350MW Shoaiba Steam Power Plant)
•Testing and Commissioning;
Preparation of commissioning documents and Testing and Commissioning for Environmental monitoring systems, Marine unloading arms, Quick release mooring hooks, Berthing Aid System, Access Gangway and Jib Crane, Slop System, Oil spillage control equipment, Metering and proving system, Cathodic Protection System, Navigational aids system, Fire fighting and Fire Alarm System, Panel Boards, and HVAC System

الخلفية التعليمية

بكالوريوس, Electrical
  • في ALIGARH MUSLIM UNIVERSITY
  • أبريل 1999

Electrical Engineering

الثانوية العامة أو ما يعادلها, Science, Maths, Arts
  • في ALIGARH MUSLIM UNIVERSITY
  • يناير 1989

Specialties & Skills

Cost Estimating
Plant Commissioning
Electrical Installation
Electrical Design
Instrumentation
DOCUMENTATION
LIGHTING
MICROSOFT WORKS
PROCUREMENT
TELEPHONE SKILLS
Electrical Engineering

اللغات

الانجليزية
متمرّس

الهوايات

  • STUDY & CHESS