Project Management Senior Construction Specialist
Saudi Aramco
Total years of experience :24 years, 11 Months
Reviewing work packages, method statements and risk assessments. Job safety analysis, Review Civil Engineering and Construction contractors standards apply to Saudi Aramco standards. I also project manage Civil Engineering and Construction.Constant reviews of work schedule to implement change where applicable.Reporting to the senior project manager.
My roles and responsibilities in this position were to carry out pre-quality checks prior to concreting and to ensure client approval. Also to check quality of finished works. I was also responsible for health and safety and checking work permits and risk assessments.
Northfield Construction Limited: Drax Biomas
Site supervisor April 2013 - June2013
Duties include: Daily safety briefings, progress meetings, site diary, organising labour, plant and materials.Quality assurance, Organising work permits and checking and reviewing Permits and risk assessments.
Costain at Centrica gas terminal: Site manager/supervisor
June 2012 - April 2013
Duties include: Quality assurance, Organising labour, ordering materials, allocation sheets, site diary, progress meetings, Reviewing permits and risk assessment, Constant reviews of work schedules to implement change, permit acceptor. Reference available.
Stam Construction January 2011 - Apr 2012
Duties included: Site Supervision, Organising plant and labour, work permits excerpter, Quality assurance, Overseeing safety, bases, retaining walls and bund walls for water containment for Yorkshire water authority. References available.
Lingard Sub Contractor Aug 2010 - Dec 2010
Duties included: Designing form work for suspended soffits on existing bridge for main support beams.Organising plant labour and materials References available.
Moortown Construction: Site Supervisor Oct 2009 - June 2010
Duties included: Running small teams of Joiners, steel fixers, concreters and labourers to Sirius Academy.
Woodland construction: Joiner supervisor Jan 2008 Oct 2009
Duties included: Overall supervision of total renovation to flood damaged properties in Humberside.
Wrights, Hull: Civil Engineering Supervisor Apr 2008 - Aug 2008
Duties included: Working on a recycling plant, radius retaining walls, decking, bases, bolt clusters, edge protectors, and managing staff.
Will Cam, BP: Civil Engineering Supervisor Feb 2008 - Apr 2008
Duties included: Construction of bund walls for chemical containment.
Mc Alpines: Civil Engineering Supervisor Nov 2006 - Jan 2008
Duties included: Supervising a small team of men working on the Melton bypass, constructing bases for steel foot bridge with access ramps and up stands, header walls to ditches, remaining wing walls to abutments on bridge and plinths for stanchions. Grout boxes, culverts and any other routine duties.
Sword construction: Civil Engineering Supervisor Apr 2001 - Nov 2006
Duties included: A major project extending the smelting works in Scunthorpe, comprising shuttering, decking and securing retaining walls with voids on a excavation approximately 40 metres deep.
Easington: Charge hand/Supervisor
Duties included: Construction of the gas terminal including the construction of a blast proof gate house and elliptical radius frontage (shape of ships bow), shuttered walls, with voids for blast proof windows, plinths for carrying pipe work and cable ducts.
A1 Extension: Civil Engineering Supervisor
Duties included: Responsible for working on the Dishforth to Darlington extension on the A1, one of the only contractors to complete own section under set time schedule (26 days early)
Channel Tunnel: Civil Engineering Supervisor Duties included: Working on the Kings cross Channel Tunnel Railway, main contractors Keir/Nuttalls completing the project under budget and within the set time limit.
Dagenham Tunnel: Civil Engineering Supervisor Duties included: Working on Leighton Buzzard sub station.
Tilbury Douglass: Civil Engineering Supervisor BP 1999 -2001