Project Manager
DIU
Total des années d'expérience :18 years, 8 Mois
The Scheme aims to pumping water to Agricultural areas via pump station.
The Pump Stations consists of: The Main Pump Station and Two Booster Pump Stations.
Each of the Main station and the Two Booster Pump Stations with installed capacity of six pumps of rating 4.9 m3/s and each driven by a 1290 kW diesel engine. The engines are horizontally mounted and coupled to the pumps by step down gearbox.
Also at each station a generating station with a capacity of four generators and its accessories.
In addition to induction motors and submersible pumps with different sizes and its control panels.
Also there are accessories devices for monitoring and measuring the different parameters such as pressure, speed, temperature...etc
My Job base on Follow-up of operations and maintenance at the three stations and troubleshoots on electrical systems.
Reviews and check the daily Pump Station operation shift logbook, operators log sheets and the maintenance logbook.
Follow-up to provide the necessary spare parts, and the preparation of daily technical reports, and budgeting for spare parts or any new construction.
Electrical Engineer
Bachelor Degree in Electrical Engineering- Power System And Electrical machines