Warehouse Lead – Sabiya CCGT-3 Project
Alghanim international
Total years of experience :19 years, 2 Months
Leading seamless warehouse operations for Sabiya CCGT-3Project, worth USD 439 million Combined Cycle Power Project Effectively managing inventory for the project with a diverse range of components, including 2 Gas Turbines (Siemens SGT5-4000F), 2 Gas Turbine Generators (Siemens SGen5-2000H), 1 Steam Turbine Generator (Siemens SST5-5000), and associated equipment. Implementing strategic planning to ensure optimal stock levels while preventing shortages.
Led smooth materials and logistics operations for Az-Zour South Combined Cycle Conversion Project, a USD 750 Million EPC Contract for the Ministry of Electricity and Water in Kuwait.
Led Alghanim’s most significant project that holds paramount importance in company success; successful and timely functionality enhanced reputation as an industry leader.
Directed the team to achieve the fastest production commencement in just 8 months, setting a regional benchmark for project efficiency and delivery.
Emergency Power Plant Shuwaikh LM6000 Gas Turbine; played key role in the record-breaking completion of the Emergency Power Plant Shuwaikh (300 MW) in Kuwait, achieving 300 MW on the national grid within an exceptional 6 months from contract signature. Received commendation from a Senior Executive at GE for overseeing the fastest project of its size ever built by GE, demonstrating meticulous material management, adherence to international standards, and adept problem-solving in day-to-day operations
To procure, store, and issue supplies in a supply operation; process and maintain inventory records; modify and implement inventory control and disposal procedures; perform related work.