Tengku Fredi Maulana, Deputy Construction Manager

Tengku Fredi Maulana

Deputy Construction Manager

Mas

Location
Indonesia
Experience
22 years, 7 Months

Share My Profile

Block User


Work Experience

Total years of experience :22 years, 7 Months

Deputy Construction Manager at Mas
  • My current job since November 2014

.(2017)
PT.Energy Sejahtera

Project Coordinator
  • January 2003 to October 2004

PT.Truba jaya engineering Resident contractor for PT. Chevron Indonesia, Duri,
Riau, providing support on oil Drilling and Production activity: Recruiting, Coordinating,
Organizing, Scheduling/Shifting of manpower and equipment, Solving technical and
managerial problem for Minas and Duri area.
Achievement : good progress and high prodictivity.

Project Coordinator
  • December 2001 to December 2002

Tripura engineers and constructors, for Caltex Facifix Duri steam Flood area 11
Project Duri, Riau. Installation pipe line from Pumping area to AWT Faclity.
Achievement : Project was completed on schedule

Engineer/Administrator
  • July 2000 to November 2001

Project: PT. Tripatra Engineers and Constructors. For Caltex Pacifix Indonesia, Duri
steam Flood, Area 11 Project, Duri, Riau Management contract and providing
contracting strategy. Review and analysis of term and condition, negotiation, technical
bid analysis, propose and negotiation claim, contract correspondence and
documentation. Prepare subcontract agreement, issue award and maintain good relation
among Subcontractor and Client. Coordinating and monitoring progress. Review of
contract document and recommend any change of design /modification for increase
efficiency and effectiveness. Monitoring progress and prepare project status report.
Liaison with client and construction team for any deviation.
Achievement : Project was proceded conform with contractual requirement and
specification.

Project Coordinator
  • December 1999 to June 2000

PT.TrubaJayaEngineering, For Cilacap Refinery maitenence project.
Project: Pertamina Cilacap Refinary maintenence Project
Managing repairing, refurbish refinery equipment, heater pipe piping and valve.
Realigment coupling motor, turbin, Pump, etc. Replacement bearing, repairing Vessel
katalisator, cleaning and chemical cleaning, reapairing/replacing structure steel and
support etc.
Achievement : Project was completed on schedule.

Site manager at SMI
  • United States
  • January 1997 to January 1999

PT.Truba Jaya engineering for

Site manager
  • January 1996 to January 1997

Truba jurong engineering for Sulfindo/Kobe Steel co ltd.
Project : Sulfindo, Chloor Alkali Plant project included demolished existing plant,
installation whole works : civil, equipment and piping, electrical and micelenious. On
Bojonegara, Cilegon, Banten.
Achievement : Project was succesfully completed on schedule, no fatal accident, within
budget and conform with contractual requirement and specification.

Site Manager at UIC
  • United Arab Emirates
  • January 1994 to January 1996

PT.Truba jurong engineering for PT.

Administrator/Engineer
  • January 1992 to January 1994

PT.Truba Jurong Engineering for PT.Tripatra and Exxon/Mobil oil Aceh Indonesia.
Project :Arun Booster compressor Project Aceh, Equipment Installation and piping
works,
Achievement :Project was successfull completed on schedule.

Administrator/Engineer
  • January 1991 to January 1992

PT.Truba Jurong Engineering for PT.IKPT/KELLOG inc/Petro Kimia Gersik, East Java
Project :.Ammonia and Urea Fertilizer Plant Project, PT.Petro Kimia Gersik, Instalation of
whole piping work included pipe rack and insulation.
Pproviding contracting strategy, Management contract, Contract review and analysis
of term and condition, negotiation, technical bid analysis, propose and negotiation
claim, contract correspondence and documentation. Prepare subcontract agreement,
Monitoring progress and prepare project status report. Liaison with client and
construction team for any deviation of works. Set-up Subcontractor progress
measurement system and control progress of work.
Achievement :Project was Successful completed on schedule and smothly

Specialties & Skills

BUDGETING
CUSTOMER RELATIONS
DOCUMENTATION
MANAGEMENT
NEGOTIATION
OIL PAINTING
PROGRESS
REQUIREMENTS
SPECIFICATION
STRATEGIC

Languages

Indonesian
Expert