Conduct PQR and arrange WPS for project specific. Preparation of Project Quality Plan and Inspection plan as per project specification. Conduct site Audits.
Preparation of QIPs, MS for Static Equipment and Piping.
Monitoring all
Conducting Internal Audits of different departments for DIMS Compliance
Follow Up of CARs/PARs and maintaining a record on standard formats.
Preparation of PQPs and QIPs for different projects at bid stage.
Extending cooperation to proposal departments regarding technical queries during proposal making
Resolving head office based issues of different project site’s QAQC personnel.
Participating actively in social activities held at head office.
Conducting Inspections of different assets for multiple project sites.
OGDCL Dakhni SRU Project:
Incoming Material Inspection.
Fabrication and welding inspection of piping.
Fabrication and welding inspection of steel structure.
NDT Coordination.
Hydro testing of piping spools.
Sandblasting and Painting inspection.
AWARENESS OF CODES AND STANDARDS:
Familiar with the following International Codes & Standards:
ASME Sec II, part A, Ferrous Material Specifications.
ASME Sec II, part C, Specifications for Welding Rods, Electrodes and Filler Metals.
ASME Sec V, Non Destructive Examination
ASME Sec VIII, Division 1, Rules for Construction of Pressure Vessels.
ASME sec IX, Qualification Standard for Welding and Brazing Procedures, welders, Brazers and Welding and Brazing Operators.
ASME B SERIES CODES AND STANDARDS
ASME B 31.1 Power Piping
ASME B 31.3 Process Piping
ASME B 31.8 Gas Transmission & Distribution
ASME B16.5 Pipe Flanges and Flanged Fittings
ASME B16.9 Wrought Steel Pipe fittings
ASME B16.47 Pipe Flanges and Flanged Fittings
API CODES AND STANDARDS
API 510 Pressure Vessel Inspection
API 577 Welding Inspection & Metallurgy.
API 570 Above ground piping inspection.
API 650 Rules for Construction of Above ground Storage Tanks.
API 653 Above ground Storage Tanks Inspection
PPL Gambat LPG plant.
PPL Adhi Plant-III
MOL EPF
Wind Energy (Metro, Yunus, Gul Ahmad)
SAP Project In Descon:
Worked as a Power User in business blueprint & realization phase.
Fully involved with the SAP team in requirement gathering and mapping of Quality Processes with SAP system. (QM Module)
Have complete hands-on in SAP system making Master Data and Transactional Data also.
Preparation of QIP as per client requirements
Coordinate with client & my execution team about work front
Managing and assigning responsibilities to inspectors in different areas.
Inspection of Critical piping as per ASME B 31.3.
To conduct WQT as per ASME Sec IX.
Preparing MS for static equipment’s & Piping according to our SOP.
Liaison with Client and
Professional Certification : SAP Power User QM Module (Descon Engineering Ltd.) (Abacus) API 577 (Cert. # 15053301 Welding Inspection and Metallurgy) AWS CWI (Cert.# 54290, Certified Welding Inspector of American Welding Society) ISO 14001:2004 Lead Auditor EMS ISO 9001:2008 Lead Auditor QMS NDT Level II (RT, UT, DPT, MPI) (As per ASNT SNT TC-1)