Instrumentation Engineer
ٍ]SDN Saudi co. for Water and Energy
Total years of experience :10 years, 2 Months
Constructing underground wells up to 500 meters deep and installing the suitable pumps, outlet lines with Valves and instrumentation for measurements.
Performed electrical repair, periodic and preventive maintenance works in the water treatment plant.
Work in project installing new treatment plant 10, 000m3/day.
Install distribution transformers and its suitable RMU.
Designed and developed automated control systems and solutions.
Scheduled periodic and preventive maintenance plans.
Control systems development and modifications including Siemens PLC program.
Prepared spare parts purchase orders.
Improved system operability.
Raised technicians’ skills and knowledge.
Perform electrical repair, periodic and preventive maintenance works in the packaging system and
Water treatment plant.
Schedule periodic and preventive maintenance plans.* Control systems development and modifications including Siemens PLC program.
Prepare spare parts purchase orders.
mprove system operability.
Raise technicians’ skills and knowledge.
BADR EL_DIEN Petroleum Company(OBIYED Field).(8 days, From (15 /
هذا مجرد تدريب على عمليات الصيانه والسيفتى للمواقع وتعلمت فيها الصيانات للمحولات والمفاتيح
Grade of graduation : Very Good with honor degree. (80%) Graduation project : Excellent.