Civil Project Engineer
Saudi aramco
Total years of experience :8 years, 2 Months
Currently working as a Site Superintendent Engineer in Saudi Aramco (SMP) with the project management team from April 2016 at master gas system expansion-Ph2-Gas Compression.
Duties:
SUPERVISING & MONITORING ASSIGNED AREA OR SYSTEM, AND DEALING WITH ANY ISSUES IN THE ASSIGNED TASKS.
• DEALING WITH THE SITE PREPARATION, TEMPORARY FACILITIES, RIPRAP STONES, AND BATCH PLANT INSTALLATION.
• DEALING WITH THE CIVIL WORK AND FOUNDATIONS OF THE GAS COMPRESSORS.
• HANDLING THE STORM WATER DRAINAGE SYSTEM AND UNDERTAKING SAFETY REVIEW FOR PROTECTION OF OPEN DITCHES.
• LOOKING AFTER THE FLARE SYSTEM INCLUDING THE CIVIL, PIPING AND STRUCTURE WORK.
• FOLLOW UP WITH ANY DOCUMENTS & ACTIVITIES FOR WORK PERMITS AND TEMPORARY ACCESS ROADS TO THE WORK SITE AND COMMUNICATING WITH OTHER DEPARTMENTS INVOLVED.
• SUPERVISING AND MONITORING WORK SCHEDULE FOR THE ASSIGNED WORK AND ENSURING THAT ALL IS COMPLETED ON TIME AND EXPEDITE ANY DELAY ON THE ACTIVITY PROGRESS.
• WITNESSING THE SITE INSPECTIONS AND MAKING SURE THAT THE WORK IS COMPLYING WITH THE COMPANY STANDARDS.
• WITNESSING, MONITORING AND REVIEWING THE ROCK EXCAVATION QUANTITIES.
• RESPONSIBLE FOR ENSURING THE CONTRACTOR FULFILLS
HIS OBLIGATION FOR SAUDIZATION AS SET OUT IN CONTRACT.
• MAINTAINS SAFE AND CLEAN WORKING ENVIRONMENT BY LOGGING SAFETY OBSERVATIONS.
• REVIEWING THE DETAILED DESIGN DRAWINGS FOR CIVIL AND ARCHITECTURE.
• EVALUATING NEW ROAD BID.
• CHAMPION OF TWO PARTIAL MECHANICAL COMPLETION CERTIFICATE (PMCCS).