Site Engineer
OTV International
Total des années d'expérience :3 years, 9 Mois
(As Site Engineer: O&M / Warranty Period)
- October 2013 - October 2014
Take active role in resolving issues relating to Mechanical, Electrical or Civil defects by optimizing
action plan in order to minimize impact on commercial production.
Coordinate with Commissioning / Operation & Maintenance teams and identify root cause of issues
relating to Pumps, Valves, Compressors, Filter Vessels and Piping.
Propose rectification solution to Project Manager
Organize and Supervise Site Maintenance/Warranty Support team and effectively carry out
rectification works On-site
Coordinate with Vendor in case of defective equipment and ensure that satisfactory action is taken in
order to replace defective equipment or resolve the issue.
(As Piping Engineer)
- April 2011 - October 2013
Overlooking Installation of AG & UG Pipelines and carrying out Quality Inspections with QC
Engineers and Vendor Assistance Supervisors.
Maintaining records of installation work on a daily basis and keeping track of progress.
Resolving issues related to Pipe Installation in coordination with design team
Estimation and monitoring of material requirement and shortages by maintaining precise records of
BOQ for the Project. (SS 316L; SDX Stainless steel; GRP Piping components & Chemicals; HDPE;
PVDF; PVC-U; Double containment Piping)
Compilation and tracking of Purchase requests and Deliveries for various Piping materials.
Conducting QC checks on Pipe spools at Vendor’s Production Facility.
Conducting training sessions for workers in order to equip them with required knowledge and skill relating to Piping works On-Site.
(As Pilot Plant Operator)
- October 2011 - April 2011
Responsible for safe running and operation of Pilot plant for a period of 6 months, adhering to Pilot plant protocol for Start-up, Shutdown and regular operations.
Calibrating Instruments for conducting tests on various parameters denoting quality of raw and
product water
Maintaining detailed records of all important parameters associated with daily operation of Pilot Plant.
Estimation and Pre-determination of material requirement and shortage for installation of
underground ductile iron pipeline and fire-fighting systems.
Handling a team of foremen, fitters and helpers
Planning of installation activities and scheduling work in order to match other site activities and
Project Schedule.
Maintaining records of installation work on a daily basis and keeping track of progress.
Ensuring strict adherence to quality control standards and procedures
Drafting As-Built Drawings in accordance with variation on Site
Overseeing Hydrotests
Preparation of Hydrotest Packs
Certified with First Class Honors