Qatar petroleum في TADMUR CONTRACTING & TRADING EST
  • قطر
  • إلى مايو 2015
Construction Manager في TADMUR CONTRACTING & TRADING EST
  • قطر
  • إلى ديسمبر 2014

GC10106300 - Automation up gradation for JMDS .

•Scope includes build new control building, new security house installation and all related civil work ( external work and MEP )
•Procurement, installation and commissioning of new DSC system
•Field civil work trenching for almost 10 KM including sand bidding and backfilling and making of 29 Duct bank including asphalting for laying the instrument cable in and making and installation and water proofing and backfilling for around 600 nos of concrete foundation for JB and F&G detector support .
•My responsibility for a whole site with a strong plan, I’m responsible for part of a project and report to a more senior manager, who may be taking care of several projects at the same time.
•Before work starts, I get things ready by taking on staff, and preparing the site, carefully planning the work to be done and installing temporary offices for site staff.
•While work is taking place, I’m monitoring progress, oversee delivery of materials and carry out safety checks and sort out any problems which could hold up work as they arise. I’m also keeping in close contact with members of their site team at all times, and liaise with architects, engineers, surveyors and planners. I will also ensure that work complies with building regulations and health and safety legislation as well as other legal requirements.
•I’m also keeping the client updated regularly on progress. Finally, I’m also acts as the first point of contact for members of the public and sub-contractors.
•It is the responsibility of me to make sure that the deadline for completing work is met, and at least share some of the responsibility if someone on our site has an accident.
•Make sure that all the activities which done are inspected by our QAQC and client and to make sure that whole the team following the QAQC regulation.

في TADMUR CONTRACTING & TRADING EST
  • قطر
  • يونيو 2010 إلى ديسمبر 2011

GC08103400 - Replacement of Instrument Air Compressors K-1112 and K-1113 at Fahahil Stripping Plant in the Dukhan Fields.

•Engineering, Procurement, Installation and Commissioning of the Instrument Air compressor system, Upgrade at Fahahil stripping Plant in Dukhan
•Scope includes installation of new IA piping system and Modification of existing compressor control system
•Two (2) new instrument air compressor packages to replace the existing compressors K-1112 and K-1113 at FSP. Each new compressor package will consist of one air compressor, inlet filter/silencer and coolers. Both compressors will be housed in a fully enclosed ventilated shelter.
•Integrated common control system for all new and existing I. A. compressors at FSP.
•Integrated common control system for existing air dryer packages at FSP. The new control system shall be housed in fully enclosed IP-65 and air-conditioned vertically mounted panel.
•All electrical power supply equipment, cabling, fuse switch cassettes, MCC / switchboard modification for the new I.A. Compressors at the New Compressor shelter and at the existing essential services 415V switchboard Tag# 11-SB-0006-2 or main 415V switchboard tag# 11-0006-1 in substation-A (subject to adequacy calculations / checks by CONTRACTOR to select most suitable source of power for the new I.A Compressors).
•Distribution boards (2 Nos) IP-56, complete with 250A incomer, motor feeder 200A, I.A. compressor auxiliary supplies, electrical control panel supply and spare ways as per QP standards/ specifications.
•Secured UPS power supply for the proposed Integrated Common Control System.
•Earthing bonding of new equipment and structure and connect to existing plant earthing grid, including any new earthing pits rods to be drawn into the ground required to achieve minimum earthing resistance as per approved standards.

Construction Supervisor في TADMUR CONTRACTING & TRADING EST
  • قطر
  • أكتوبر 2009 إلى يونيو 2010

Replacement of the existing HVAC with in all Dukhan plants including all the related civil works .

Site Supervisor في TADMUR CONTRACTING & TRADING EST
  • قطر
  • أغسطس 2008 إلى أكتوبر 2009

This project involves Engineering, Procurement, Installation and Commissioning.
•Upgrade and Replacement of Existing 72 Nos. Street Lights with Light Poles 9 meter high, hinged type, hot tip galvanized, with flanged fixing base and extended luminaries, fixing arms and ex junction boxes.
•Installation of new 12 Nos. 3.3KV RMUs, installation of 3.3kV/415V transformer, installation of feeder pillars, installation of flood lighting fixtures, installation distribution panels with photocell and lighting control panels.
•Power cabling up to 3.3KV via trench of nearly 1500 mts, cable underground termination and jointing (LV & HV). Laying and termination of Earthing cables, etc.
Manage with technical support to the project team on coordinate with other divisions to complete the project successfully by giving tasks to the team leaders for every week and taking feedback about the work from site engineer.
Manage and implement the proper handling regarding the maintenance of the following light fixtures including control gears, fluorescent tubes, ballasts, igniters, MCB, etc.
Preparation of test procedures and field quality plan for the execution of electrical testing activities.
Reports and record discrepancies and corrective actions and other activities done during the shift.
Over all in charge in construction site with regards of field operation, manage all activities in accordance with the contract and physical standards.
In charge in concreting works, prepared daily pouring schedule, check and inspect delivered concrete ready mix as per specification requirements.
Prepare daily accomplishment report regarding concreting works of the project.
Raise requisition for quotations and purchase order’s of materials necessary for the project in co ordination with procurement department by proving required technical information and follow up the delivery of the material.
Attending the Progress meetings with clients.
Review of all design documentations and drawings & keep records of the submittals.
Prepare necessary documents, logs and records for all activities involved in the projects.

Maintenance Employee في ABDUL RAHMAN EL HALLAB
  • لبنان
  • يونيو 2006 إلى نوفمبر 2006

Maintain of the faulty cooler rooms, fridges and the HVAC.

في TADMUR CONTRACTING & TRADING EST
  • قطر
  • ديسمبر 2011 إلى

Call off project (Street light maintenance within dukhan township)
Maintenance in charge

Responsibilities:

•Preparing daily accomplishment report regarding activities of the project.

•Organize and supervise daily activities of the entire field operation.
•Familiarize all requirements of the plans and specifications for project implementation.
•Conduct periodic meeting with site personnel to assess site .
•Execution with technical support to the project team on coordinate with other divisions to complete the project successfully by giving tasks to the team leaders for every week and taking feedback about the work from the client engineer.
•Coordinates to client Engineers regarding the activities completed and ready for inspection.
•Applying for the permit to work, (Hot, Cold, Excavation….)

•Coordinating with QP job officer for the inspection and for any clarification or for modification as per site condition.

Installation and Maintenance Supervisor في ZOURAY ESTABLISHMENT
  • لبنان
  • ديسمبر 2006 إلى

Installed more than 140 air conditions and heating control units for new Buildings.
•Performed proper programming for electrical control units for cooler rooms and boilers.
•Performed maintenance for about 300 boilers for heaters.

Construction manager في TADMUR CONTRACTING & TRADING EST
  • قطر
  • يونيو 2015 إلى

Qatar petroleum (UMM bab )

Electrical Supervisor في TADMUR CONTRACTING & TRADING EST
  • قطر
  • يناير 2014 إلى

Supervises and implements electrical, works.
•Supervise all activities in accordance with the contract and physical standards.
•Preparing daily accomplishment report regarding activities of the project.
•Organize and supervise daily activities of the entire field operation.
•Familiarize all requirements of the plans and specifications for project implementation.
•Coordinates to Project Engineers regarding the area ready for concrete pouring such as Lighting Poles, Blinding Works, Roads & Building Works, Cable Trench and Compacting.
•Conduct periodic meeting with site personnel to assess site situation and update them Check evaluation of sub-contractors billing in coordination with quantity surveyor.
•Execution with technical support to the project team on coordinate with other divisions to complete the project successfully by giving tasks to the team leaders for every week and taking feedback about the work from site engineer.
•Implement the proper handling regarding the maintenance of the following light fixtures including control gears, fluorescent tubes, ballasts, igniters, MCB, etc.
•Installation of 11/3.3 KV, 2000 KVA, dry type transformers, 11/0.415 KV, 2500 KVA, transformer, 3.3 KV switch gear, 415 V MV panel.
•Installation of MCC’s, BMS panels, Chiller management system, VSD & SSS chiller starter panels of 3.3 KV.
•Installation of cooling tower fan motors, Chilled water pump, Condenser water pumps.
•Installation of cable trays, laying of 11 KV, 0.6 KV, 3.3 KV cables
•Termination of 11 KV cables to transformers, 3.3 KV cables to transformers, Laying of 0.6 KV cables up to 185 sq mm size, termination & jointing of LV cables.
•Laying of control wiring, (BMS & chilled water system).
•Support for testing of cables like DC high pressure test, egger test, continuity test with testing team

Construction manager في TADMUR CONTRACTING & TRADING EST
  • قطر
  • إلى

Closing all the civil punch list

Scope includes making of new foundation of POP up blocker, new sliding gate, new turn style gate new boom briers and traffic signage .
•My responsibility for a whole site with a strong plan, I’m responsible for part of a project and report to a more senior manager, who may be taking care of several projects at the same time.
•Before work starts, I get things ready by taking on staff, and preparing the site, carefully planning the work to be done and installing temporary offices for site staff.
•While work is taking place, I’m monitoring progress, oversee delivery of materials and carry out safety checks and sort out any problems which could hold up work as they arise. I’m also keeping in close contact with members of their site team at all times, and liaise with architects, engineers, surveyors and planners. I will also ensure that work complies with building regulations and health and safety legislation as well as other legal requirements.
•I’m also keeping the client updated regularly on progress. Finally, I’m also acts as the first point of contact for members of the public and sub-contractors.
•It is the responsibility of me to make sure that the deadline for completing work is met, and at least share some of the responsibility if someone on our site has an accident.
•Make sure that all the activities which done are inspected by our QAQC and client and to make sure that whole the team following the QAQC regulation.

Construction manager (|Civil ) في Qatar petroleum EIMSAEID
  • إلى

3 PCR project ( installation of new DCS panel including all the related work CIVIL, instrumentation, electrical )

•Scope includes Field civil work trenching for almost 3.5 KM including sand bidding and backfilling and making of 4 Duct bank for laying the instrument cable in
•My responsibility for a whole site with a strong plan, I’m responsible for part of a project and report to a more senior manager, who may be taking care of several projects at the same time.
•Before work starts, I get things ready by taking on staff, and preparing the site, carefully planning the work to be done and installing temporary offices for site staff.
•While work is taking place, I’m monitoring progress, oversee delivery of materials and carry out safety checks and sort out any problems which could hold up work as they arise. I’m also keeping in close contact with members of their site team at all times, and liaise with architects, engineers, surveyors and planners. I will also ensure that work complies with building regulations and health and safety legislation as well as other legal requirements.
•I’m also keeping the client updated regularly on progress. Finally, I’m also acts as the first point of contact for members of the public and sub-contractors.
•It is the responsibility of me to make sure that the deadline for completing work is met, and at least share some of the responsibility if someone on our site has an accident.
•Make sure that all the activities which done are inspected by our QAQC and client and to make sure that whole the team following the QAQC regulation.

Construction Manager في TADMUR CONTRACTING & TRADING EST
  • قطر
  • إلى

Construction of storm water tank and the pumping system



•Scope includes build new concrete storm water tank and foundation with shelter for the filter and making of 2 nos of pump foundation and 34 pipe support
•Procurement, installation and commissioning of new pumping system
•piping fabrication and installation works
•My responsibility for a whole site with a strong plan, I’m responsible for part of a project and report to a more senior manager, who may be taking care of several projects at the same time.
•Before work starts, I get things ready by taking on staff, and preparing the site, carefully planning the work to be done and installing temporary offices for site staff.
•While work is taking place, I’m monitoring progress, oversee delivery of materials and carry out safety checks and sort out any problems which could hold up work as they arise. I’m also keeping in close contact with members of their site team at all times, and liaise with architects, engineers, surveyors and planners. I will also ensure that work complies with building regulations and health and safety legislation as well as other legal requirements.
•I’m also keeping the client updated regularly on progress. Finally, I’m also acts as the first point of contact for members of the public and sub-contractors.
•It is the responsibility of me to make sure that the deadline for completing work is met, and at least share some of the responsibility if someone on our site has an accident.
•Make sure that all the activities which done are inspected by our QAQC and client and to make sure that whole the team following the QAQC regulation.

الخلفية التعليمية

بكالوريوس, Electrical
  • في El-Kobbe Technical College
  • يناير 2007

courses: H2S BA training …………………………………………..2012 •OSHA 18001 awareness training………..……………..2010 • ISO 14001-2004 awareness training ...………………

بكالوريوس, Electrical
  • في El-Kobbe Technical College
  • يناير 2007

courses: H2S BA training …………………………………………..2012 •OSHA 18001 awareness training………..……………..2010 • ISO 14001-2004 awareness training ...………………

بكالوريوس, Electrical
  • في El-Kobbe Technical College
  • يناير 2007

courses: H2S BA training …………………………………………..2012 •OSHA 18001 awareness training………..……………..2010 • ISO 14001-2004 awareness training ...………………

Specialties & Skills

BILLING
CABLING
CUSTOMER RELATIONS
DELIVERY
ENGINEERING
MATERIALS MANAGEMENT
PERSONNEL
PROGRESS
TECHNICAL SUPPORT

اللغات

العربية
متمرّس
الانجليزية
متمرّس