Project Construction Manager à Combined Group Contracting
  • Émirats Arabes Unis - Dubaï
  • Je travaille ici depuis octobre 2016

1) Residential Compound 410 Houses.

Construction, Completion and Maintenance of 410 Houses including
Related Infrastructure and Road Works. In addition to (04) Mosques,
(06) Commercial Retail Buildings, (13) Parks and (13) Sub-Stations.

Client : Abu Dhabi Housing Authority.
Employer : Musanada, Abu Dhabi General Services Company.
Consultant : Dorsch Gruppe DC Abu Dhabi.
Contractor : Combined Group Contracting Co.
Contract Value : AED 1, 264, 000, 000 / U.S Dollar 346, 000, 000


2) Residential Compound 232 Houses.

Construction Completion and Maintenance of Residential
Compound 232 Houses.

Client : Shiekh Zayed Housing Programme
Consultant : Al Suweidi Engineering
Contractor : Combined Group Contracting
Contract Value : U.A.E.AED 324, 000, 000/ U.S Dollar 89, 000, 000

Construction manager à Detech Contracting Company
  • Émirats Arabes Unis - Dubaï
  • janvier 2014 à octobre 2016

1. Jebel Ali Hills (Roads & Infrastructure) Package-04.
Including (Telecom Duct Works, Irrigation Works, Fire Fighting Works, Drainage Works, Sanitary Sewer Works, Sewer Rising Main and Sewer Pump Station).
Client : MERRAS
Consultant : Parsons Overseas limited
Contractor : Ghantoot Road Contracting
Contract Value : U.A.E.AED 160, 000, 000/ U.S Dollar 44, 000, 000



2-Asset Enhancement Scheme, Stage 1 in Abu Dhabi, Area 2 Construction of Deep trunk Sewer from MPS 14 TO MPS 8 including Interception of Sewers and Abandonment of Existing pump Stations.

In this project we have done one of the Biggest Pump Station (MPS8N) in the Middle East in which the Depth of excavation more than 40 meter and the Diameter 42 meter, Raft thickness reached to 4.6 meter in addition the walls thickness varies from 2.9 meter to 1.5 meter it was really a big challenge to manage and construct such project.

Client : Abu Dhabi Sewerage Services Company (ADSSC)
Consultant : Montgomery Watson Harza (MWH UK Ltd.)
Contractor : Detech Contracting Company
Contract Value : U.A.E. AED 800, 000, 000
U.S Dollar 218, 000, 000

Sr.Project Engineer à Ghantoot Group
  • Émirats Arabes Unis - Abu Dhabi
  • octobre 2010 à janvier 2014

1. The Presidential Palace Project .

Successfully participated in the construction one of Mega Project in the world THE PRESIDENTIAL PALACE under the JV (Joint Venture) of Consolidated Contractor Company CCC & Ghantoot Group with total budget of approximately 12 Billion's AED.



Client : Government of the U.A.E. - Ministry of Presidential Affairs
Client Representative : Executive Committee For The Presidential Palace Project
Project Manager : Armstrong
Lead Consultant : EWAN
Cost Consultant : HAJ Gulf
Contract Value : U.A.E. AED 12, 000, 000, 000
U.S Dollar 03, 300, 000, 000


2. Abu Dhabi Future School Program Phase 4 Package 5

Client : ADEC Abu Dhabi Education Council
Employer : Musanada, Abu Dhabi General Services Company
PMC : Projacs International
Consultant : KEO International Consultants
Contractor : Ghantoot Group
Contract Value : AED 120, 000, 000/ U.S Dollar 33, 000, 000

Project Engineer à Emirates Link Maltouro
  • Émirats Arabes Unis - Abu Dhabi
  • septembre 2007 à octobre 2010

1).H.H. SHK. Saif Bin Zayed Al Nahayan Tower
Commercial Building has 3 basement floors + ground floor
+ Mezzanine floor + 19 floors + Roof level

Client : Privet Office H.H. SHK. Saif Bin Zayed Al Nahayan
Consultant : Heberger Engineering
Contractor : Emirates Link Maltouro
Contract Value : U.A.E. AED 71, 000, 000
U.S Dollar 19, 400, 000


2).BLOOM Gardens - Villas & Townhouses

The Bloom Gardens is low-rise residential development consisting of 123 villas and Townhouses.

Client : Bloom Properties
Consultant : World Planners.
Contractor : Emirates Link Maltouro
Contract Value : U.A.E. AED 262, 000, 000
U.S Dollar 71, 400, 000

Site Engineer à Gulf Contractors Company
  • Émirats Arabes Unis - Abu Dhabi
  • septembre 2005 à septembre 2007

1) ADDC H.Q Building & Multistory Garage - Abu Dhabi.

Client : Abu Dhabi Water & Electricity Authority
Consultant : Architecture and Planning Group
Contractor : Gulf Contractors Company
Contract Value : U.A.E. AED 45, 000, 000
U.S Dollar 12, 300, 000

2) Primary Health Care Center Clinics - Abu Dhabi.

Client : General Authority for Health Services of Abu Dhabi.
Consultant : Hospital Designer and Planner H.D.P (Overseas) Ltd
Contractor : Gulf Contractors Company
Contract Value : U.A.E. AED. 39, 000, 000
U.S Dollar 10, 600, 000

Éducation

Baccalauréat, Civil Engineering
  • à Near East University of Cyprus
  • juin 2005

• B.Sc. in Civil Engineering from the Near East University , Cyprus in June 2005

Specialties & Skills

Construction Management
Cost Control
Planning
Project Management
CIVIL ENGINEER
COMMERCIAL BUILDINGS
CONSTRUCTION PRACTICES
CONTRACTS
SAFETY & QUALITY MANAGEMENT
PROBLEM SOLVING
PUMP STATIONS
PLANNING
PROJECT MANAGEMENT
ROADS & INFRASTRUCTURE
MOTIVATE PROJECT TEAM
TOWN HOUSES & VILLAS
SITE MONITORING
TECHNICAL COORDINATION
HIGH RISE TOWERS
DECISION MAKING
PRESIDENTIAL PALACE

Profils Sociaux

Site Web Personnel
Site Web Personnel

Le lien a été supprimé pour non-respect des conditions d'utilisation. Veuillez contacter l’équipe d'assistance pour plus d'informations.

Langues

Arabe
Langue Maternelle
Anglais
Expert
Turc
Moyen

Adhésions

of UAE Society of Engineers
  • Member
  • February 2008

Formation et Diplômes

PMP Professional Project Management Program (Certificat)
Date de la formation:
February 2018
Valide jusqu'à:
March 2018
FIDIC Contracts 99 (Red Book) (Certificat)
Date de la formation:
April 2008
Valide jusqu'à:
April 2008
Project Management Scheduling , (Primavera version 6) (Certificat)
Date de la formation:
November 2008
Valide jusqu'à:
November 2008
Building Construction, High –Rises (Certificat)
Date de la formation:
May 2012
Valide jusqu'à:
May 2012
Resource Management , (Primavera version6) (Certificat)
Date de la formation:
November 2008
Valide jusqu'à:
November 2008